US20 / US97 BEND NORTH CORRIDOR PEO October 28, 2019 US20 / US97 - PowerPoint PPT Presentation

US20 / US97 BEND NORTH CORRIDOR PEO October 28, 2019 US20 / US97 BEND NORTH CORRIDOR US20 / US97 BEND NORTH CORRIDOR GOALS Reduce congestion on US97 & US20 Reduce overall crash rate & severity throughout corridor Reduce


  1. US20 / US97 BEND NORTH CORRIDOR PEO October 28, 2019

  2. US20 / US97 BEND NORTH CORRIDOR

  3. US20 / US97 BEND NORTH CORRIDOR GOALS • Reduce congestion on US97 & US20 • Reduce overall crash rate & severity throughout corridor • Reduce truck-related crashes at intersections • Increase travel time reliability • Improve bicycle and pedestrian access US97/Cooley Road and US97/Robal Intersections are listed in the top five percent of ODOT’s Safety Priority Index System Today US97 is congested almost 50% of the time within the corridor. By 2040 traffic within the corridor will grow by over 50 percent.

  4. FEDERAL ENVIRONMENTAL IMPACT STATEMENT (2013) • Realign US97 to the east • Existing US97 to become 3 rd Street (Frontage Road) • US97 / Cooley separated crossing • US20 @ Cooley and Robal intersection improvements • Various local connections & intersection improvements • Approximate total Cost +$275 Million

  5. HB2017 • Earmarked $50 Million for US97 Cooley Road Mid-Term Improvements Phas Phase Budge udget PE $5 Million RW $8 Million CN $37 Million • Preliminary Engineering 2021 • Construction 2024

  6. INFRASTRUCTURE FOR AMERICA (INFRA) Grant Award • INFRA Request - $66.7 Million • Actual Award - $60.4 Million • Total with Match - $133.4 Million • ODOT, City of Bend, Deschutes County, & Private Development • INFRA Requirements o Realign US97 o US97/BNSF/Cooley Improvements o US 20/Cooley Improvements o Construction Funds Obligated by Sept. 2022 o Agreement/Term Sheet Pending

  7. FEDERAL ENVIRONMENTAL IMPACT STATEMENT (2013) • Record of Decision – 2014 • Renewal Required for current project • Scope Refinements to fit budget and FEIS intent

  8. US97 CORRIDOR Budget - Appx. $125-140 Million -Realign Northbound & Southbound US97 to east -Grade Separated Crossing @ Cooley -Extension of 3 rd St. to Existing US97

  9. US20 CORRIDOR Budget - Appx. $35 Million -4 Dual Lane Roundabouts -Dual EB & WB Lanes -Raised Median -Pavement Preservation -Construction 2022

  10. DESIGN/BUILD DELIVERY • Not Widely Used (at ODOT) • Procurement, Specs, Administration Guidelines need to be refreshed • Working with DOT partners

  11. Next Steps • MPO Policy Board Governance • R/W Acquisition of new US97 Alignment • Complete traffic analysis on related elements • Identify & prioritize additional improvements in North Corridor • Public/Stakeholder Awareness & Outreach

  12. MOVING FORWARD* • Public Notification/Involvement • ROD Renewal • Winter 2019 to Early 2020 • Winter 2020 • RFQ/RFP/Award • Construction Expected to be 2 seasons • No later than spring 2021 • Award by Spring 2022 *All dates subject to change

  13. QUESTIONS?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.