West Trail Living Shoreline Project Progress Update San Mateo - - PowerPoint PPT Presentation

west trail living shoreline project progress update
SMART_READER_LITE
LIVE PREVIEW

West Trail Living Shoreline Project Progress Update San Mateo - - PowerPoint PPT Presentation

West Trail Living Shoreline Project Progress Update San Mateo County Harbor District Board of Harbor Commissioners Meeting August 2020 Progress Data Concept Engineering Permitting Construction Collection Design (Fall / Winter 2020)


slide-1
SLIDE 1

West Trail Living Shoreline Project Progress Update

San Mateo County Harbor District Board of Harbor Commissioners Meeting August 2020

slide-2
SLIDE 2

Progress Permitting Engineering Concept Design Data Collection Construction

DRAFT FINAL PLANS, SPECS & ESTIMATE (August 2020) SUBMITTED (July 2020) (Fall / Winter 2020)

slide-3
SLIDE 3

Shoreline Protection – Design Goals

  • Protect trail from chronic erosion
  • Use nature-based techniques, minimize hardscape
  • Accommodate sea level rise
slide-4
SLIDE 4

Stormwater Improvements – Design Goals

  • Improve aesthetics and function
  • Water quality and ecological enhancements
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7

SHORELINE PROTECTION

slide-8
SLIDE 8

(Photo: SMCHD 2020)

slide-9
SLIDE 9

LIVING SHORELINE & TRAIL – PLAN VIEW

Rock Fingers Dune Beach Cobble Berm

slide-10
SLIDE 10

LIVING SHORELINE & TRAIL – TYPICAL SECTION

slide-11
SLIDE 11

Surfer’s Point, Ventura, CA

March 2016 November 2017

Mixed Sand / Cobble Beach Analog

slide-12
SLIDE 12

SAND SOURCES Need = 7,000 CY Sources:

  • Overwash Shoal – 5,400 CY
  • Airport Stockpile – 1,600 CY
slide-13
SLIDE 13

ROCK SOURCES

  • 1-4” Rock - Need 4,500 CY
  • 4-10 Ton Rock – Need 500

CY Source: Re-use and Quarry

slide-14
SLIDE 14

STORMWATER IMPROVEMENTS

slide-15
SLIDE 15
slide-16
SLIDE 16

Drainage Basin Remove Existing Outfall Improve Ex. Stormdrain Bury Pipe

slide-17
SLIDE 17

Rock-lined Channel Check Dam

slide-18
SLIDE 18

Construction Schedule

SMCHD Board of Harbor Commissioners Meeting

slide-19
SLIDE 19

Construction & Monitoring – Anticipated Costs Hard costs:

  • ~$2.0M with 20% Contingency
  • Native Planting & Maintenance

Soft costs:

  • Restoration plan
  • Construction management
  • Biological monitoring
  • Eelgrass
  • Listed species
  • Physical monitoring
  • Renourishment?
slide-20
SLIDE 20

CONSTRUCTION DETAILS

  • Import of Sand & Gravel
  • West Point Parking Lot
  • Night work requested to

Minimize Impacts

slide-21
SLIDE 21

Grants & Permitting

SMCHD Board of Harbor Commissioners Meeting

slide-22
SLIDE 22

Grant Funding Investigations

  • Grant opportunities were researched and explored throughout Project planning.
  • National Fish and Wildlife Foundation Grant applied for, late 2019.
  • Honda Foundation Grant.

SMCHD Board of Harbor Commissioners Meeting

slide-23
SLIDE 23

Permitting and Agency Consultation

Multiple Permits Required:

  • U.S. Army Corps of Engineers—Individual Permit CWA Section 404; RHA

Section 10.

  • Regional Water Quality Control Board—Section 401 Water Quality

Certification/Waste Discharge Requirement.

  • Coastal Commission/County—Consolidated Coastal Development Permit.

Consultations: U.S. EPA; NOAA Fisheries (NMFS); Cal Department of Fish and Wildlife

SMCHD Board of Harbor Commissioners Meeting

slide-24
SLIDE 24

Permitting and Environmental Approvals

  • CEQA Draft MND - Public comment thru August 21
  • Permitting
  • Applications submitted in July 2020, currently under review by

agencies.

  • Anticipate permits by Fall 2020.
  • Monitoring and reporting required during and after construction.

SMCHD Board of Harbor Commissioners Meeting

slide-25
SLIDE 25

Next Steps

  • Bidding Process – 40 days (October 2020)
  • CEQA & Permits (Fall 2020)
  • Mobilization – 14 days (November 2020)
  • Construction – 120 days (March 2021

completion)

  • Dune and Biofiltration planting (Spring 2021)

SMCHD Board of Harbor Commissioners Meeting

slide-26
SLIDE 26

www.ghd.com