Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow
WATER COMMITTEE MEETING
July 25, 2019
WATER COMMITTEE MEETING July 25, 2019 Agenda AGENDA Opening - - PowerPoint PPT Presentation
Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow WATER COMMITTEE MEETING July 25, 2019 Agenda AGENDA Opening Remarks A. Chairman/Executive Director/Committee Champion Status Report concerning legislation
Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow
July 25, 2019
AGENDA
Director/Committee Champion Status Report concerning legislation and regulatory matters, budgets, current projects and ongoing programs of the District including the Regional Water System, Watershed Protection, and Water Conservation
2
AGENDA
A. Consider approval of Water Committee meeting minutes – June 27, 2019 Recommend approval of Water Committee meeting minutes Executive Session
3
Action Items B. Additional Funding for Bois d’Arc Lake Land Acquisition Program – Administrative Memorandum No. 5438 Consider recommendation on adoption of Resolution No. 19-35 authorizing additional funding in the amount of $25,500,000 to acquire all remaining properties required for the construction, operation, and maintenance of Bois d’Arc Lake and associated facilities, Project No. 101-0120-07 C. Additional Funding for Leonard Water Treatment Plant Land Acquisition Program – Administrative Memorandum No. 5440 Consider recommendation on adoption of Resolution No. 19-37 authorizing additional funding in the amount of $500,000 to acquire remaining property needed for the Leonard Water Treatment Plant, Project No. 101-0154-09
D.
Conveyance of Surplus Property for Bois d’Arc Lake – Administrative Memorandum No. 5439 Consider recommendation on adoption of Resolution No. 19-36 authorizing the Executive Director to convey certain surplus tracts of land with no public access to adjoining landowners and provide access easements to certain other tracts of land with no access due to the District’s acquisition of properties for Bois d’Arc Lake, Project No. 101-0120-07
AGENDA
4
Executive Session to seek advice on legal matters regarding pending
session and then discuss matters outside of that provision.
permitted under the language merely because an attorney is present.
privileged and should remain confidential
EXECUTIVE SESSION Section 551.071, Consultation with Attorney
RECOMMENDATION
6
Scope: Land acquisition and support services necessary to facilitate the construction, operation and maintenance of the Bois d’Arc Lake Project. Project:
Amount: $25,500,000
Administrative Memorandum No. 5438
Adjourn Executive Session
RECOMMENDATION
7
Scope: Land acquisition and necessary support services to facilitate the purchase of one remaining property required for the Leonard WTP and associated facilities. Project:
Amount: $500,000 Administrative Memorandum No. 5440
RECOMMENDATION
8
Scope: Provide for disposition of certain land locked tracts of land surplus to the needs of the District which have no public access and to provide access to certain other tracts with no access due to the acquisition of properties for the Lake, as reflected in Exhibit “A.” Project:
Amount: N/A
Administrative Memorandum No. 5439
E. Amendment No. 11 to Construction Manager At-Risk Agreement on Bois d’Arc Lake Raw Water Pump Station and Leonard Water Treatment Plant High Service Pump Station – Administrative Memorandum No. 5435 Consider recommendation authorizing Amendment No. 11 to Construction Manager At-Risk Agreement with Garney Companies, Inc., in the amount
Bois d’Arc Lake Raw Water Pump Station, Project No. 101-0358-14, and in the amount of $15,276,465.60 for concrete structure construction and discharge pipe installation for the Leonard Water Treatment Plant High Service Pump Station, Project No. 101-0428-16
AGENDA
9
BDL CMAR 3 AMENDMENT NO. 11 – RAW WATER PS AND HIGH SERVICE PS
ultimate capacity, liquid oxygen system, and discharge piping
required to support expansion to ultimate capacity), an electrical room, generator, and effluent flow meter vault
10
BDL CMAR 3 Amendment No. 11 – Raw Water PS and High Service PS
HSPS at Leonard WTP RWPS at BDL
11
BDL CMAR 3 AMENDMENT NO. 11 – RAW WATER PS AND HIGH SERVICE PS
critical work to proceed—schedule driven.
12
BDL CMAR 3 AMENDMENT NO. 11 – RAW WATER PS AND HIGH SERVICE PS
Construction Cost
RWPS - $4,018,998.00 HSPS - $13,992,000.00
$18,010,998.00
General Conditions (6% of construction cost)
$1,080,659.88
Construction Services Fee (2% of cost of work)
$381,833.16
Contingency (1% of cost of work)
$190,916.58
$19,664,407.62
13
RECOMMENDATION
14
CMAR: Garney Companies, Inc. Scope: Construction services for the Raw Water Pump Station electrical system and High Service Pump Station structure and discharge pipe Project:
Pump Station Amount: $4,387,942.02 (RWPS) and $15,276,465.60 (HSPS) Total Amount Requested: $19,664,407.62
F. Amendment No. 7 to Construction Manager At-Risk Agreement on Treated Water Pipeline from Leonard Water Treatment Plant to McKinney No. 4 – Administrative Memorandum No. 5434 Consider recommendation authorizing Amendment No. 7 to the Construction Manager At-Risk Agreement with Garney Companies, Inc., in the amount of $42,299,445.92 for treated water pipe material purchase, Project No. 101-0425-16, Treated Water Pipeline from Leonard Water Treatment Plant to McKinney No. 4
AGENDA
15
BDL CMAR 5 AMENDMENT NO. 7 – TREATED WATER PIPELINE FROM LWTP
Plant (WTP) site to McKinney No. 4 site by September 2021
84-inch diameter pipe and is divided into two segments (Segments D and E).
84-inch pipe material, isolation valves, and associated appurtenances
16
BDL CMAR 5 AMENDMENT NO. 7 – TREATED WATER PIPELINE FROM LWTP FROM FROM LWTP
17
BDL CMAR 5 AMENDMENT NO. 7 – TREATED WATER PIPELINE FROM LWTP
18
BDL CMAR 5 AMENDMENT NO. 7 – TREATED WATER PIPELINE FROM LWTP
Construction Cost Pipe purchase - $36,897,954.39 Design Progression allowance - $2,213,877.26
$39,111,831.65
General Conditions (5% of construction cost)
$1,955,591.58
Construction Services Fee (2% of cost of work)
$821,348.46
Contingency (1% of cost of work)
$410,674.23
$42,299,445.92
19
RECOMMENDATION
20
CMAR: Garney Companies, Inc. Scope: CMAR construction services for treated water pipe material purchase Project:
Treatment Plant to McKinney No. 4 Amount: $42,299,445.92 (Partial Guaranteed Maximum Price)
G. Renner Road to Plano Delivery Point No. 2 Pipeline Change Order
Consider recommendation authorizing Change Order No. 1 with McKee Utility Contractors, Inc., in the credit amount of ($468,000) on Project No. 101-0462-17, Renner Road to Plano Delivery Point No. 2 Pipeline
AGENDA
21
RENNER ROAD TO PLANO DELIVERY POINT NO. 2
22
Inc., May 30, 2019
Station
RENNER ROAD TO PLANO DELIVERY POINT NO. 2
23
– Ductile iron pipe – Concrete block erosion protection system
the onset?
RECOMMENDATION
24
Contractor: McKee Utility Contractors, Inc. Scope: Construction, Change Order No. 1 Project:
Pipeline Amount: ($468,000) Credit
H. Potable Water Supply Contract with Cash Special Utility District – Administrative Memorandum No. 5424 Consider recommendation authorizing execution of Potable Water Supply Contract with Cash Special Utility District
AGENDA
25
CASH SUD POTABLE WATER CONTRACT
26
into a potable water supply contract with NTMWD on July 26, 1979 with contract term of 40 years
supply contract Standard Contract Provisions:
RECOMMENDATION
27
Contracting Party: Cash Special Utility District Scope: Potable Water Supply Contract Contract Term: 20 years
I. Agreed Order and Supplemental Environmental Project with Texas Commission
Environmental Quality – Administrative Memorandum No. 5425 Consider recommendation authorizing execution of Agreed Order with an Administrative Penalty
$7,275 and the
to perform a Supplemental Environmental Project in lieu of fine with the Texas Commission on Environment Quality regarding the 72-inch North Garland Pipeline at Shiloh Business Park in Richardson, Texas
AGENDA
28
12/4/2018 RELEASE OF POTABLE WATER Proposed Agreed Order: 12/4/2018 Release of Potable Water Briefed at June Water Committee Meeting
Collection Events (Cooke, Fannin & Grayson Counties)
29
RECOMMENDATION
30
Regulating Entity: Texas Commission on Environmental Quality Scope: Agreed Order and Supplemental Environmental Project Affected Facility: 72-inch North Garland Pipeline at Shiloh Business Park, Richardson, TX Amount: $7,275
J. Amended and Restated John Bunker Sands Wetland Center Operating Agreement – Administrative Memorandum No. 5423 Consider recommendation authorizing execution
Amended and Restated Operating Agreement for the John Bunker Sands Wetland Center
AGENDA
31
JBS WETLAND CENTER: OPERATING AGREEMENT Purpose: Enter into permanent operating agreement Substantially conforms to Temporary Operating Agreement (October 6, 2017). Ensure continued operation of the JBS Wetland Center:
with approval
Approved by JBS Board on July 15, 2019
JBS WETLAND CENTER: OPERATING AGREEMENT
RECOMMENDATION
34
Contracting Party: Wetlands Management, LP and John Bunker Sands Wetland Center, Inc. Project John Bunker Sands Wetland Center Amount: $0
A. FY19 amended and FY20 preliminary budget briefing
AGENDA
35
REGIONAL WATER SYSTEM - BUDGET
36
Allen, Farmersville, Forney, Frisco, Garland, McKinney, Mesquite, Plano, Princeton, Richardson, Rockwall, Royse City, Wylie and 34 Customers
REGIONAL WATER SYSTEM – FY19 ANNUAL MINIMUMS (PER THOUSAND GALLONS)
37
Members Minimum
Allen 6,011,208 Farmersville 280,467 Forney 1,956,185 Frisco 10,986,490 Garland 13,721,955 McKinney 11,963,029 Mesquite 8,297,666 Plano 26,719,809 Princeton 535,076 Richardson 11,019,311 Rockwall 3,953,622 Royse City 493,325 Wylie 1,877,558
Total Member 97,815,701 Total Customer 20,334,405 Total System 118,150,106
RWS STRATEGIC FINANCIAL PLAN
38
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 Current $2.92 $2.99 $3.14 $3.33 $3.50 $3.64 $3.79 $3.94 $4.10 $4.26 $4.43 Curr Incr 2% 5% 6% 5% 4% 4% 4% 4% 4% 4% Prior $2.92 $3.12 $3.31 $3.48 $3.62 $3.76 $3.91 $4.07 $4.23 $4.40 $4.58 Prior Incr 7% 6% 5% 4% 4% 4% 4% 4% 4% 4% $2.50 $3.00 $3.50 $4.00 $4.50 $5.00
NTMWD Regional Water System Member Cost Per 1,000 Gallons
PRELIMINARY
39
PRELIMINARY ANNUAL MINIMUM FY20 PROJECTED RATE FY20 PROPOSED RATE INCREASE/ (DECREASE) MEMBER CITY 3.12 2.99 (0.13) Allen 6,011,208 18,754,969 17,973,512 (781,457) Farmersville 280,467 875,057 838,596 (36,461) Forney 1,956,185 6,103,297 5,848,993 (254,304) Frisco 10,986,490 34,277,849 32,849,605 (1,428,244) Garland 13,721,955 42,812,500 41,028,645 (1,783,855) McKinney 11,963,029 37,324,650 35,769,457 (1,555,193) Mesquite 8,297,666 25,888,718 24,810,021 (1,078,697) Plano 26,719,809 83,365,804 79,892,229 (3,473,575) Princeton 536,305 1,673,272 1,603,552 (69,720) Richardson 11,019,311 34,380,250 32,947,740 (1,432,510) Rockwall 3,953,622 12,335,301 11,821,330 (513,971) Royse City 493,325 1,539,174 1,475,042 (64,132) Wylie 1,877,558 5,857,981 5,613,898 (244,083) Total 97,816,930 305,188,822 292,472,621 (12,716,201)
40
Revised RWS FY20 Water Rate FY20 RWS Operating Budget (FY19 SFP w/ $3.12) $ 368,307,510 Rate Incr/(Decr) Support Fund Allocation: $ (2,347,805) $ (0.02) 9% Reduction in Variable Costs: Chemicals (3,097,400) (0.03) Power (1,695,500) (0.02) Water Purchases (332,390)
(5,125,290) (0.05) Capital Savings: Capital Improvement (11,100,000) (0.11) Debt Service Payment (918,455) (0.01) Capital Savings: (12,018,455) (0.12) Supplemental Request Reductions: Priority 1 (878,115) (0.01) Priority 2 (87,850)
(267,100)
(1,233,065) (0.01) Transmission Department: 7,416,085 0.07 Other: Leonard WTP & BDL Department Increase 412,515
$ 355,411,495
$ (0.13) Adopted Water Rate in FY19 2.92 Revised FY20 Member City Water Rate 2.99 2.38% FY19 Cost of Service Member City Water Rate 3.12 23.32% Difference (0.13)
41
REGIONAL WATER SYSTEM - BUDGET Expenditures by Category
$5 $55 $105 $155 $205 $255
Personnel Operating Capital FY19 Bdgt $51 $87 $222 FY19 Amnd $51 $81 $222 FY20 Bdgt $13 $119 $223
Millions
37% Incr <$15 M> CIP Fund Decr $16 M Debt Incr 75% Decr .5% Incr Estimated $32 M net to account for Support Services Allocation <$40 M > Support Services $1.7 M Personnel 0% 7% Decr 0% <$1 M> Chemical <$6 M> Power <$2 M> Wtr Purchases $2 M PUC $1 M Richardson PL
REGIONAL WATER SYSTEM - FY20 BOND ISSUES
42
10/2019 Regional Water System Revenue Bonds, Series 2019A - $142 M (NON SWIFT)
mechanical improvements, Phases I and II, additional clearwells at Wylie WTP, and other miscellaneous improvements.
11/2019 Regional Water System Revenue Bonds, Series 2019 - $101 M (SWIFT)
to the Bois d’Arc Lake program, and Contingency
09/2020 Regional Water System Refunding Bonds 09/2020 Regional Water System Revenue Bonds, Series 2020A - $94 M (NON SWIFT)
WTP II, Structural and Mechanical Improvements Phase II, System wide Meter Vault Improvements - Setpoint Control Phase IV, and other miscellaneous improvements.
REGIONAL WATER SYSTEM - CIP
43
FY20 CIP Contracts to be funded with RWS Capital Improvement Fund:
(Construction / Inspection Contracts unless otherwise noted.)
$19M – Wylie Rockwall Farmersville 36”/48” Pipeline Improvements Phase II $10M – Future Water Supply Project – Permitting and Mitigation $ 9M – Wylie WTP Ammonia System Improvements $ 6M – HSPS 2-2 and 2-3 Control Valve Improvements $ 5M – Transmission System Water Quality Analyzers $ 4M – HSPS 2-1 Electrical Improvement Phase IIB $ 4M – Wylie WTP I Washwater Supply System Improvements $ 3M – Air Valve Improvements – North System Phase II $25M – Other (Construction, Engineering, Property) $85M – Total CIP FY20 Project Costs
AGENDA
B. Opportunity for Committee members to provide feedback on Water Committee meeting
44
AGENDA
agenda items
(No substantive discussion of items will take place at this time)
45