Niagara Region Wind Farm
Mountainview Road Construction Overview
November 25, 2015
Wind Farm Mountainview Road Construction Overview November 25, - - PowerPoint PPT Presentation
Niagara Region Wind Farm Mountainview Road Construction Overview November 25, 2015 Agenda 1. Introduction to Project Parties 2. Transmission Line Route Overview 3. Mountainview Road Construction Plan Overview 4. Mountainview Road
Mountainview Road Construction Overview
November 25, 2015
Agenda
FWRN LP
Proj
Owners Win ind Farm arm Con Contractor Transmis issio ion Lin Line Con Contractor
sections, including the length of Mountainview Road
Duct Banks & Junction Boxes
Du Duct Ban ank: buried underground transmission line
Duct Banks & Junction Boxes
Jun Junction Box: buried vault where cables are spliced together
Width: 3.65 metres Length: 9.00 metres Depth: 2.60 metres
Duct Bank Installation Process Summary
Process a) Cut and dispose asphalt road surface b) Mobilize to site (inc. set up of traffic barrels & signs) c) Excavator digs out trench area (5 – 6m at a time) d) Install conduit, spacers and rebar e) Pour concrete over conduit f) Backfill trench Road to be resurfaced in Spring.
Duct Bank Installation Overview
Vault Installation Process Summary
Proc
a) Cut and dispose asphalt road surface b) Mobilize to site (inc. set up of traffic barrels & signs) c) Excavator digs out vault pit d) Placement of shoring box e) Install vault & lid f) Backfill around vault N.B .B. Cab able le ins nstalla latio ion will ll tak ake pla place aft fter du duct t ban bank and and vau ault lt ins nstall llatio ions ar are com
lete and and will ll req equir ire rem emoval of
ault lids.
Vault Installation Overview
Crane Hole & Vault Excavator Dump Truck
Dust & Noise Control
Du Dust Con
No Nois ise Con
l Measures
Acti ctivity Tim ime Per erio iod Mountainvie iew Roa
Duct Ban Bank Ins Install llation (N (North to to So South)
January
January – February
January – February
January – February
February
February
February – March
February – March
Average du duct ba bank install llation rate is s 100 100 – 150 150m pe per da day. Du Duct ct ba bank installation wi will ll req equire lane closures s on
ly.
Duct Bank
Vaults
Acti ctivity Tim ime Per erio iod Mountainvie iew Roa
Installa lation (N (North to to So South)
January 5 – 7
January 11 – 13
January 18 – 20
January 25 – 27
February 1 – 3
February 8 – 10
February 15 – 17
February 22 – 24
Vault installation wi will req equire de detours of
non-local l tr traffic. c.
Vault 1 detour
Mountainview Road Greenlane South Service Road
Vault 2 detour
Mountainview Road King Street Greenlane
Vault 3 detour
Mountainview Road
Vault 4 detour
Mountainview Road King Street McLeod Street
Vault 5 detour
Mountainview Road McLeod Street Locust Lane
Vault 6 detour
Mountainview Road McLeod Street Locust Lane
Vault 7 detour
Mountainview Road King Street Thirty Road Walker Road
Vault 8 detour
Mountainview Road Walker Road
Lane Closures (1 of 15)
Mountainview Road
Lane Closures (2 of 15)
Mountainview Road
Lane Closures (3 of 15)
Mountainview Road
Lane Closures (4 of 15)
Mountainview Road
Lane Closures (5 of 15)
Mountainview Road King Street
Lane Closures (6 of 15)
Mountainview Road King Street
Lane Closures (7 of 15)
Mountainview Road King Street McLeod Street
Lane Closures (8 of 15)
Mountainview Road McLeod Street
Lane Closures (9 of 15)
Mountainview Road McLeod Street
Lane Closures (10 of 15)
Locust Lane Konkle Road Mountainview Road
Lane Closures (11 of 15)
Konkle Road Mountainview Road
Lane Closures (12 of 15)
Konkle Road Mountainview Road
Lane Closures (13 of 15)
Konkle Road Mountainview Road Walker Road
Lane Closures (14 of 15)
Mountainview Road Walker Road
Lane Closures (15 of 15)
Walker Road
Appendix
Cable Installation