Walk Bridge Program Housekeeping Items 6/12/2020 Manresa Island - - PDF document

walk bridge program housekeeping items
SMART_READER_LITE
LIVE PREVIEW

Walk Bridge Program Housekeeping Items 6/12/2020 Manresa Island - - PDF document

Walk Bridge Program Housekeeping Items 6/12/2020 Manresa Island Online Public Meeting Ju ne 16, 2020 www.WalkBridgeCT.com 1 This meeting is recorded. There may be a few glitches, so please bear with us. We will immediately address any


slide-1
SLIDE 1

6/12/2020 1

www.WalkBridgeCT.com

Walk Bridge Program

Ju ne 16, 2020

Manresa Island Online Public Meeting

www.WalkBridgeCT.com

Housekeeping Items

 This meeting is recorded.  There may be a few glitches, so please bear with us. We will immediately address any technical difficulties.  Please mute your phone during the presentation.  Please enter any questions or comments in the chat box. We will answer questions at the end of the presentation.  CTDOT will accept questions and comments until July 3, 2020.  Meeting materials are available at walkbridgect.com.

1 2

slide-2
SLIDE 2

6/12/2020 2

www.WalkBridgeCT.com

Meet Your Speakers

  • Jim Fallon, CTDOT
  • Lauren DiGovanni, HNTB
  • Sarah Walker, HNTB

www.WalkBridgeCT.com

Meeting Agenda

175 TRAINS/DAY 125K PASSENGERS/DAY

  • 1. Introductions & Meeting Purpose
  • 2. Walk Bridge Overview
  • 3. Proposed Lift-Span Construction
  • 4. Proposed Use of Manresa Island
  • 5. Natural Resources, Navigation & Aquatic Resources, Community
  • 6. Minimization and Mitigation Measures
  • 7. Federal and State Reviews, Approvals and Permits
  • 8. Next Steps
  • 9. Questions and Comments

3 4

slide-3
SLIDE 3

6/12/2020 3

www.WalkBridgeCT.com www.WalkBridgeCT.com www.walkbridgect.com

WALK BRIDGE REPLACEMENT REPLACEMENT OF THE OSBORNE AVENUE RAILROAD BRIDGE FORT POINT STREET BRIDGE REPLACEMENT AND ROADWAY REALIGNMENT EAST AVENUE BRIDGE REPLACEMENT AND ROADWAY IMPROVEMENT PROJECT CP243 INTERLOCKING PROJECT A N N ST R EET B R IDG E R EP L ACE M EN T DANBURY BRANCH DOCKYARD PROJECT

The Walk Bridge Program

5 6

slide-4
SLIDE 4

6/12/2020 4

www.WalkBridgeCT.com

240’ Vertical Lift Span

  • Shortest construction schedule
  • Lowest risk during construction
  • Shortest period of navigation

restrictions

  • Fewest foundations in water
  • Improved alignment with

Stroffolino Bridge

Project Overview

Anticipated Duration: Approximately 5-6 years

www.WalkBridgeCT.com www.walkbridgect.com

Proposed Lift-Span Construction

Replacement bridge lift spans will be:

  • Constructed off-site using accelerated bridge

construction (ABC) techniques

  • Floated to the bridge site
  • Installed in about 96 hours

7 8

slide-5
SLIDE 5

6/12/2020 5

www.WalkBridgeCT.com

Construction Parcels Overview

CTDOT will require parcels for the construction of Walk Bridge for:

  • River and rail access and staging
  • Equipment and material storage
  • ABC -Replacement bridge lift spans construction
  • On site location -68 & 90 Water Street -initially

proposed; less than 0.2 nautical mile from Walk Bridge

  • Off site location proposed in Value Engineering Study;

about 2 nautical miles from Walk Bridge

  • Barges used to construct and transport lift spans to

bridge site

www.WalkBridgeCT.com

Proposed Use of Manresa Island

Walk Bridge Manresa Island

9 10

slide-6
SLIDE 6

6/12/2020 6

www.WalkBridgeCT.com www.walkbridgect.com

Proposed Use of Manresa Island

Northern Parcel (Parcel 5/86/2; 92 acres)

  • No construction use;
  • Site access only for up to 60 months.

Southern Parcel (Parcel 5/86/1; 33 acres)

  • Construction easement for 5-acre Staging and Storage Yard

in isolated, previously developed and disturbed area with waterfront access;

  • Use for up to 60 months. Active lift span construction for

up to 48 months.

www.WalkBridgeCT.com

Staging and Storage Yard: Work Area

  • Pre-assembly of structural components;
  • Full assembly of both lift span trusses before float-in

to the bridge site;

  • Berthing of safety boat vessels and emergency rescue
  • perations associated with lift span construction;
  • Temporary berthing of construction vessels and

barges.

11 12

slide-7
SLIDE 7

6/12/2020 7

www.WalkBridgeCT.com

Staging and Storage Yard : Laydown Area

  • Storage of construction materials (steel and timber);
  • Temporary storage of components from demolition of

existing bridge and project site (stone masonry and concrete debris, structural steel members, timber cribbing/pilings).

  • No dredged material will be transported to or stored
  • n site.

www.WalkBridgeCT.com

Natural Resources

  • No freshwater or tidal wetlands exist in staging and storage yard; No impact to intertidal area.
  • No adverse impact to 100-year floodplain due to minor fill required for site preparation.
  • No impact to groundwater.

13 14

slide-8
SLIDE 8

6/12/2020 8

www.WalkBridgeCT.com

Navigation and Aquatic Resources

  • Equipment and material barges about

300 feet outside of channel ≈ No impact to federal navigation channel.

  • Previous aquatic protected species and

habitat review included Manresa Island area ≈ No additional impact.

  • Spud piles used to anchor barges
  • Barge movements ≈ No impact to river

bottom or increased turbidity.

www.WalkBridgeCT.com

Community

  • No impact on existing land uses.
  • Restored to pre-construction conditions after

project completion.

  • Employee traffic approximately 22 round-trips per

day (6-day week).

  • Truck traffic approximately 3 round-trips per day

during peak construction (5-day week; daylight hours).

  • Located 0.4 mile from nearest receptor ≈ no

perceptible increase in noise.

15 16

slide-9
SLIDE 9

6/12/2020 9

www.WalkBridgeCT.com www.walkbridgect.com

Time of year restrictions and protection protocols for State-listed Species included in permits and contract specifications Six-inch layer of geotextile and stone as a separation barrier from existing Areas of Concern  Secure storage of fuels and hazardous materials -Flood Contingency Plan  Completely fenced with secure entrance gate

 Completely fenced with secure entrance

Minimization and Mitigation Measures

www.WalkBridgeCT.com

Federal and State Reviews, Approvals and Permits

 NEPA and Section 106 Re-evaluation Consultation with FTA for Verification of Project FONSI  Coordination with National Marine Fisheries Service  Coordination with CTDEEP Divisions of Wildlife & Fisheries  CTDEEPFlood Management Certification  CTDEEP Structures, Dredging & Fill Permit and Section 401 Water Quality Certification  U.S. Army Corps of Engineers Section 404 and Section 408 Permits  U.S. Coast Guard Bridge Permit  CTDEEP General Permit for Discharge of Stormwater and Dewatering Wastewaters from Construction Activity

17 18

slide-10
SLIDE 10

6/12/2020 10

www.WalkBridgeCT.com

Next Steps

 Public review comments –through July 3, 2020  NEPA Re-evaluation Consultation with FTA for Verification of Project FONSI –August 1, 2020  Permit application filings –Summer 2020  Final design –Fall 2020  Construction start –Fall 2021

www.WalkBridgeCT.com www.walkbridgect.com

Stay Involved

www.walkbridgect.com 833-GO2-WALK info@walkbridgect.com @walkbridgect

19 20