SLIDE 1
WELCOME TO THE 2019 FURRY CREEK HOLIDAY RECEPTION! From last years - - PowerPoint PPT Presentation
WELCOME TO THE 2019 FURRY CREEK HOLIDAY RECEPTION! From last years - - PowerPoint PPT Presentation
WELCOME TO THE 2019 FURRY CREEK HOLIDAY RECEPTION! From last years reception. Dont be fooled by the sad expressions. Everyone really enjoyed Valeries remarks and the food! Dillon is always making notes. But we never see them! Yang is
SLIDE 2
SLIDE 3
SLIDE 4
Yang is thinking: I wish Michael didn’t speak so much! Dillon is always making notes. But we never see them!
SLIDE 5
We are pleased to share an update on our rezoning application and other activities in the community over the past year
SLIDE 6
As you may have noticed, while the Clubhouse renovations have been progressing nicely, not everything is completely finished!
SLIDE 7
In January, the architects and engineer went to China to visit Fine Peace golf course communities
Denis Arseneau Michael Geller Kevin Healy Derek Neale
SLIDE 8
In March we submitted our rezoning application which has been subsequently updated
SLIDE 9
In May we were pleased to attend the FCCA AGM
SLIDE 10
Although some of us get a bit nervous when the police are in the room!
SLIDE 11
Also in May we appreciated the opportunity to show SLRD staff around the community
SLIDE 12
On Friday September 13th we signed an agreement in principle with Oliver’s Landing Strata Corporation regarding the future of the Recreation Centre and related matters which will hopefully be approved by the residents in early 2020
SLIDE 13
In October we were pleased to give a tour to some of the SLRD Board Directors
SLIDE 14
During the year we spent considerable time reviewing and revising our plans
SLIDE 15
For the past 2 years, our plans included replacing Lot 2 townhouses with six terraced buildings ranging in height from 6 to 12 storeys
SLIDE 16
After Fine Peace acquired the ‘Uplands’ we also proposed relocation
- f the Village Centre from Lot 4 to a more central and viable location
SLIDE 17
Proposed Community & Village Centre
(as per rezoning report and submission)
Plans included one and two-storey buildings
A COMMUNITY HEART It is proposed that the primary neighbourhood commercial area be relocated from Lot 4 to a new location that would be more accessible to the broader community. It might also be desirable to relocate the proposed community centre to an adjacent site combined with a short pedestrian street and public square that would become the ‘heart’ of the Furry Creek community.
SLIDE 18
Lot 2 development
Village Centre Ocean Crest
While most residents have generally applauded these changes, some residents, including the Ocean Crest Strata expressed several concerns
SLIDE 19
- 1. Relocation of village and community centre
- 2. View impacts of buildings along waterfront
Some felt relocation of Village Centre was done
without adequate community-wide consultation
The minor intrusion into golf course sets a dangerous
precedent
Village Centre will have negative impacts in terms of
noise, fumes and reduced property values
Plan could result in excessive paved parking areas
and potential traffic accidents
Proposed Lot 2 development, especially 12 storey
‘signature building’, will be very visible and block views
SLIDE 20
Aerial view looking west at revised scheme with its green roofs and reduced parking area
- Surface parking has been
reduced; parking placed underground; loading dock screened
- Now single level buildings along
Furry Creek Drive with sloping green roofs
- Outdoor patios limited to
- west side of buildings
- Intrusion into golf course
- reduced. 3rd hole tee box now
located on roof
- Mechanical equipment
- screened. Service lane between
buildings eliminated
To address these residents’ concerns regarding the Community and Village Centre, several changes are proposed
SLIDE 21
Revised plans: Note: relocation of Community Centre will require approval from Provincial Government
SLIDE 22
SLIDE 23
SLIDE 24
SLIDE 25
View looking south-west over community centre and entry to underground parking
SLIDE 26
Aerial view looking north at single storey structures with sloping green roofs and 3rd hole tee box now on roof of building
3rd hole tee box
SLIDE 27
At our 2018 community presentation, we committed to undertake more detailed view impact analyses of Lot 2 for both existing residents, golfers and those driving highway
SLIDE 28
Last year’s plan with 6 apartment buildings with heights terracing from north to south 6 to 12 storeys, improved floodproofing and more open space
SLIDE 29
Site section showing the grade elevation of some existing houses along Ocean Crest
- Dr. at 56 m. The proposed roof elevation for a 12-floor building at 48 m +/-
SLIDE 30
Aerial of last year’s scheme looking south-east
BEFORE 8 storeys 10 storeys 10 storeys 12 storeys
SLIDE 31
View of 12 storey ‘signature building’ over 14th hole
BEFORE
SLIDE 32
BEFORE
SLIDE 33
Potential view impacts from 12 storey building overlooking 14th hole for some existing Uplands residents based on original scheme
BEFORE
SLIDE 34
Given concerns of Ocean Crest and other residents about taller buildings, we photographed balloons at proposed building locations and heights
SLIDE 35
View impact studies were carried out for all the properties along Ocean Crest
SLIDE 36
Stills and videos were also taken along Stonegate Drive and Furry Creek Drive
SLIDE 37
None of the balloons were visible from this property along Stonegate
SLIDE 38
However balloons (yellow dots) were visible along Ocean Crest Drive
SLIDE 39
SLIDE 40
We looked at potential view impacts from Oliver’s Landing, but there weren’t any
SLIDE 41
We also completed a detailed LiDAR (3D Laser scanning) aerial survey of the property
SLIDE 42
As result of community concerns, balloon photos, and LiDAR survey we decided to reduce height of the ‘signature building’ from 12 storeys to a terraced 4-6 storey building
SLIDE 43
View of revised 6-storey ‘signature building’ looking northeast. The heights of other buildings generally relate to the height of the trees.
SLIDE 44
SLIDE 45
View of revised waterfront development from 400 Ocean Crest
SLIDE 46
View of revised waterfront development from 800 Ocean Crest
SLIDE 47
We hope you agree we have made a sincere effort to address residents’ concerns about any negative impacts of the relocated Village Centre and Lot 2 views
SLIDE 48
We have also studied Public Views: Revised signature building and Lot 2 as viewed from highway driving north
SLIDE 49
View of proposed Lot 2 buildings from highway driving north
SLIDE 50
View of proposed 15 storey buildings in Northwest and Northeast from highway driving north
SLIDE 51
View of proposed 15 storey buildings from highway driving north without trees
SLIDE 52
LiDAR View of proposed 15 storey buildings from highway driving north
SLIDE 53
View of proposed 15 storey buildings from highway driving north
SLIDE 54
View of Lot 2 buildings from highway driving south
SLIDE 55
The zoning bylaw includes an overall plan establishing building heights and densities
SLIDE 56
FORM AND CHARACTER OF PROPOSED BUILDINGS
This new building in British Properties is illustrative of one potential design
To guide design of new buildings, DESIGN GUIDELINES have been prepared as part of zoning
SLIDE 57
Some buildings might have ‘Whistler-like’ rooflines, (although not as large as these)
SLIDE 58
Design Guidelines encourage a variety of other styles with flat and sloping roofs, and natural materials, including stone, wood, concrete and glass
SLIDE 59
Elsewhere in the community, 2 and 3 storey duplexes and townhouses are proposed
SLIDE 60
An example of a 4-storey terraced building with flat roofs included in the Design Guidelines
SLIDE 61
An artist’s illustration of a building designed for the Marina Neighbourhood
SLIDE 62
An artist’s illustration of a 7 storey building proposed within the community
SLIDE 63
Following rezoning, every proposal will go through a separate Development Permit review to ensure conformance with zoning, design guidelines, etc.
SLIDE 64
While seeking approval in principle for taller buildings, it’s on understanding taller buildings will not be approved until necessary fire safety measures, equipment and training in place.
FIRE SAFETY
SLIDE 65
Future Firefighter
A new fire hall is proposed, along with additional specialized equipment and training and agreements with Squamish and Lions Bay Fire Departments
Excerpt from original legal covenant. The cost has increased!
SLIDE 66
Our transportation & civil engineers have confirmed it is feasible and safe to locate new bus stops on both sides of the highway. Discussions are now ongoing with BC Transit to explore the next steps for improved public transit.
PUBLIC TRANSIT
SLIDE 67
RESORT FACILITIES: The plans now include a variety of resort facilities
SLIDE 68
MARINA: We have received approval in principle for a small 20-berth +/- residents’ only private marina north of Oliver’s Landing
SLIDE 69
We continue to address some previously identified community concerns:
- Desire for CN Whistle cessation
- Desire for legal public access to
the beach
- Improvements to the deck at the
end of the spit
- Installation of toilet facilities for
beach users
SLIDE 70
Our landscape architect PWL has developed a plan for a new waterfront park alongside the 14th hole that includes legal public access to the beach and waterfront, children’s play and picnic areas, and a new washroom
SLIDE 71
SLIDE 72
Detailed site and local trail networks are also being developed (thanks 2 Brians!)
SLIDE 73
Roadway sections A variety of roadway sections are designed within the site to respond to the topography and whether there is public or private
- wnership. As
indicated in these sections, the
- bjective is to
minimize the footprint and impact of the road and trail system on the lands.
12.4 ROAD AND TRAIL SECTIONS
SLIDE 74
The community development will be phased over many years
SLIDE 75
Phase 1: Completion of Oliver’s Landing
SLIDE 76
Phase 2: Start on Lot 2 and resort facilities
SLIDE 77
Phase 3: Start on Collector and Marina neighbourhoods and Village Centre. Continuation of Lot 2
SLIDE 78
Phase 4: Start on Northwest neighbourhood. Continuation of Village Centre and Lot 2. Completion of Marina Neighbourhood
SLIDE 79
Phase 5: Start on Uplands South neighbourhood. Continuation of Collector Neighbourhood Completion of Lot 2
SLIDE 80
Phase 6: Start on Uplands North Neighbourhood. Completion of Collector Neighbourhood
SLIDE 81
Phase 7: Start on Upper Benchlands Neighbourhood Continuation of Northwest/Northeast & Uplands North Neighbourhoods
SLIDE 82
Phase 8: Start on Mountain Neighbourhood. Continuation of Upper Benchlands
SLIDE 83
One day it will be all finished!
SLIDE 84
SLRD staff are presenting to SLRD Board on December 19 to seek direction. We are hoping the Board will refer the application, as proposed, to Public Hearing in early 2020 to allow community residents and public to have their say, especially regarding proposal for limited taller buildings over 6 storeys in height
Next steps:
SLIDE 85