UTAH LAKESHORE TRAIL HOTPOTS AND AMANDA LANE UDOT PIN 14987 UTAH - - PowerPoint PPT Presentation

utah lakeshore trail
SMART_READER_LITE
LIVE PREVIEW

UTAH LAKESHORE TRAIL HOTPOTS AND AMANDA LANE UDOT PIN 14987 UTAH - - PowerPoint PPT Presentation

UTAH LAKESHORE TRAIL HOTPOTS AND AMANDA LANE UDOT PIN 14987 UTAH LAKESHORE TRAIL HOTPOTS AND AMANDA LANE Hotpots Segment: 4,500 feet (0.08 miles) Amanda Lane Segment: 3,600 feet (0.07 miles) Completes gaps Continuous


slide-1
SLIDE 1

UTAH LAKESHORE TRAIL

HOTPOTS AND AMANDA LANE

UDOT PIN 14987

slide-2
SLIDE 2

UTAH LAKESHORE TRAIL

HOTPOTS AND AMANDA LANE

Lars Gail Nathan Zach Geoff Aaron

  • Hotpots Segment: 4,500 feet (0.08 miles)
  • Amanda Lane Segment: 3,600 feet

(0.07 miles)

  • Completes gaps
  • Continuous trail
  • Contributes to goal
  • Included in State and Regional active

transportation plans

slide-3
SLIDE 3

Project Progress

  • Trail design at 90%
  • CatEx complete
  • Public meetings
  • Agreements
  • Section 404 Application submitted - permit pending
slide-4
SLIDE 4

Wetland Impacts

  • Hotpots Segments: 1.38 acres
  • Amanda Lane Segments: 1.55 acres
  • Total = 2.93 acres

Hotpots Segment Amanda Lane Segment

slide-5
SLIDE 5

Cost Estimates

Original Cost Estimate: $996,000.00 (funded by UDOT/MAG) Updated Cost Estimate: $1,296,000.00 (6.77% match included) *Items not included in original scope: 1) Boardwalk EPA Site, 2) Mitigation Site, and 3) Stormwater Permitting.

slide-6
SLIDE 6

Boardwalk

  • Boardwalk
  • Wetlands
  • $120,000.00 cost
slide-7
SLIDE 7

Wetland Mitigation Site

  • Wetland Mitigation
  • Restoration
  • Removal
  • Planting
slide-8
SLIDE 8

Wetland Mitigation Site

Existing Condition Proposed Restoration

slide-9
SLIDE 9

Drainage/Stormwater Improvement

  • Current discharge
  • FFSL requirements
  • Cut ditch
  • Consolidation
  • Permits
slide-10
SLIDE 10

Request For Funding

  • Additional $300,000.00 ($96,000.00 from

MAG contingency, $204,000.00 from Utah County funds)

  • Total funding $1,260,000.00
  • Construction in winter 2019/2020
  • Trail open in June 2020