Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow WATER COMMITTEE MEETING May 30, 2019 Agenda AGENDA Opening Remarks A. Executive Director/Committee Champion Status Report concerning legislation and


slide-1
SLIDE 1

Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow

WATER COMMITTEE MEETING

May 30, 2019

slide-2
SLIDE 2

Agenda

AGENDA

Opening Remarks

  • A. Executive

Director/Committee Champion Status Report concerning legislation and regulatory matters, budgets, current projects and

  • ngoing

programs

  • f

the District including the Regional Water System, Watershed Protection, and Water Conservation

2

slide-3
SLIDE 3

Agenda

AGENDA

Action Items

A. Consider approval of Water Committee meeting minutes – March 28, 2019 B. Consider approval of Water Committee meeting minutes – April 11, 2019 Recommend approval of Water Committee meeting minutes

3

slide-4
SLIDE 4

Action Items

C. TABLED ITEM: Consider recommendation on authorizing execution of engineering services agreement with Hazen and Sawyer, Inc., for the Wylie Water Treatment Plant II Ferric Sulfate Storage and Feed Facility Improvements

AGENDA

4

slide-5
SLIDE 5

RECOMMENDATION

5

Recommend not taking this item to the Board.

slide-6
SLIDE 6

Action Items

D. Consider recommendation on authorizing Amendment No. 13 to the Construction Manager At-Risk (CMAR) Agreement with Archer Western Construction, LLC, on Project No. 101-0344- 13, Bois d’Arc Lake Dam and Intake Structure, establishing a partial guaranteed maximum price (GMP) of $44,687,897.67 for construction of the terminal storage reservoir and allocate additional funding in that amount; establishing the final GMP for the entire CMAR 1 project scope in the amount of $216,714,595.64; set the CMAR’s substantial completion deadline to December 15, 2020 and set the final completion deadline to May 30, 2021; and set liquidated damages to $4,000 per day from substantial completion and $2,500 per day from final completion (Please refer to Administrative Memorandum No. 5414)

AGENDA

6

slide-7
SLIDE 7

BDL CMAR 1 AMENDMENT NO. 13 – TSR AT LEONARD WTP

Background:

  • Construct a 210 MG earthen embankment terminal

storage reservoir (TSR) at the Leonard Water Treatment Plant (Leonard WTP) site.

  • Future planned expansion to have an ultimate storage

capacity of 420 MG on site

7

slide-8
SLIDE 8

BDL CMAR 1 Amendment no. 13 – TSR at Leonard WTP

TSR at Leonard WTP

8

slide-9
SLIDE 9

BDL CMAR 1 Amendment no. 13 – TSR at Leonard WTP

slide-10
SLIDE 10

BDL CMAR 1 AMENDMENT NO. 13 – TSR AT LEONARD WTP

Scope of Work:

  • CMAR to award contracts for:
  • Construction of embankment, liner, 3,000 LF of 90-inch

pipeline, and appurtenances;

  • Construction of electrical and instrumentation equipment;
  • Quality control for materials testing; and,
  • Installation of two mixers in the TSR
  • Total estimated cost for Partial GMP included in this

Amendment No. 13 is $44,687,897.67

10

slide-11
SLIDE 11

BDL CMAR 1 AMENDMENT NO. 13 – TSR AT LEONARD WTP

WP No. 1 – Embankment, liner and pipeline WP No. 2 – Electrical and instrumentation

Company Total Base Bid $ From Low 40 Points Technical Component 60 Points Price Component Total Points Thalle 36,443,564.60 $ 580,610.60 $ 32.37 59.04 91.41 Flatiron 35,862,954.00 $

  • $

22.97 60 82.97 Oscar Renda 37,676,300.00 $ 1,813,346.00 $ 25.36 57.11 82.47 RE Monks 47,597,494.00 $ 11,734,540.00 $ 34.92 45.21 80.13 Phillips and Jordan 51,962,110.00 $ 16,099,156.00 $ 29.93 41.41 71.34

Company Total Base Bid $ From Low 40 Points Technical Component 60 Points Price Component Total Points ACME 2,094,213.00 $

  • $

34.05 60 94.05 FSG 2,257,500.00 $ 163,287.00 $ 37.28 55.66 92.94

11

slide-12
SLIDE 12

BDL CMAR 1 AMENDMENT NO. 13 – TSR AT LEONARD WTP

WP No. 3 – Construction material testing

Company Total Base Bid $ From Low 40 Points Technical Component 60 Points Price Component Total Points PSI 335,052.80 $ 41,052.80 $ 34.71 52.65 87.36 MEG 294,000.00 $

  • $

24.08 60 84.08 AGG 385,448.00 $ 91,448.00 $ 34.67 45.76 80.43 Alpha 427,790.00 $ 133,790.00 $ 34.62 41.24 75.86 TSI 389,812.00 $ 95,812.00 $ 30.47 45.25 75.72

12

slide-13
SLIDE 13

BDL CMAR 1 AMENDMENT NO. 13 – TSR AT LEONARD WTP

CMAR 1 Amendment No. 13 TSR Partial GMP PRICE

Construction Cost

$39,105,234.40

General Conditions

$2,659,155.94

Construction Services Fee

$2,088,219.52

Contingency

$835,287.81

Total Board Approval - Ad Memo

$44,687,897.67

13

slide-14
SLIDE 14

BDL CMAR 1 AMENDMENT NO. 13 - TSR AND FINAL GMP FOR DAM AND INTAKE STRUCTURE

TOTAL MAXIMUM CONTRACT PRICE SUMMARY The total maximum contract price includes a summary of all construction costs, which is the sum of all construction work (including materials), applicable pre-negotiated preconstruction and procurement services fee, general conditions, contingency, and CMAR construction services fee. CMAR 1 Contract Price Summary Description Status Lump Sum Cost

Preconstruction Services Fee Board Approved $990,467.00 Amendment No. 1- Additional Preconstruction Services for Dam and Intake Structure Board Approved $142,000.00 Amendment No. 2- Preconstruction services for Impoundment Clearing and Leonard Terminal Reservoir Board Approved $406,239.00 Amendment No. 3 Contract Modifications No Additional Funding Requested $0.00 Amendment No. 4 Procurement Services for Dam, Intake Structure and Leonard Terminal Reservoir (Increase) Board Approved $517,207.00 Amendment No. 5 Partial GMP for Fannin County Road (CR) 2715 Improvements Board Approved $2,806,130.36 Amendment No. 6 Partial GMP for Dam Site Clearing Board Approved $1,216,437.43 Amendment No. 7 Modify provisions in the Agreement and General Conditions to comply with Texas Water Development Board (TWDB) requirements No Additional Funding Requested $0.00 Amendment No. 8 GMP (Dam, Intake Tower and Reservoir Clearing) less previously authorized Partial GMPs (includes work packages 1 and 9) and preconstruction services credit (unused services) Board Approved $166,106,551.35 Amendment No. 9 Advance to CMAR the lump sum of the anticipated General Conditions to cover costs associated with CMAR’s initial project mobilization, procuring payment and performance bonds (the Mobilization Advance of $2,952,060.45) No Additional Funding Requested $0.00 Amendment No.10 (Change Order No.1 for Dam, Intake Tower and Reservoir Clearing)-Additional Clearing due to recently acquired lands now available for clearing, remove work that will be addressed by the mitigation full service provider and remobilization cost necessary to remobilize the clearing subcontractor once the remaining lands are acquired Board Approved $1,991,209.08 Amendment No.11 (Change Order No. 2)- Removal of Deleted Work from CMAR’s Work resulting in a net reduction to the total estimated Cost of Work on the Dam and Reservoir Clearing Project Board Approved $(93,630.25) Amendment No.12 –Change order for a 58-day time extension due for the September 21, 2018 flood event Board approved $0.00

Amendment No.13 – Partial GMP for construction work of the Leonard WTP Terminal Storage Reservoir Current Request $44,687,897.67 CMAR 1 FINAL GMP FOR THE ENTIRE CMAR 1 PROJECT SCOPE $216,714,595.64

CMAR 1 Final Maximum Contract Price - Includes all Preconstruction and Procurement Fees $218,770,508.64 CMAR 1 Estimated Contract Price Included in the $1.6B Program Summary $201,162,442.00

14

slide-15
SLIDE 15

BDL CMAR 1 AMENDMENT NO. 13 – TSR AT LEONARD WTP

Increase in cost justification:

The Partial GMP of $44,687,897.67 included in this administrative memorandum compares to an estimated cost of $31,300,000.00 included in the Program Cost. Increased costs were incurred due to:

  • Transfer of 3,000 linear feet of 90-inch pipe from the raw water pipeline
  • Increased depth to allow future transfer of Texoma raw water via gravity
  • Raising of the embankment for better control of overflow
  • Increased excavation in rock

15

slide-16
SLIDE 16

RECOMMENDATION

16

slide-17
SLIDE 17

Action Items

E. Consider recommendation on authorizing execution of a post- termination, final payment, and release agreement and authorization to issue final payment to Ratcliff Constructors, LP, in the final payment amount

  • f

$181,974.95 and ($9,795,025.05) credit for termination of contract, on Project

  • No. 101-0352-14, Wylie Water Treatment Plant Water System

Operations Center (Please refer to Administrative Memorandum No. 5416)

AGENDA

17

slide-18
SLIDE 18

WATER SYSTEM OPERATIONS CENTER

18

  • Initial construction contract awarded to Ratcliff in May 2018
  • Construction delayed due to unanticipated permitting and zoning

complications; extreme detrimental impact to the Contractor

  • By contract, Contractor can terminate and seek recovery for legitimate

costs incurred:

  • Ratcliff labor costs for:
  • Development of shop drawings (rounded)

$56,742

  • Project management and

$72,722 supervision

  • Structural steel from Russellville

$52,511

  • Total

$181,974.95

slide-19
SLIDE 19

WATER SYSTEM OPERATIONS CENTER

19

  • Nature of the raw steel procurement agreement between Ratcliff and

Russellville did not lend itself to clean re-assignment to NTMWD, for subsequent assignment to new contractor.

  • Re-assignment of materials between contractors presents potential for

many liabilities to pass to Owner

  • Final payment of $129,464 to Ratcliff will settle all claims against the

current contract

  • Final payment of $52,511 to Russellville accounts for incurred cost for raw

steel, detailing fees, restocking credit and scrap credit.

  • Total out-of-pocket for termination and release is $181,974.95.
slide-20
SLIDE 20

RECOMMENDATION

20

slide-21
SLIDE 21

Action Items

F. Consider recommendation authorizing execution

  • f

engineering services agreement with Kimley-Horn and Associates, Inc., in the amount of $252,000 on Project No. 101-0427-16, Kaufman 20-Inch Waterline Assessment, Phase II (Please refer to Administrative Memorandum No. 5407)

AGENDA

21

slide-22
SLIDE 22

KAUFMAN 20-INCH WATERLINE ASSESSMENT

22

  • 79,000 LF of bar wrapped pipe; constructed in 1974
  • Sole treated water supply for Kaufman
  • Phase I, completed 2018, replaced combination air valves and

inspected 55,000 LF of the pipeline

  • Seven damaged sections targeted for immediate repair
  • Phase II:
  • Repair seven known damaged sections
  • Install access points to facilitate inspection of remaining 24,000 LF
  • Planning level construction estimate: $1,600,000
slide-23
SLIDE 23

KAUFMAN 20-INCH WATERLINE ASSESSMENT

23

slide-24
SLIDE 24

RECOMMENDATION

24

slide-25
SLIDE 25

Action Items

  • G. Consider

recommendation

  • n

authorizing execution

  • f

engineering services agreement with Halff Associates, Inc., in the amount of $315,800 for preliminary engineering design on Project No. 101-0519-18, North Garland Pipelines Condition Assessment (Please refer to Administrative Memorandum No. 5403)

AGENDA

25

slide-26
SLIDE 26

NORTH GARLAND SYSTEM HYDRAULIC OPTIMIZATION

26

  • Physical condition assessment of 60-inch and 72-inch pipelines in the

North Garland System is currently in progress

  • This effort will look at system hydraulic performance under various
  • perating conditions:
  • Maintain minimum 5 psi pressure under all conditions (regulatory

requirement)

  • Evaluate potential operational and/or physical improvements to:
  • Regulate pressure variations within the system
  • Mitigate potential for material fatigue
  • Mitigate transient surges (positive and negative)
slide-27
SLIDE 27

NORTH GARLAND SYSTEM HYDRAULIC OPTIMIZATION

27

slide-28
SLIDE 28

28

slide-29
SLIDE 29

RECOMMENDATION

29

slide-30
SLIDE 30

Action Items

  • H. Consider

recommendation

  • n

authorizing award

  • f

construction contract with Canary Construction, Inc., in the amount of $3,680,919 on Project No. 101-0467-17, South System Air Valve Improvements, Phase II (Please refer to Administrative Memorandum No. 5406)

AGENDA

30

slide-31
SLIDE 31

SOUTH SYSTEM AIR VALVES, PHASE II

31

Current Construction Contract:

  • Replace 137 combination air valve assemblies; various sizes
  • Replace/modify 64 air manholes as needed for new assemblies

Current TCEQ guidelines require venting of air release above grade Phase II involves work in cities of:

  • Wylie
  • Plano
  • Richardson
  • Garland
  • Mesquite
  • Rowlett
  • Sachse
  • Murphy
  • Sunnyvale
slide-32
SLIDE 32

32

slide-33
SLIDE 33

RECOMMENDATION

33

slide-34
SLIDE 34

Action Items

I. Consider recommendation

  • n

authorizing award

  • f

construction contract with McKee Utility Contractors, Inc., in the amount of $6,279,290 on Project No. 101-0462-17, Renner Road to Plano Delivery Point No. 2 Pipeline (Please refer to Administrative Memorandum No. 5405)

AGENDA

34

slide-35
SLIDE 35

RENNER ROAD TO PLANO DP NO. 2

35

  • Construction of parallel pipeline
  • Plano DP No. 1 has been decommissioned
  • Capacity demand has shifted to Plano DP No. 2
  • Facilitates water delivery from Shiloh Road Pump Station in

Richardson

  • 8,000 LF of 24-inch pipe and includes
  • isolation valves
  • air valves
  • cathodic protection

Engineer’s OPCC was $6,000,000; award amount $6,279,290 Five bids within $1M spread (14%)

slide-36
SLIDE 36

RECOMMENDATION

36

slide-37
SLIDE 37

Action Items

J. Consider recommendation on adoption of Resolution No. 19- 29 authorizing use

  • f

competitive sealed proposal procurement method under Texas Government Code, Chapter 2269, for the Wylie Water Treatment Plant IV Filter Gallery Wall Structural Evaluation, Project No. 101-0422-16 (Please refer to Administrative Memorandum No. 5404)

AGENDA

37

slide-38
SLIDE 38

PLANT IV FILTER REPAIR – CSP PROCUREMENT METHOD

38

  • Authorize use of Competitive Sealed Proposal (CSP) procurement

method

  • Selection based on qualifications rather than low bid pricing alone
  • Recommended due to complexity of repair methods and project

staging

  • Repairs will involve multiple shutdowns and mobilization across

several years, in order to maintain critical plant operations

  • Contractor qualifications and experience will be critical factor in

successful project performance

slide-39
SLIDE 39

PLANT IV FILTER REPAIR – CSP PROCUREMENT METHOD

39

Chapter 2269 of Texas Government Code allows NTMWD to elect to use alternate procurement methods such as CSP for construction projects. Legal counsel has advised of statutory need for NTMWD Board to specifically elect to utilize alternative delivery for each event.

slide-40
SLIDE 40

RECOMMENDATION

40

slide-41
SLIDE 41

AGENDA

Discussion Items

  • A. Cost of Service projection

B. Preliminary budget and personnel requests

41

slide-42
SLIDE 42

WATER COST OF SERVICE PROJECTIONS

42

COST OF SERVICE PROJECTIONS

slide-43
SLIDE 43

ANNUAL COST OF SERVICE PROJECTIONS

43

ASSUMPTIONS:

  • 5% Personnel Escalation
  • 3% Supplies, Contractual Services, Power, Chemical, Capital

Outlay

  • 4% Support Services Allocation

Finance is working with Engineering to evaluate all projects $5 M and over for potential TWDB funding.

slide-44
SLIDE 44

COST REDUCTION EFFORTS

44

  • Deferred future capital projects to reduce the debt

issuance in future years

– Resulting in Debt Savings, while projects are scheduled to be awarded in future years.

  • Assumed additional reliance on SWIFT

– Lower the cost of borrowing when projects fit within the lending guidelines of SWIFT funding.

slide-45
SLIDE 45

45

PRELIMINARY

slide-46
SLIDE 46

BUDGET METHODOLOGY

Member Consumption (Billion Gallons)

  • Traditional Method - Budget for full

variable rate to be covered directly by rate

  • Proposed Method - Only 91% of

variable is directly covered by rate

  • Remaining 9% (if needed) is

budgeted in RWS Contingency

  • Only Exceeded 90% once in previous

10 years

  • Rebates and Excess Rates still

calculated using traditional method

  • Does not affect contract or Rebate

Policy

FY Minimum Actual % of Min

09 92.8 79.2 85% 10 92.8 74.6 80% 11 92.8 85.9 93% 12 93.6 81.0 86% 13 93.6 78.4 84% 14 93.9 69.0 74% 15 93.9 66.6 71% 16 93.9 80.7 86% 17 95.0 78.7 83% 18 95.0 84.8 89% Average 83%

46

slide-47
SLIDE 47

BUDGET METHODOLOGY

Variable Rate – FY19 Budget Tracking

47

Budget Amended Difference

Chemical

$27.9 M $26.9 M <$1.0 M>

Production Power

$17.4 M $11.3 M <$6.1 M>

Water Purchases

$ 4.6 M $4.4 M <$0.2 M> Total Variable $49.9 M $42.5 M <$7.3 M> 15% Amended Budget Consumption is down 15%.

slide-48
SLIDE 48

BUDGET METHODOLOGY

Variable Rate – Proposed FY20 Budget Traditional Proposed Difference

Chemical

$ 34 M $ 31 M $ 3 M

Production Power

$ 21 M $ 19 M $ 2 M

Water Purchases

$ 5 M $ 4 M $ 1 M $ 61 M $ 55 M $ 6 M Impact to Rate: $.06 Reduction

48

slide-49
SLIDE 49

SUPPORT SERVICES PHASE-IN

49

Support Cost Allocation 5 YR Phase-In

  • Reviewed and Improved Departmental Allocations
  • Removed Support Departments from Water System
  • Created a Support Services Fund starting in FY20

Results in an Estimated $9.86 M additional funds to be allocated to the non-water systems.

  • Recommend a 5 YR phase-in to reduce the immediate

financial impact Includes Administration, Engineering and Maintenance

slide-50
SLIDE 50

50

COST ALLOCATION 5 YR. PHASE-IN (CURRENT $’S)

IMPACTS

System FY 19 Budget 1st Year 2nd Year 3rd Year 4th Year 5th Year 5th Year Total RWWS $ 5.09 M $ 0.83 M $ 0.83 M $ 0.83 M $ 0.83 M $ 0.83 M $ 9.24 M UEF $ 1.17 M $ 0.55 M $ 0.55 M $ 0.55 M $ 0.55 M $ 0.55 M $ 3.92 M SW $ 1.51 M $ 0.18 M $ 0.18 M $ 0.18 M $ 0.18 M $ 0.18 M $ 2.41 M SS $ 2.27 M $ 0.41 M $ 0.41 M $ 0.41 M $ 0.41 M $ 0.41 M $ 4.32 M NET $10.04 M $ 1.97 M $ 1.97 M $ 1.97 M $ 1.97 M $ 1.97 M $ 19.89 M

*numbers may not tie due to rounding

slide-51
SLIDE 51

51

BUDGET SUMMARY

slide-52
SLIDE 52

PRELIMINARY 5-YEAR GROWTH PROJECTION (WATER)

52

Department / Group FY19 FY20 FY21 FY22 FY23 FY24 Change from Current Projected FY24 Headcount Water General 6

  • 6

Plant Operations 72

  • 3

4 5 3 15 87 Transmission 4 3 2 1 3

  • 10

14 Bois d‘Arc Lake Ops 1 2 5 6

  • 13

14 Leonard WTP 7 7 2

  • 1

17 17 Tawakoni WTP 12

  • 12

East Fork RWS 7

  • 7

Bonham WTP 11

  • 11

Public Education 2

  • 2

Growth/Expansion

  • 9

12 8 1 30 Programs/Service

  • 3

5 5 8 3 24 Total Headcount 115 12 17 13 8 4 54 169

slide-53
SLIDE 53

FY20 PERSONNEL REQUESTS – PRELIMINARY

Water Ops (12) New Facility-Expansion Bois d’Arc Lake Permit Supervisor Bois d’Arc Lake Operations New Facility-Expansion Bois d’Arc Lake Supervisor Bois d’Arc Lake Operations New Facility-Expansion Water Treatment Plant Manager - Leonard Leonard WTP New Facility-Expansion Lead Water Plant Operator – Leonard (2) Leonard WTP New Facility-Expansion Water Plant Operator II – Leonard (4) – Funding 1/1/20 Leonard WTP New Program/Existing Deficiency Lead Control Room Operator – Transmission Plant Operations New Program/Existing Deficiency Lead Transmission System Operator (FY19 Add, FY20 Fund) Plant Operations New Program/Existing Deficiency Transmission System Operator II (FY19 Add, FY20 Fund) Plant Operations

53

slide-54
SLIDE 54

54

WATER OPERATIONS PERSONNEL

New Requested Personnel $862 K 3% Merit Adjustment $212 K 2% Market Adjustment $141 K Benefits/Other $244 K Total Increase $1,459 K

slide-55
SLIDE 55

REGIONAL WATER SYSTEM

55

  • FY19 Significant Items
  • Amended Budget Based on 99.87 BG
  • $1.2 M Legal – PUC, Rate Litigation awarded in FY19
  • Est $7.3 M Net Rebate
  • <$7.3 M> Variable Costs
  • FY20 Budget
  • <$2 M> Support Service Fund Impact
  • <$63 M> Support service expenses removed from RWS
  • $14 M Support services revenues removed from RWS
  • $34 M Indirect Support services expenses added to RWS O&M
  • $13 M Direct Support services expenses added to RWS O&M
  • $2 M Increase to Capital.
  • $15 M Full year debt service of ’20 bonds
  • $2 M Increase on existing P&I and I&S required balance
  • <$15 M> Decrease in transfer to Capital Improvements Fund
slide-56
SLIDE 56

56

$1.58 $ 0.68 $0.46 $1.60 $ 0.65 $0.46

10%

Capital Improvement Fund

$34 M

15%

Variable O&M

$55 M

22%

Fixed O&M

$77 M

53%

Debt Issuance

$190 M

$2.99 Water Rate FY20 Budget

$1.60 $ 0.65 $0.46 $0.28

slide-57
SLIDE 57

57

SUPPORT EXPENSES ($M)

System FY19 FY20 RWS $ 49 $ 47 Other Systems $ 14 $ 16 Total Support Expenses $ 63 $ 63

slide-58
SLIDE 58

58

RWS SUPPORT EXPENSES ($M) (TOTAL SUPPORT)

System FY19 FY20 Personnel $ 40 $ 0 O&M $ 9 $ 47 Total RWS Support Expenses $ 49 $ 47

slide-59
SLIDE 59

59

REGIONAL WATER SYSTEM Expenditures by Category

$25 $75 $125 $175 $225 $275

Personnel Operating Capital FY19 Bdgt $51 $87 $222 FY19 Amnd $51 $83 $222 FY20 Bdgt $13 $121 $224

Millions

<$1 M>Chemical <$6 M> Power $3 M PUC 46% Incr <$15 M> CIP Fund Decr $17 M Debt Incr 75% Decr 1% Net Support Services <$40 M > Support Services $1.5 M Personnel 0% 4% Decr Rebates 0%

slide-60
SLIDE 60

REGIONAL WATER SYSTEM FY20 BOND ISSUES

60

Regional Water System Revenue Bonds, Series 2019 - $101 M (SWIFT)

  • Treated Water Pipeline from Leonard WTP to Highway 5 Pump Station
  • Other Costs Relating to the Bois d’Arc Lake program
  • Contingency

Regional Water System Revenue Bonds, Series 2019A - $139 M (NON SWIFT)

  • System Wide Meter Vault Improvements
  • Expand HSPS 3-1
  • Wylie WTP II Structural and Mechanical Improvements, Phases I and II
  • Additional Clearwells at Wylie WTP
  • Other Miscellaneous Improvements

Will reassess District needs before each of these issues and reduce accordingly

slide-61
SLIDE 61

REGIONAL WATER SYSTEM FY20 BOND ISSUES

61

Regional Water System Revenue Bonds, Series 2019 - $101 M (SWIFT)

  • Treated Water Pipeline from Leonard WTP to Highway 5 Pump Station
  • Other Costs Relating to the Bois d’Arc Lake program
  • Contingency

Regional Water System Revenue Bonds, Series 2019A - $139 M (NON SWIFT)

  • System Wide Meter Vault Improvements
  • Expand HSPS 3-1
  • Wylie WTP II Structural and Mechanical Improvements, Phases I and II
  • Additional Clearwells at Wylie WTP
  • Other Miscellaneous Improvements
slide-62
SLIDE 62

AGENDA

Discussion Items

  • C. Regulatory update

62

slide-63
SLIDE 63

WATER COMMITTEE MEETING

Environmental Protection Agency Administrative Compliance Order (ACO) Overview

  • The origin of the ACO for the District dates back to incidents at Rowlett

Creek and Wylie Treatment Complex from November 2015 and August

  • f 2016.
  • July 2017 - Ammonia leak at Wylie Complex.
  • March 2018 - EPA inspection and subsequent report lead to 5 Areas
  • f Concern (AOCs).
  • August 2018 - District staff met with EPA to provide a progress

update on the corrective actions addressing the findings from the March inspection.

  • March 2019 – District receives Administrative Compliance Order No.

CAA-06-2019-3305 from EPA.

  • April 2019 – Board approves entering into ACO.

63

slide-64
SLIDE 64

WATER COMMITTEE MEETING

64

slide-65
SLIDE 65

WATER COMMITTEE MEETING Progress to Date

District took immediate action to address items in the ACO.

  • Addressed the inspection finding which were called out in the ACO

Violations 1-3.

  • Standard Operating Procedures updated.
  • Initial ammonia system assessment by 3rd party (Sept. 2017).
  • Critical updates performed (June 2018).*
  • Engaged a 3rd party expert to perform in depth assessment and

recommended updates. Completion in June 2019.

  • Chlorine and ammonia system training held for operations and

maintenance staff. Completed May 2018.

65

slide-66
SLIDE 66

WATER COMMITTEE MEETING Forward Look

  • Lloyd Gosselink is assisting with engaging a 3rd party RMP auditor.
  • Required to engage within 90 days of ACO execution. – Ahead of

schedule.

  • Enter into a service agreement with 3rd party specialist to perform

maintenance on chorine and ammonia systems and provide training to staff.

  • Service agreement was signed on 3/27/19. Maintenance activities

and training scheduled to occur June – September. Ahead of schedule.

  • Provide 3rd party hazard analysis and recommended system updates.
  • Completed and will be submitted to EPA. Ahead of schedule.
  • Scrubber system improvements
  • Conversion to LAS

66

slide-67
SLIDE 67

WATER COMMITTEE MEETING

67

slide-68
SLIDE 68

WATER COMMITTEE MEETING

Outstanding Violations

  • Failure to maintain the filters in a

watertight condition at Plant 4.

  • Expected to go before Board in

June or July.

  • Failure to measure and record the

Combined Filter Effluent (CFE) turbidity levels at least once every four hours.

  • Eng. Proj. 16-15 will address Plant 4.
  • A project nomination for Plants 1, 2

and 3 will be submitted.

Texas Commission on Environmental Quality (TCEQ) Comprehensive Compliance Investigation May 2019 New Alleged Violations

  • Failure to provide an air gap on the

filter to waste lines at Plant 3.

  • Engineering began evaluation with

consultant prior to inspection.

  • Failure to provide signage of a

restricted zone at the raw water intake.

  • Signs and buoys are on order.

68

slide-69
SLIDE 69

WATER COMMITTEE MEETING

Texas Commission on Environmental Quality (TCEQ) Comprehensive Compliance Investigation May 2019

  • Failure to maintain the vent

screen on the air relief line at the Farmersville Pump Station Pumps.

  • Screens have been repaired.
  • Failure to maintain the cover on

the overflow on the 3.5 MG storage tank without a gap of less than 1/16th in.

  • Gap is now compliant.
  • Overflow cover needs to be
  • replaced. Replacement cover

should arrive the week of 5/20/19.

69

slide-70
SLIDE 70

Additional Issues

  • Remove vegetation from fence line at the Farmersville Pump Station.
  • Vegetation has been removed. Annual contract with right of way and fence company.
  • Assess the discharge at the Casa View Pump Station.
  • Additional leak detection investigation will occur to determine the discharge source.
  • Ensure the most current backflow prevention assembly test and maintenance

form is utilized.

  • Current form has been adopted.
  • The weirs on the sedimentation basins at Plant 3 are in need of repair or
  • replacement. Ensure even flow can exit the basin.
  • A project nomination is being submitted.

70

slide-71
SLIDE 71

WATER COMMITTEE MEETING Additional TCEQ considerations

  • Casa View 4 MG tank will be reviewed further.
  • Wylie Complex Contact Time (CT) study.

71

slide-72
SLIDE 72

AGENDA

Discussion Items

D. Opportunity for Committee members to provide feedback on Water Committee meeting

72

slide-73
SLIDE 73

AGENDA

Discussion Items

E. Opportunity for Committee members to request potential future agenda items

(No substantive discussion of items will take place at this time)

Adjournment