presented by
Carl Fiset
Engineer
Centre Lac-Brome December 8, 2012
Carl Fiset Engineer Centre Lac-Brome December 8, 2012 Contents - - PowerPoint PPT Presentation
presented by Carl Fiset Engineer Centre Lac-Brome December 8, 2012 Contents Length of the presentation: 1 hour Current aqueduc network Supply Water quality Consumption Consumption 2011-2012 problems Action Plan
presented by
Engineer
Centre Lac-Brome December 8, 2012
Length of the presentation: 1 hour Current aqueduc network Supply Water quality Consumption Consumption 2011-2012 problems Action Plan Question period
Principal flow unit: L/min. (liters per minute) Secondary flow unit : USGPM (US gallons per minute) Volume unit: m³ (cubic meters) 1 m³ (cubic meter) = 1000 L (liters)
1 m³ (cubic meter) = 1000 L (liters)
1 USGPM = 3,785 l/min. 1 liter = 0,258 US gals. MDDEFP: Ministère du Développement Durable, de
l’Environnement, Faune et des Parcs
MAMROT: Ministère des Affaires Municipales, Région et
Occupation du Territoire
Artesian well Infiltation gallery
Artesian well:
Drilling into the ground where water flows spontaneously Aquifer: a geological formation that is sufficiently porous and/or
fractured or cracked and permeable containing an underground water table (natural replenishment)
table (natural replenishment)
Filter pipe(perforated pipe)installed horizontally capturing
water from the underground water table using a pump
Strainer Undisturbed soil Coarser sand 2 to 4 mm Silt backfill material Vent
Bondville Reservoir
AQUEDUC NETWORK:
healthy according to MAMROT
Spring Hill Reservoir Jolibourg well Bailey Sector:
Bailey Sector (Bolton West): 82,4% of total production
LB-4-99:
Built in1999 Draws groundwater in an aquifer at the level of the rocky
subterranean layer at a depth of 43.3 meters
Flow
LB-4-99 LB-1-97 Jolibourg
subterranean layer at a depth of 43.3 meters
Authorized at a flow rate of 1,134 L/min. Chlorinated and pumped to the Spring Hill reservoir Equipped with a magnetic flowmeter and a water-level
probe (lowering of groundwater)
58.7% of total production
Well LB-1-97
Built in 1997 to replace the Bailey 2 well Draws groundwater in an aquifer of sand and gravel at a
depth of 14.34 meters
Flow
LB-4-99 LB-1-97 Jolibourg
depth of 14.34 meters
Authorized at a flow rate of 455 L/min Chlorinated and pumped to the Spring Hill reservoir Equipped with a magnetic flowmeter and a water-level
probe (lowering of groundwater)
23.6% of total production
Trial infiltration gallery
Built in 2007 to replace the Bailey surface well, deemed too
vulnerable
Small-scale constrution in order to evaluate potentiel Small-scale constrution in order to evaluate potentiel Draws groundwater close to Coldbrook Stream at a depth
horizontally
Potentiel flow of 280 L/min. Equipped with a magnetic flowmeter Operated between November 2009 and August 2012 No authorization from MDDEFP
Permanent infiltration gallery
Built in 2011 to increase the capacity of the small gallery The large infiltration gallery draws groundwater in the same way as the
trial infiltration gallery but at a depth of 6 meters
Flow about 665 L/min. Manganese concentration of 0.5 mg/L is above the esthetic standard of
0.05 mg/L (no danger for health) 0.05 mg/L (no danger for health)
Treatment possible but expensive:
Green sand filter: $200 000 + installation and building
Capacity for manganese dilution with the other wells: 0.136 mg/L An increase in the inflow from Coldbrook Stream could possibly reduce
the mangenese concentration: repair breach in dam and dredging
Use of large infiltration gallery has the effect of drying up the trial
infiltration gallery: 665-280= 385 (a gain of 385 L/min.)
This source could be used with caution in the case of periods of high
consumption, low supply or major fire.
No authorization form MDDEFP
Permanent infiltration gallery
No danger to health Unstable in water and precipitates and produces sediment
in the form of black silt
Water has bad taste Water has bad taste May leave spots on laundry and plumbing accessories Sticks to conduit walls, reduces flow and can become
detached with turbulence
Presence of manganese in low amounts at several locations
in the network
Built in 1991 Draws groundwater, in an aquifer of sand and gravel
at a depth of 42 meters
Rehabilitated in 1997 Pumps water directly in the network
Flow
LB-4-99 LB-1-97 Jolibourg
Pumps water directly in the network Current flow of 340 L/min. (authorized at 770 L/min.
in 1992)
Building redone in 2009 with a chlorination unit, not
connected (cause = time in contact with chlorine insufficient)
Not measured since the work (2009) Non-chlorinated 17.6% of production
Built in 1974 (useful life about 50 years = 2024) Material: Concrete Capacity of 4,546 m³ Capacity of 4,546 m³ Stand-alone capacity (±1500 L/min.) of 48 hours and a stand-
alone at maximum flow (±3000 L/min.) of 24 hours
Supplied by a 300 mm PVC conduit (autumn 2007) from the
Bailey sector wells:
LB-4-99 LB-1-97 (Trial infiltation gallery) (Permanent infiltration gallery)
Built in 1974 (useful life about 50 years = 2024) Material: Concrete Capacity of 227m³ Supplied by the Spring Hill reservoir (by gravity): Peak of 1000 L/min. when recharging
Peak of 1000 L/min. when recharging
Buffer reservoir used to supply the Inverness sector (about 130
residences) and to adjust the chlorine concentration when needed (standard: 0.3gm/L).
New chlorination station (not operating) One flowmeter at the entry and one at the exit (not connected) Equipped with a modulating valve Stand-alone about 13 hours (at 355 L/min.)
22 water meters already installed and measured every
Flowmeters installed:
Spring Hill reservoir (1984) Spring Hill reservoir (1984) Bondville reservoir (two not connected) Well LB-4-99 Well LB-1-97.
Computer and software recording data installed in the
Sampling performed according to the regulations in effect
No contamination problems in wells or in the network Monitoring of results handled by the SM laboratory of Monitoring of results handled by the SM laboratory of
Water of quality requiring minimal treatment
26%
2011
6% 68% LEK Duck Farm Other consumers
Knowlton Packaging 2012 Reduction of 18% compared to 2011 to 2011
2011: 1,828 m³ of water at a cost of $23,619 were delivered
between July 21 and 23
2012: June 20 to 23, July 25 to 26, August 1 to3, August 20 to 23,
august 29 to 31
12,298 m³ (533L/min.) of water at a cost of about $150,000 before Jolibourg
well and the trial infiltration gallery were suspended until official authorization was obtained (demand estimated at 2,742L/min.) authorization was obtained (demand estimated at 2,742L/min.)
September 20: official authorization from the MDDEFP to operate
the Jolibourg well (acquired right since 1991)
2012: September 3 to 7, September 10 to14, September 18 to 21,
September 25 to 27 for a total of about 13,410,5 m³
In total 25,708.5 m³ of water at a cost of about $300,000
Increase in water needs since 2009 Closing of the trial infiltration gallery since we did not
Weather favouring water consumption even though
No reduction in production capacity No possibility of increasing production or of using
Meet with the MDDEFP to review the situation and present our plan - Completed Determine the least expensive and most effective solutions- Completed Respond to the request for conformity from the MDDEFP (letter of May 17, 2012) Combine several requests for authorization from the MDDEFP based on the
recommandations of expert consultants:
Increase the production capacity of Well LB-4-99 to 1,300 l/min., an increase of Increase the production capacity of Well LB-4-99 to 1,300 l/min., an increase of
166l/min. – in progress
Provide the hydrogeological study to obtain authorization to operate the trial
infiltration gallery, for a increase of 280 l/min. – in progress
Provide the hydrogeological study ot obtain the authorization to operate the
permanent infiltration gallery for an increase of 385 l/min. – in progress
Study the possibility of operating the Jolibourg well at its full potential (pumping
trial), for a possible increase of 430 l/min.– to be determined
Balance the modulating valve of the Bondville resrvoir – to come Search for groundwater in early 2013 – to be determined
Reduction in Knowlton Packaging cooling water
Leak detection programme (2013 budget) Updating of intervention plan (2013 budget) Implement the water conservation strategy:
Implement the water conservation strategy:
Awareness campaign Barrels of capturing gray water at reasonable prices Sale of reduced water consumption kits (faucet, toilet,
shower head,etc.)
Complete the installation of instrumentation and controls
Connection of the new flowmeter at Jolibourg – in progress Connection of the equipment and the chlorination station
Connection of the equipment and the chlorination station
at the Bondville reservoir – to come
Replacement of the flowmeter at the Spring Hill reservoir
(1984) – to come
Modifications to the software programming to produce
more complete reports – to come
Protect the Bailey sector from the operating activities of
Make operators aware of the risks of contamination Encourage the operators to implement measures to allow a
Encourage the operators to implement measures to allow a
reduction of risk (recovery of leaks from the machinery)
Scenario 1 (normal consumption):
Source Flow (L/min.) LB-4-99 1,300 LB-1-97 455 Trial infiltration gallery 280 Permanent infiltration gallery Jolibourg 340 Knowlton Packaging reduction 212
Scenario 2 (Peak consumption):
Total: 2,587 Source Flow (L/min.) LB-4-99 1,300 LB-1-97 455 Trial infiltration gallery Permanent infiltration gallery 665 Jolibourg 340 Knowlton Packaging reduction 212 Total: 2,972
Scenario 3 (full potential):
Source Flow (L/min.) LB-4-99 1,300 LB-1-97 455 Trial infiltration gallery Permanent infiltration gallery 665 Jolibourg 770 Knowlton Packaging reduction 212
Total: 3,402
Question period