Valdez Operations Overview Alyeska Pipeline Service Company Prince William Sound Regional Citizens Advisory Council Board Meeting January 24, 2019 Anchorage, Alaska January 24, 2019 VMT Operations 2018* Tankers Loaded 247 Tankers Escorted


slide-1
SLIDE 1

Valdez Operations Overview

Alyeska Pipeline Service Company

Prince William Sound Regional Citizens Advisory Council Board Meeting January 24, 2019 Anchorage, Alaska

January 24, 2019

slide-2
SLIDE 2

Page 2 of 23

2018*

Tankers Loaded 247 Tankers Escorted 255 Barrels Loaded 178,137,687

Since Startup

Tankers Loaded 22,407 Tankers Escorted 13,710 Barrels Loaded 17,120,939,370

VMT Operations

* As of 12/31/18 January 24, 2019

slide-3
SLIDE 3

Page 3 of 23

Health-Safety-Environment

Valdez Operations

Safety 2018

Days Away From Work Cases TAPS Combined Recordable Incident Rate % 0.27

Environment 2018

Spill Volume (Gallons) 217.2862 (12.2862*) Number of Spills 10

* Outside containment

January 24, 2019

slide-4
SLIDE 4

Page 4 of 23

Alyeska Organizational Update

January 24, 2019

slide-5
SLIDE 5

Page 5 of 23

Alyeska Organizational Update

January 24, 2019

slide-6
SLIDE 6

Page 6 of 23

Alyeska Organizational Update

January 24, 2019

slide-7
SLIDE 7

Page 7 of 23 January 24, 2019

Alyeska Organizational Update

Operations and Maintenance Division

slide-8
SLIDE 8

Page 8 of 23 January 24, 2019

Alyeska Organizational Update

Engineering and Risk Division

slide-9
SLIDE 9

Page 9 of 23

Fishing Vessel Availability

End of 4 th quarter 2018

Port Tier 1 Tier 2

Valdez 21 23 Cordova 32 (7RR) 115 Whittier 6 23 Seward 30 Homer 55 Kodiak 39

TOTAL 59 285

*RR = Rapid Response

January 24, 2019

slide-10
SLIDE 10

Page 10 of 23 January 24, 2019

SERVS Highlights

2019 Fishing Vessel Training

  • Spring Fishing Vessel Training
  • Kodiak: March 27 – April 2
  • Homer: April 3 – April 9
  • Seward: April 10 – April 14
  • Cordova: April 15 – April 26
  • Valdez: April 27 – May 3
  • Fall Fishing Vessel Training
  • Whittier: September 18 – September 24
  • Cordova: September 25 – October 6
slide-11
SLIDE 11

Page 11 of 23

  • October 9: Alyeska IMT developed first 12 hours of

documentation for PWS Tanker Exercise

  • October 10: Alyeska SERVS completed demonstration

exercises in greater than 20 knot winds (Note: this demonstration completes transition plan exercises)

  • October 10‐11: PWS Tanker Exercise with Crowley Alaska

Tankers

  • November 5‐6: ADEC unannounced PWS Tanker Exercise
  • December 17: ADEC inspection of OSRB‐2
  • Total 2018 transition / assurance tug and barge deployments

completed: 215

January 24, 2019

2018 Drills, Exercises and Training

4Q Exercise Highlights

slide-12
SLIDE 12

Page 12 of 23

  • January 9 & 16: ICS 305 / 307 training for resource ordering

and ICS 204s

  • March 4: Non‐mechanical Airborne Dispersant Delivery

System (ADDS) Pack training exercise in Valdez

  • March 9: Veterinary technician (Otter Rehab) training in

Anchorage

  • March 26: VMT IMT training exercise
  • May 8: VMT IMT exercise
  • Week of October 7: BP PWS tanker exercise
  • Continued increased ECO assurance activities

January 24, 2019

2019 Drills, Exercises and Training

Upcoming 2019 Exercise Highlights

slide-13
SLIDE 13

Page 13 of 23

  • VMT coordination group quarterly meetings
  • VMT contingency plan renewal application
  • Submitted for sufficiency review on November 5, 2018
  • Public review period: November 23, 2018 – January 7, 2019
  • VMT contingency plan routine amendment to address

Qualified Individual (QI) changes effective January 1

  • Routine amendment application submitted on January 2, 2019

January 24, 2019

2019 Look Ahead

Contingency Plan Activities

slide-14
SLIDE 14

VMT 2018 Projects Highlights

X218 – 2018 Tank Inspection and Maintenance Program

  • Completed exterior coating of Tank 94 (Ballast Water Tank)
  • Completed API 653 internal inspection of Tank 56 (Diesel Storage Tank)

Z716 – Below Ground Crude Oil Piping Internal Inspection

  • Completed 19 pig runs (10 runs “A” header, 9 runs “B” header); < 5

gallons wax removed

  • Inspection data revealed the system is good for operation
  • Dual off‐take scope execution underway; commissioning in 2019

Z735 – Valdez Facilities Bird Deterrent

  • ERB proof‐of‐concept laser was not successful; new conceptual design

for ERB roof in progress for 2019 execution

  • Installation and repair of deterrents will continue in 2019

Page 14 of 23 January 24, 2019

slide-15
SLIDE 15

VMT 2018 Projects Highlights

Z761 – 2018 Ballast Header Inspection and Repair

  • Completed internal cleaning, inspection, testing and repair of the 42”

ballast header piping for Berth 5, “A” header, and the Tank 93 branch leg (~7200 ft. of piping)

  • Remaining “A” header work to be completed in 2019

Z758 – VMT IWWS Trunk Line Lifecycle Repairs

  • HDPE piping sliplined in existing ductile iron pipe (~2000 ft.); 7

manholes replaced or repaired; 1 manhole eliminated

  • Installed vapor sensors in MH‐2‐22 (westernmost manhole on PDC

road)

Z748 – VMT Berth Crude Block Valves Replacement

  • Installed and commissioned 4 new Chromatic dual off‐set full port ball

valves on Berth 5

  • Berth 4 valves to be installed in 2019

Page 15 of 23 January 24, 2019

slide-16
SLIDE 16

VMT 2018 Projects Highlights

Z751 – VMT Berth Fisher Control Valves Replacement

  • Installed and commissioned 4 Fisher Pressure Indicating Control Valves

(PICVs) on Berth 5

  • Berth 4 valves to be installed in 2019

Z738 – Replace Incinerator Waste Gas Shutdown Valves

  • Replaced 14 obsolete valves and actuators on the vapor recovery

system

  • Achieves Safety Integrity Level (SIL) 2 system rating

Z739 – DAF Vapor System Emergency Shutdown and Ventilation

  • Stack and generator concrete pads completed in 2018
  • Install and commission equipment and instrumentation in 2019

Page 16 of 23 January 24, 2019

slide-17
SLIDE 17

VMT 2019 Projects Summary

X219 – 2019 Tank Inspection and Maintenance Program

  • API 653 internal inspection of Tank 8 (Crude Storage Tank)
  • Exterior coating of Tank 93 (Ballast Water Tank) and Tank 10 (Crude

Storage Tank)

Page 17 of 23 January 24, 2019

slide-18
SLIDE 18

VMT 2019 Projects Summary

Z716 – Below Ground Crude Oil Piping Internal Inspection (Dual Off‐ takes)

  • Install 36‐inch dual off‐take piping and valves upstream of the East

Metering facility

  • Requires pipeline shutdown for commissioning (June 2019)

Page 18 of 23 January 24, 2019 Dual off‐takes final design rendering 2 ea. 36” valves installed in fall 2018

slide-19
SLIDE 19

VMT 2019 Projects Summary

Z762 – 2019 Ballast Header Inspection and Repair

  • Clean, inspect and repair the ballast header piping from BWT West

Manifold to the “B” header termination vault

  • Shortest section of inspection program piping (~740 ft.)

Page 19 of 23 January 24, 2019 West Manifold

slide-20
SLIDE 20

VMT 2019 Projects Summary

Z586 – Berths 4 and 5 EMAC (Electronic Measurement and Control) Replacement

  • Replace existing Daniels Metering systems with a new site‐specific

Omni EMAC system for Berths 4 and 5 at the West Metering Facility

  • Requires a short shutdown for system conversion on each berth

Page 20 of 23 January 24, 2019 West Metering existing Daniels Metering system

slide-21
SLIDE 21

VMT 2019 Projects Summary

Z769 – Replace VMT Pig Receiver Isolation Valves

  • Replace the 48‐inch (58‐MOV‐001) and 36‐inch (58‐MOV‐003) scraper

trap isolation valves at the East Metering facility

  • Installation planned during the August 2019 pipeline shutdown

Page 21 of 23 January 24, 2019 East Metering pig trap isolation valves

slide-22
SLIDE 22

VMT 2019 Projects Summary

Z770 – Ship Loading Vapor Collection Life Cycle Replacement

  • Extend life of existing Fenwal systems on Berths 4 and 5
  • Bulk purchase replacement infrared detectors, controllers and chassis

Page 22 of 23 January 24, 2019 Berth causeway

slide-23
SLIDE 23
  • X. Project Management Improvements

23