WELCOME TO THE 2019 FURRY CREEK HOLIDAY RECEPTION!

slide-2
SLIDE 2

From last year’s reception. Don’t be fooled by the sad expressions. Everyone really enjoyed Valerie’s remarks… and the food!

slide-3
SLIDE 3
slide-4
SLIDE 4

Yang is thinking: I wish Michael didn’t speak so much! Dillon is always making notes. But we never see them!

slide-5
SLIDE 5

We are pleased to share an update on our rezoning application and other activities in the community over the past year

slide-6
SLIDE 6

As you may have noticed, while the Clubhouse renovations have been progressing nicely, not everything is completely finished!

slide-7
SLIDE 7

In January, the architects and engineer went to China to visit Fine Peace golf course communities

Denis Arseneau Michael Geller Kevin Healy Derek Neale

slide-8
SLIDE 8

In March we submitted our rezoning application which has been subsequently updated

slide-9
SLIDE 9

In May we were pleased to attend the FCCA AGM

slide-10
SLIDE 10

Although some of us get a bit nervous when the police are in the room!

slide-11
SLIDE 11

Also in May we appreciated the opportunity to show SLRD staff around the community

slide-12
SLIDE 12

On Friday September 13th we signed an agreement in principle with Oliver’s Landing Strata Corporation regarding the future of the Recreation Centre and related matters which will hopefully be approved by the residents in early 2020

slide-13
SLIDE 13

In October we were pleased to give a tour to some of the SLRD Board Directors

slide-14
SLIDE 14

During the year we spent considerable time reviewing and revising our plans

slide-15
SLIDE 15

For the past 2 years, our plans included replacing Lot 2 townhouses with six terraced buildings ranging in height from 6 to 12 storeys

slide-16
SLIDE 16

After Fine Peace acquired the ‘Uplands’ we also proposed relocation

  • f the Village Centre from Lot 4 to a more central and viable location
slide-17
SLIDE 17

Proposed Community & Village Centre

(as per rezoning report and submission)

Plans included one and two-storey buildings

A COMMUNITY HEART It is proposed that the primary neighbourhood commercial area be relocated from Lot 4 to a new location that would be more accessible to the broader community. It might also be desirable to relocate the proposed community centre to an adjacent site combined with a short pedestrian street and public square that would become the ‘heart’ of the Furry Creek community.

slide-18
SLIDE 18

Lot 2 development

Village Centre Ocean Crest

While most residents have generally applauded these changes, some residents, including the Ocean Crest Strata expressed several concerns

slide-19
SLIDE 19
  • 1. Relocation of village and community centre
  • 2. View impacts of buildings along waterfront

 Some felt relocation of Village Centre was done

without adequate community-wide consultation

 The minor intrusion into golf course sets a dangerous

precedent

 Village Centre will have negative impacts in terms of

noise, fumes and reduced property values

 Plan could result in excessive paved parking areas

and potential traffic accidents

 Proposed Lot 2 development, especially 12 storey

‘signature building’, will be very visible and block views

slide-20
SLIDE 20

Aerial view looking west at revised scheme with its green roofs and reduced parking area

  • Surface parking has been

reduced; parking placed underground; loading dock screened

  • Now single level buildings along

Furry Creek Drive with sloping green roofs

  • Outdoor patios limited to
  • west side of buildings
  • Intrusion into golf course
  • reduced. 3rd hole tee box now

located on roof

  • Mechanical equipment
  • screened. Service lane between

buildings eliminated

To address these residents’ concerns regarding the Community and Village Centre, several changes are proposed

slide-21
SLIDE 21

Revised plans: Note: relocation of Community Centre will require approval from Provincial Government

slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25

View looking south-west over community centre and entry to underground parking

slide-26
SLIDE 26

Aerial view looking north at single storey structures with sloping green roofs and 3rd hole tee box now on roof of building

3rd hole tee box

slide-27
SLIDE 27

At our 2018 community presentation, we committed to undertake more detailed view impact analyses of Lot 2 for both existing residents, golfers and those driving highway

slide-28
SLIDE 28

Last year’s plan with 6 apartment buildings with heights terracing from north to south 6 to 12 storeys, improved floodproofing and more open space

slide-29
SLIDE 29

Site section showing the grade elevation of some existing houses along Ocean Crest

  • Dr. at 56 m. The proposed roof elevation for a 12-floor building at 48 m +/-
slide-30
SLIDE 30

Aerial of last year’s scheme looking south-east

BEFORE 8 storeys 10 storeys 10 storeys 12 storeys

slide-31
SLIDE 31

View of 12 storey ‘signature building’ over 14th hole

BEFORE

slide-32
SLIDE 32

BEFORE

slide-33
SLIDE 33

Potential view impacts from 12 storey building overlooking 14th hole for some existing Uplands residents based on original scheme

BEFORE

slide-34
SLIDE 34

Given concerns of Ocean Crest and other residents about taller buildings, we photographed balloons at proposed building locations and heights

slide-35
SLIDE 35

View impact studies were carried out for all the properties along Ocean Crest

slide-36
SLIDE 36

Stills and videos were also taken along Stonegate Drive and Furry Creek Drive

slide-37
SLIDE 37

None of the balloons were visible from this property along Stonegate

slide-38
SLIDE 38

However balloons (yellow dots) were visible along Ocean Crest Drive

slide-39
SLIDE 39
slide-40
SLIDE 40

We looked at potential view impacts from Oliver’s Landing, but there weren’t any

slide-41
SLIDE 41

We also completed a detailed LiDAR (3D Laser scanning) aerial survey of the property

slide-42
SLIDE 42

As result of community concerns, balloon photos, and LiDAR survey we decided to reduce height of the ‘signature building’ from 12 storeys to a terraced 4-6 storey building

slide-43
SLIDE 43

View of revised 6-storey ‘signature building’ looking northeast. The heights of other buildings generally relate to the height of the trees.

slide-44
SLIDE 44
slide-45
SLIDE 45

View of revised waterfront development from 400 Ocean Crest

slide-46
SLIDE 46

View of revised waterfront development from 800 Ocean Crest

slide-47
SLIDE 47

We hope you agree we have made a sincere effort to address residents’ concerns about any negative impacts of the relocated Village Centre and Lot 2 views

slide-48
SLIDE 48

We have also studied Public Views: Revised signature building and Lot 2 as viewed from highway driving north

slide-49
SLIDE 49

View of proposed Lot 2 buildings from highway driving north

slide-50
SLIDE 50

View of proposed 15 storey buildings in Northwest and Northeast from highway driving north

slide-51
SLIDE 51

View of proposed 15 storey buildings from highway driving north without trees

slide-52
SLIDE 52

LiDAR View of proposed 15 storey buildings from highway driving north

slide-53
SLIDE 53

View of proposed 15 storey buildings from highway driving north

slide-54
SLIDE 54

View of Lot 2 buildings from highway driving south

slide-55
SLIDE 55

The zoning bylaw includes an overall plan establishing building heights and densities

slide-56
SLIDE 56

FORM AND CHARACTER OF PROPOSED BUILDINGS

This new building in British Properties is illustrative of one potential design

To guide design of new buildings, DESIGN GUIDELINES have been prepared as part of zoning

slide-57
SLIDE 57

Some buildings might have ‘Whistler-like’ rooflines, (although not as large as these)

slide-58
SLIDE 58

Design Guidelines encourage a variety of other styles with flat and sloping roofs, and natural materials, including stone, wood, concrete and glass

slide-59
SLIDE 59

Elsewhere in the community, 2 and 3 storey duplexes and townhouses are proposed

slide-60
SLIDE 60

An example of a 4-storey terraced building with flat roofs included in the Design Guidelines

slide-61
SLIDE 61

An artist’s illustration of a building designed for the Marina Neighbourhood

slide-62
SLIDE 62

An artist’s illustration of a 7 storey building proposed within the community

slide-63
SLIDE 63

Following rezoning, every proposal will go through a separate Development Permit review to ensure conformance with zoning, design guidelines, etc.

slide-64
SLIDE 64

While seeking approval in principle for taller buildings, it’s on understanding taller buildings will not be approved until necessary fire safety measures, equipment and training in place.

FIRE SAFETY

slide-65
SLIDE 65

Future Firefighter

A new fire hall is proposed, along with additional specialized equipment and training and agreements with Squamish and Lions Bay Fire Departments

Excerpt from original legal covenant. The cost has increased!

slide-66
SLIDE 66

Our transportation & civil engineers have confirmed it is feasible and safe to locate new bus stops on both sides of the highway. Discussions are now ongoing with BC Transit to explore the next steps for improved public transit.

PUBLIC TRANSIT

slide-67
SLIDE 67

RESORT FACILITIES: The plans now include a variety of resort facilities

slide-68
SLIDE 68

MARINA: We have received approval in principle for a small 20-berth +/- residents’ only private marina north of Oliver’s Landing

slide-69
SLIDE 69

We continue to address some previously identified community concerns:

  • Desire for CN Whistle cessation
  • Desire for legal public access to

the beach

  • Improvements to the deck at the

end of the spit

  • Installation of toilet facilities for

beach users

slide-70
SLIDE 70

Our landscape architect PWL has developed a plan for a new waterfront park alongside the 14th hole that includes legal public access to the beach and waterfront, children’s play and picnic areas, and a new washroom

slide-71
SLIDE 71
slide-72
SLIDE 72

Detailed site and local trail networks are also being developed (thanks 2 Brians!)

slide-73
SLIDE 73

Roadway sections A variety of roadway sections are designed within the site to respond to the topography and whether there is public or private

  • wnership. As

indicated in these sections, the

  • bjective is to

minimize the footprint and impact of the road and trail system on the lands.

12.4 ROAD AND TRAIL SECTIONS

slide-74
SLIDE 74

The community development will be phased over many years

slide-75
SLIDE 75

Phase 1: Completion of Oliver’s Landing

slide-76
SLIDE 76

Phase 2: Start on Lot 2 and resort facilities

slide-77
SLIDE 77

Phase 3: Start on Collector and Marina neighbourhoods and Village Centre. Continuation of Lot 2

slide-78
SLIDE 78

Phase 4: Start on Northwest neighbourhood. Continuation of Village Centre and Lot 2. Completion of Marina Neighbourhood

slide-79
SLIDE 79

Phase 5: Start on Uplands South neighbourhood. Continuation of Collector Neighbourhood Completion of Lot 2

slide-80
SLIDE 80

Phase 6: Start on Uplands North Neighbourhood. Completion of Collector Neighbourhood

slide-81
SLIDE 81

Phase 7: Start on Upper Benchlands Neighbourhood Continuation of Northwest/Northeast & Uplands North Neighbourhoods

slide-82
SLIDE 82

Phase 8: Start on Mountain Neighbourhood. Continuation of Upper Benchlands

slide-83
SLIDE 83

One day it will be all finished!

slide-84
SLIDE 84

SLRD staff are presenting to SLRD Board on December 19 to seek direction. We are hoping the Board will refer the application, as proposed, to Public Hearing in early 2020 to allow community residents and public to have their say, especially regarding proposal for limited taller buildings over 6 storeys in height

Next steps:

slide-85
SLIDE 85

We now welcome your comments, questions, and suggestions