valdez operations overview
play

Valdez Operations Overview Alyeska Pipeline Service Company Prince - PowerPoint PPT Presentation

Valdez Operations Overview Alyeska Pipeline Service Company Prince William Sound Regional Citizens Advisory Council Board Meeting January 24, 2019 Anchorage, Alaska January 24, 2019 VMT Operations 2018* Tankers Loaded 247 Tankers Escorted


  1. Valdez Operations Overview Alyeska Pipeline Service Company Prince William Sound Regional Citizens Advisory Council Board Meeting January 24, 2019 Anchorage, Alaska January 24, 2019

  2. VMT Operations 2018* Tankers Loaded 247 Tankers Escorted 255 Barrels Loaded 178,137,687 Since Startup Tankers Loaded 22,407 Tankers Escorted 13,710 Barrels Loaded 17,120,939,370 * As of 12/31/18 January 24, 2019 Page 2 of 23

  3. Health-Safety-Environment Valdez Operations Safety 2018 Days Away From Work Cases 0 TAPS Combined Recordable Incident Rate % 0.27 Environment 2018 Spill Volume (Gallons) 217.2862 (12.2862*) Number of Spills 10 * Outside containment January 24, 2019 Page 3 of 23

  4. Alyeska Organizational Update January 24, 2019 Page 4 of 23

  5. Alyeska Organizational Update January 24, 2019 Page 5 of 23

  6. Alyeska Organizational Update January 24, 2019 Page 6 of 23

  7. Alyeska Organizational Update Operations and Maintenance Division January 24, 2019 Page 7 of 23

  8. Alyeska Organizational Update Engineering and Risk Division January 24, 2019 Page 8 of 23

  9. Fishing Vessel Availability End of 4 th quarter 2018 Port Tier 1 Tier 2 Valdez 21 23 Cordova 32 (7RR) 115 Whittier 6 23 Seward 30 Homer 55 Kodiak 39 TOTAL 59 285 *RR = Rapid Response January 24, 2019 Page 9 of 23

  10. SERVS Highlights 2019 Fishing Vessel Training  Spring Fishing Vessel Training  Kodiak: March 27 – April 2  Homer: April 3 – April 9  Seward: April 10 – April 14  Cordova: April 15 – April 26  Valdez: April 27 – May 3  Fall Fishing Vessel Training  Whittier: September 18 – September 24  Cordova: September 25 – October 6 January 24, 2019 Page 10 of 23

  11. 2018 Drills, Exercises and Training 4Q Exercise Highlights  October 9: Alyeska IMT developed first 12 hours of documentation for PWS Tanker Exercise  October 10: Alyeska SERVS completed demonstration exercises in greater than 20 knot winds (Note: this demonstration completes transition plan exercises)  October 10 ‐ 11: PWS Tanker Exercise with Crowley Alaska Tankers  November 5 ‐ 6: ADEC unannounced PWS Tanker Exercise  December 17: ADEC inspection of OSRB ‐ 2  Total 2018 transition / assurance tug and barge deployments completed: 215 January 24, 2019 Page 11 of 23

  12. 2019 Drills, Exercises and Training Upcoming 2019 Exercise Highlights  January 9 & 16: ICS 305 / 307 training for resource ordering and ICS 204s  March 4: Non ‐ mechanical Airborne Dispersant Delivery System (ADDS) Pack training exercise in Valdez  March 9: Veterinary technician (Otter Rehab) training in Anchorage  March 26: VMT IMT training exercise  May 8: VMT IMT exercise  Week of October 7: BP PWS tanker exercise  Continued increased ECO assurance activities January 24, 2019 Page 12 of 23

  13. 2019 Look Ahead Contingency Plan Activities  VMT coordination group quarterly meetings  VMT contingency plan renewal application  Submitted for sufficiency review on November 5, 2018  Public review period: November 23, 2018 – January 7, 2019  VMT contingency plan routine amendment to address Qualified Individual (QI) changes effective January 1  Routine amendment application submitted on January 2, 2019 January 24, 2019 Page 13 of 23

  14. VMT 2018 Projects Highlights X218 – 2018 Tank Inspection and Maintenance Program  Completed exterior coating of Tank 94 (Ballast Water Tank)  Completed API 653 internal inspection of Tank 56 (Diesel Storage Tank) Z716 – Below Ground Crude Oil Piping Internal Inspection  Completed 19 pig runs (10 runs “A” header, 9 runs “B” header); < 5 gallons wax removed  Inspection data revealed the system is good for operation  Dual off ‐ take scope execution underway; commissioning in 2019 Z735 – Valdez Facilities Bird Deterrent  ERB proof ‐ of ‐ concept laser was not successful; new conceptual design for ERB roof in progress for 2019 execution  Installation and repair of deterrents will continue in 2019 January 24, 2019 Page 14 of 23

  15. VMT 2018 Projects Highlights Z761 – 2018 Ballast Header Inspection and Repair  Completed internal cleaning, inspection, testing and repair of the 42” ballast header piping for Berth 5, “A” header, and the Tank 93 branch leg (~7200 ft. of piping)  Remaining “A” header work to be completed in 2019 Z758 – VMT IWWS Trunk Line Lifecycle Repairs  HDPE piping sliplined in existing ductile iron pipe (~2000 ft.); 7 manholes replaced or repaired; 1 manhole eliminated  Installed vapor sensors in MH ‐ 2 ‐ 22 (westernmost manhole on PDC road) Z748 – VMT Berth Crude Block Valves Replacement  Installed and commissioned 4 new Chromatic dual off ‐ set full port ball valves on Berth 5  Berth 4 valves to be installed in 2019 January 24, 2019 Page 15 of 23

  16. VMT 2018 Projects Highlights Z751 – VMT Berth Fisher Control Valves Replacement  Installed and commissioned 4 Fisher Pressure Indicating Control Valves (PICVs) on Berth 5  Berth 4 valves to be installed in 2019 Z738 – Replace Incinerator Waste Gas Shutdown Valves  Replaced 14 obsolete valves and actuators on the vapor recovery system  Achieves Safety Integrity Level (SIL) 2 system rating Z739 – DAF Vapor System Emergency Shutdown and Ventilation  Stack and generator concrete pads completed in 2018  Install and commission equipment and instrumentation in 2019 January 24, 2019 Page 16 of 23

  17. VMT 2019 Projects Summary X219 – 2019 Tank Inspection and Maintenance Program  API 653 internal inspection of Tank 8 (Crude Storage Tank)  Exterior coating of Tank 93 (Ballast Water Tank) and Tank 10 (Crude Storage Tank) January 24, 2019 Page 17 of 23

  18. VMT 2019 Projects Summary Z716 – Below Ground Crude Oil Piping Internal Inspection (Dual Off ‐ takes)  Install 36 ‐ inch dual off ‐ take piping and valves upstream of the East Metering facility  Requires pipeline shutdown for commissioning (June 2019) Dual off ‐ takes final design rendering 2 ea. 36” valves installed in fall 2018 January 24, 2019 Page 18 of 23

  19. VMT 2019 Projects Summary Z762 – 2019 Ballast Header Inspection and Repair  Clean, inspect and repair the ballast header piping from BWT West Manifold to the “B” header termination vault  Shortest section of inspection program piping (~740 ft.) West Manifold January 24, 2019 Page 19 of 23

  20. VMT 2019 Projects Summary Z586 – Berths 4 and 5 EMAC (Electronic Measurement and Control) Replacement  Replace existing Daniels Metering systems with a new site ‐ specific Omni EMAC system for Berths 4 and 5 at the West Metering Facility  Requires a short shutdown for system conversion on each berth West Metering existing Daniels Metering system January 24, 2019 Page 20 of 23

  21. VMT 2019 Projects Summary Z769 – Replace VMT Pig Receiver Isolation Valves  Replace the 48 ‐ inch (58 ‐ MOV ‐ 001) and 36 ‐ inch (58 ‐ MOV ‐ 003) scraper trap isolation valves at the East Metering facility  Installation planned during the August 2019 pipeline shutdown East Metering pig trap isolation valves January 24, 2019 Page 21 of 23

  22. VMT 2019 Projects Summary Z770 – Ship Loading Vapor Collection Life Cycle Replacement  Extend life of existing Fenwal systems on Berths 4 and 5  Bulk purchase replacement infrared detectors, controllers and chassis Berth causeway January 24, 2019 Page 22 of 23

  23. QUESTIONS? January 24, 2019 Page 23 of 23 X. Project Management Improvements 23

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend