CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD SEWER UPGRADING PROJECT July 7, 2015 WELCOME TO THE INFORMATION SESSION CITY OF EDMONTON: ASPEN GARDENS, Project Overview: ROYAL GARDENS and GREENFIELD - What Are The Benef ts


slide-1
SLIDE 1

WELCOME TO THE INFORMATION SESSION

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD

SEWER UPGRADING PROJECT

July 7, 2015

slide-2
SLIDE 2
  • REDUCE RISK OF

BASEMENT FLOODING DUE TO SEWER BACKUP

  • PROVIDE A HIGHER LEVEL

OF SANITARY SERVICE

Project Overview

Project Overview: What Are The Benef ts

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

THE CITY OF EDMONTON IS UPGRADING THE SANITARY SEWER SYSTEM IN THESE NEIGHBORHOODS TO:

W E S T B R O O K L I F T S T A T I O N

DERRICK GOLF & WINTER CLUB

WHITEMUD DRIVE

ASPEN GARDENS ROYAL GARDENS GREENFIELD

119 STREET

SWEETGRASS

111 STREET 40 AVENUE 34 AVENUE

WESTBROOK ESTATES

W H I T E M U D D R I V E
  • ST. BONIFACE
CATHOLIC SCHOOL WESTBROOK SCHOOL VERNON BARFORD
  • JR. HIGH
F A I R W A Y D R . W E S T B R O O K D R . 114 STREET 37 AVENUE 117 STREET 38 AVENUE 37A AVENUE 39A AVENUE 41 AVENUE 117 STREET 3 7 A V E N U E F A I R W A Y D R . 3 9 A V E N U E ASPEN DR. WEST A S P E N D R . E A S T 4 1 A A V E N U E 121 STREET 1 2 2 S T R E E T 123 STREET 4 2 A V E N U E 119 STREET

WESTBROOK SCHOOL

slide-3
SLIDE 3

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

Design: Aspen Gardens

Aspen Gardens - Proposed Sanitary Sewer Upgrades

750 LENGTH = 810 M

slide-4
SLIDE 4

Aspen Gardens - Proposed Sanitary Sewer Upgrades

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

Design: Aspen Gardens

LENGTH = 20 M

slide-5
SLIDE 5

Design: Royal Gardens

Royal Gardens - Proposed Sanitary Sewer Upgrades

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

LENGTH = 260 M

slide-6
SLIDE 6

Design: Greenf

eld

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

Greenfi eld - Proposed Sanitary Sewer Upgrades

LENGTH = 810 M

slide-7
SLIDE 7

Aspen Gardens

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

City of Edmonton Construction: Start Date: May 2015 End Date: Spring 2016

LEGEND:

  • ---- SEWER UPGRADES

O CONSTRUCTION SHAFT

Construction Schedule External Contractor Construction External Contractor Construction: Start Date: Spring 2016 End Date: Fall 2016 Spring 2016 Fall 2016

slide-8
SLIDE 8

Location: Royal Gardens

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

Construction Schedule

LEGEND:

  • ---- SEWER UPGRADES

External Contractor Construction: Start Date: July 2015 End Date: August 2015 July 2015 August 2015

slide-9
SLIDE 9

Location: Greenf eld

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

Construction Schedule

LEGEND:

  • ---- SEWER UPGRADES

External Contractor Construction: Start Date: August 2015 End Date: Fall 2015 August 2015 F a l l 2 1 5

slide-10
SLIDE 10

Project Overview: Where are we today?

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD - SANITARY SEWER UPGRADING PROJECT

slide-11
SLIDE 11

THANK YOU

CITY OF EDMONTON: ASPEN GARDENS, ROYAL GARDENS and GREENFIELD

SEWER UPGRADING PROJECT

July 7, 2015

Thank you for taking the time to review the Aspen Gardens, Royal Gardens and Greenfi eld Sewer Upgrading project details. Please fi ll out the Participant Survey Form before you leave.

PROJECT CONTACT: CITY OF EDMONTON Max Mao, M.Sc., P.Eng., PMP 780.944.0033