R ANCHO M URIETA C OMMUNITY S ERVICES D ISTRICT Presentation to the Board September 20, 2017 Water Supply Augmentation Fee & Community Facilities Fee Presented by: Presentation Outline Introduction Prior Efforts Existing Fee


  1. R ANCHO M URIETA C OMMUNITY S ERVICES D ISTRICT Presentation to the Board September 20, 2017 Water Supply Augmentation Fee & Community Facilities Fee Presented by:

  2. Presentation Outline • Introduction • Prior Efforts • Existing Fee Account Balances • Administration Capital Fee Distribution • Anticipated Costs • Adjusted Balance Summary • Development Summary • Water Supply Augmentation Projects

  3. Presentation Outline • Proposed Facility Capital Improvement Projects • Administration Capital Improvement Cost Distribution • Dual Benefit Projects • Final Revenue Need Summary • Proposed Fees • Proposed Non-Residential EDU Methodology Change • Next Steps • Questions

  4. Prior Efforts • Water Supply Augmentation CIP Tech Memo o Projects based on Recycled Water Program Preliminary Design Report prepared by Kennedy Jenks • Facilities CIP Tech Memo o Projects based on updating prior District CIP lists • Review and Approve Water Supply Augmentation CIP and Facilities CIP Tech Memos o Improvements Committee – May 2, 2017 o Board of Directors – May 17, 2017 & June 21, 2017

  5. Existing Fee Account Balances • Table 1 – Current Balance Summary Administration Fee Account Cash on Hand Loan Balance Distribution Current Balance Water Supply Augmentation $1,698,790 $382,964 $0 $2,081,754 Water Capital -$245,589 $0 $217,776 -$27,813 Sewer Capital -$49,563 $0 $166,271 $116,708 Drainage Capital $235,171 $65,106 $35,270 $335,547 Security Capital -$136,350 $0 $140,518 $4,168 TOTAL $1,502,459 $448,070 $559,835 $2,510,364 • Cash on hand & loan balances as of May 31, 2017

  6. Administration Capital Improvements Fee Distribution • Per District Audited Financial Statements o Water: 38.9% o Sewer: 29.7% o Drainage: 6.3% o Security: 25.1%

  7. Anticipated Costs • Kennedy Jenks Studies o 100% Water Supply Augmentation Fee • Coastland Fee Study Report o 50% Water Supply Augmentation Fee o 50% Community Facilities Fee o Same percentages as Administration Fee Distribution • Future Fee Study Report o 50% Water Supply Augmentation Fee o 50% Community Facilities Fee o Same percentages as Administration Fee Distribution

  8. Project Cost Estimates • Table 2 – Adjusted Balance Summary Fee Account Current Balance Anticipated Costs Adjusted Balance Water Supply Augmentation $2,081,754 $63,793 $2,017,961 Water Capital -$27,813 $27,436 -$55,249 Sewer Capital $116,708 $20,947 $95,761 Drainage Capital $335,547 $4,443 $331,104 Security Capital $4,168 $17,703 -$13,535 TOTAL $2,510,364 $134,322 $2,436,042

  9. Development Summary • Development Projects & EDU Summary Calculation TM: Appendix B • Summarized in Table 3 • Total Number of EDUs – 1,718.1 • Based on o Known Development Projects o Parks o Others

  10. Water Supply Augmentation Projects • Water Supply Augmentation Project – Recycled Water Program TM: Appendix C • Summarized in Table 4 • Eighteen Projects • Total Cost of $12,219,250 • Anderson Ranch Spray Field 4 moved to Facility CIP TM

  11. Proposed Facility Capital Improvement Projects • Facility Capital Improvements Project TM: Appendix D • Summarized in Tables 5 through 8 • Twenty-Five Projects • Water Total Cost of $3,601,920 o Includes RWA Grant Match for Backup Well • Sewer Total Cost of $5,446,930 o Includes Anderson Ranch Spray Field 4 • Drainage Total Cost of $382,120 • Administration Total Cost of $400,960

  12. Administration Capital Improvement Project Distribution • One Project • Water Capital Improvement: $155,973 • Sewer Capital Improvement: $119,085 • Drainage Capital Improvement: $25,261 • Security Capital Improvement: $100,641 • Same Percentages as Administration Fee Distribution

  13. Dual Benefit Projects • Benefit New Development & Existing Users • Ten Projects Total • Water & Sewer Share Based on Water Usage • Drainage Share Based on Undeveloped Acreage o District-wide Projects Based on Full Acreage o Commercial Area Based on Benefit Area Acreage • Summarized in Tables 9 through 11 • Water Allocated Cost of $2,761,699 • Sewer Allocated Cost of $4,115,673 • Drainage Allocated Cost of $205,882

  14. Final Revenue Need Summary • Table 12 – Final Revenue Need Summary Development Share of Fee Account Project Costs Adjusted Balance Final Revenue Need Water Supply Augmentation $12,219,150 $2,017,961 $10,201,189 Water Capital $2,917,672 -$55,249 $2,972,921 Sewer Capital $4,234,758 $95,761 $4,138,997 Drainage Capital $231,143 $331,104 -$99,961 Security Capital $100,641 -$13,535 $114,176

  15. Proposed Fees • Water Supply Augmentation Fee: $5,938 per EDU • Community Facilities Fees o Water Capital Improvement Fee: $1,730 per EDU o Sewer Capital Improvement Fee: $2,409 per EDU o Drainage Capital Improvement Fee: $0 per EDU o Security Capital Improvement Fee: $66 per EDU o Total Fee: $4,205 per EDU

  16. Proposed Non-Residential EDU Methodology Change • Currently Based on SF by Use • Proposed Based on Meter Size o 1” meter = 1 EDU o 1.5” meter = 2 EDUs o 2” meter = 3.2 EDUs o 3” meter = 6.4 EDUs o 4” meter = 10 EDUs o 6” meter = 20 EDUs o 8” meter = 32 EDUs

  17. Next Steps • Today – Review & Provide Comments on Report and Ordinance • October 18 – Approve Study and First Reading • November 15 – Adopt Ordinance

  18. QUESTIONS?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.