Wind Farm Mountainview Road Construction Overview November 25, - - PowerPoint PPT Presentation

wind farm
SMART_READER_LITE
LIVE PREVIEW

Wind Farm Mountainview Road Construction Overview November 25, - - PowerPoint PPT Presentation

Niagara Region Wind Farm Mountainview Road Construction Overview November 25, 2015 Agenda 1. Introduction to Project Parties 2. Transmission Line Route Overview 3. Mountainview Road Construction Plan Overview 4. Mountainview Road


slide-1
SLIDE 1

Niagara Region Wind Farm

Mountainview Road Construction Overview

November 25, 2015

slide-2
SLIDE 2

Agenda

  • 1. Introduction to Project Parties
  • 2. Transmission Line Route Overview
  • 3. Mountainview Road Construction Plan Overview
  • 4. Mountainview Road Construction Schedule Overview
  • 5. Detours & Traffic Management Overview
  • 6. Q&A
slide-3
SLIDE 3
  • 1. Introduction to Project Parties

FWRN LP

Proj

  • ject Ow

Owners Win ind Farm arm Con Contractor Transmis issio ion Lin Line Con Contractor

slide-4
SLIDE 4
  • 2. Transmission Line Route Overview
  • About 40km long
  • 289 poles
  • Six underground

sections, including the length of Mountainview Road

slide-5
SLIDE 5
  • 3. Construction Plan Overview

Duct Banks & Junction Boxes

Du Duct Ban ank: buried underground transmission line

slide-6
SLIDE 6
  • 3. Construction Plan Overview

Duct Banks & Junction Boxes

Jun Junction Box: buried vault where cables are spliced together

Width: 3.65 metres Length: 9.00 metres Depth: 2.60 metres

slide-7
SLIDE 7
  • 3. Construction Plan Overview

Duct Bank Installation Process Summary

Process a) Cut and dispose asphalt road surface b) Mobilize to site (inc. set up of traffic barrels & signs) c) Excavator digs out trench area (5 – 6m at a time) d) Install conduit, spacers and rebar e) Pour concrete over conduit f) Backfill trench Road to be resurfaced in Spring.

slide-8
SLIDE 8
  • 3. Construction Plan Overview

Duct Bank Installation Overview

slide-9
SLIDE 9
  • 3. Construction Plan Overview

Vault Installation Process Summary

Proc

  • cess

a) Cut and dispose asphalt road surface b) Mobilize to site (inc. set up of traffic barrels & signs) c) Excavator digs out vault pit d) Placement of shoring box e) Install vault & lid f) Backfill around vault N.B .B. Cab able le ins nstalla latio ion will ll tak ake pla place aft fter du duct t ban bank and and vau ault lt ins nstall llatio ions ar are com

  • mple

lete and and will ll req equir ire rem emoval of

  • f vaul

ault lids.

slide-10
SLIDE 10
  • 3. Construction Plan Overview

Vault Installation Overview

Crane Hole & Vault Excavator Dump Truck

slide-11
SLIDE 11
  • 3. Construction Plan Overview

Dust & Noise Control

Du Dust Con

  • ntrol Measures
  • Water trucks (hazard potential – ice forming)
  • Calcium chloride
  • Light brine solution
  • Street brushes
  • Proper housekeeping

No Nois ise Con

  • ntrol

l Measures

  • Work within allowed hours
  • Noise awareness training
slide-12
SLIDE 12

Acti ctivity Tim ime Per erio iod Mountainvie iew Roa

  • ad Du

Duct Ban Bank Ins Install llation (N (North to to So South)

  • Interconnect to north of Greenlane Rd

January

  • North of Greenlane Rd to north of King St

January – February

  • North of King St to north of McLeod St

January – February

  • North of McLeod St to south of McLeod St

January – February

  • South of McLeod to north of Locust Ln

February

  • North of Locust Ln to east of Konkle Rd

February

  • East of Konkle Rd to Walker Rd (south of Mountainview Rd)

February – March

  • Walker Rd

February – March

Average du duct ba bank install llation rate is s 100 100 – 150 150m pe per da day. Du Duct ct ba bank installation wi will ll req equire lane closures s on

  • nly

ly.

  • 4. Construction Schedule Overview

Duct Bank

slide-13
SLIDE 13
  • 4. Construction Schedule Overview

Vaults

Acti ctivity Tim ime Per erio iod Mountainvie iew Roa

  • ad Vault Ins

Installa lation (N (North to to So South)

  • Vault 1 (south of 4621 Mountainview Rd)

January 5 – 7

  • Vault 2 (in front of 4514 Mountainview Rd)

January 11 – 13

  • Vault 3 (north of 4382 Mountainview Rd

January 18 – 20

  • Vault 4 (in front of 4282 Mountainview Rd)

January 25 – 27

  • Vault 5 (south of corner of Mountainview & McLeod)

February 1 – 3

  • Vault 6 (in front of 4056 Mountainview Rd)

February 8 – 10

  • Vault 7 (between 3994 and 3980 Mountainview Rd)

February 15 – 17

  • Vault 8 (south of 3994 Walker Rd)

February 22 – 24

Vault installation wi will req equire de detours of

  • f no

non-local l tr traffic. c.

slide-14
SLIDE 14
  • 5. Detours & Traffic Management

Vault 1 detour

Mountainview Road Greenlane South Service Road

slide-15
SLIDE 15
  • 5. Detours & Traffic Management

Vault 2 detour

Mountainview Road King Street Greenlane

slide-16
SLIDE 16
  • 5. Detours & Traffic Management

Vault 3 detour

Mountainview Road

slide-17
SLIDE 17
  • 5. Detours & Traffic Management

Vault 4 detour

Mountainview Road King Street McLeod Street

slide-18
SLIDE 18
  • 5. Detours & Traffic Management

Vault 5 detour

Mountainview Road McLeod Street Locust Lane

slide-19
SLIDE 19
  • 5. Detours & Traffic Management

Vault 6 detour

Mountainview Road McLeod Street Locust Lane

slide-20
SLIDE 20
  • 5. Detours & Traffic Management

Vault 7 detour

Mountainview Road King Street Thirty Road Walker Road

slide-21
SLIDE 21
  • 5. Detours & Traffic Management

Vault 8 detour

Mountainview Road Walker Road

slide-22
SLIDE 22
  • 5. Detours & Traffic Management

Lane Closures (1 of 15)

Mountainview Road

slide-23
SLIDE 23
  • 5. Detours & Traffic Management

Lane Closures (2 of 15)

Mountainview Road

slide-24
SLIDE 24
  • 5. Detours & Traffic Management

Lane Closures (3 of 15)

Mountainview Road

slide-25
SLIDE 25
  • 5. Detours & Traffic Management

Lane Closures (4 of 15)

Mountainview Road

slide-26
SLIDE 26
  • 5. Detours & Traffic Management

Lane Closures (5 of 15)

Mountainview Road King Street

slide-27
SLIDE 27
  • 5. Detours & Traffic Management

Lane Closures (6 of 15)

Mountainview Road King Street

slide-28
SLIDE 28
  • 5. Detours & Traffic Management

Lane Closures (7 of 15)

Mountainview Road King Street McLeod Street

slide-29
SLIDE 29
  • 5. Detours & Traffic Management

Lane Closures (8 of 15)

Mountainview Road McLeod Street

slide-30
SLIDE 30
  • 5. Detours & Traffic Management

Lane Closures (9 of 15)

Mountainview Road McLeod Street

slide-31
SLIDE 31
  • 5. Detours & Traffic Management

Lane Closures (10 of 15)

Locust Lane Konkle Road Mountainview Road

slide-32
SLIDE 32
  • 5. Detours & Traffic Management

Lane Closures (11 of 15)

Konkle Road Mountainview Road

slide-33
SLIDE 33
  • 5. Detours & Traffic Management

Lane Closures (12 of 15)

Konkle Road Mountainview Road

slide-34
SLIDE 34
  • 5. Detours & Traffic Management

Lane Closures (13 of 15)

Konkle Road Mountainview Road Walker Road

slide-35
SLIDE 35
  • 5. Detours & Traffic Management

Lane Closures (14 of 15)

Mountainview Road Walker Road

slide-36
SLIDE 36
  • 5. Detours & Traffic Management

Lane Closures (15 of 15)

Walker Road

slide-37
SLIDE 37

Q & A

slide-38
SLIDE 38

Appendix

Cable Installation