US-69 McAlester US-69 from the US-270 junction south approximately - - PowerPoint PPT Presentation

us 69 mcalester
SMART_READER_LITE
LIVE PREVIEW

US-69 McAlester US-69 from the US-270 junction south approximately - - PowerPoint PPT Presentation

US-69 McAlester US-69 from the US-270 junction south approximately 2 miles to Fourteenth Street, including the Village Road (Kinkead Road) interchange and adjacent frontage roads. Anthony Echelle, P.E. ODOT Division II Engineer Project Area


slide-1
SLIDE 1

US-69 McAlester

US-69 from the US-270 junction south approximately 2 miles to Fourteenth Street, including the Village Road (Kinkead Road) interchange and adjacent frontage roads.

Anthony Echelle, P.E. ODOT Division II Engineer

slide-2
SLIDE 2

Project Area Base Image

slide-3
SLIDE 3

Project Area Overview

slide-4
SLIDE 4

US-69 McAlester

  • The purpose of this

meeting is to present the proposed design to obtain public input to aid the Department in moving forward with the completion of the environmental studies, design, and construction.

  • Project History
  • Current Functional

Plans

  • Approved EA with

FONSI

  • Proposed Changes
  • Construction Phases
  • Reasons Why
  • Proposed Changes
slide-5
SLIDE 5

Project History

  • 1996 Public Meeting
  • 2001 Public Meeting
  • 2003 EA/FONSI

Approved

  • 2004 Functional Plans

Approved

  • 2008 Right-of-way &

Utility Plans (Comanche)

  • 2009-to-Present

Comanche R/W Acquired & Utilities Relocated

  • Due To The Following

Factors the Design is Being Re-Evaluated

  • Construction Costs
  • Constructability
  • Changing Traffic

Conditions

  • Public Comments and

Requests

slide-6
SLIDE 6

Proposed Changes

  • Comanche Avenue Project
  • Keep the Bridge / Ramps / Frontage Road design north of

Comanche

  • Eliminate the depressed section of US-69 and the turn-

around bridge between Comanche & Peaceable

  • Reconstruct US-69 near existing grade
  • Village Road (Kinkead) Project
  • Frontage Roads
  • Extend US-69 / Ramps / Frontage Roads reconstruction

almost to Fourteenth Street

  • Construct Village Road Interchange (with turnaround

lanes) south of the present intersection

  • Add another northbound exit ramp
  • Convert to one-way as construction phases are completed
slide-7
SLIDE 7

Comanche Project Overview (Previous)

slide-8
SLIDE 8

Keep Bridge / Ramp / Roads as Designed North of Comanche

slide-9
SLIDE 9

Eliminate Depressed US-69

slide-10
SLIDE 10

Eliminate the Turnaround Bridge

slide-11
SLIDE 11

Comanche Project Proposed Typical Section

slide-12
SLIDE 12

Comanche Project Overview (New)

slide-13
SLIDE 13

Ramps / Bridges / Roads Keep the Design North of Comanche

slide-14
SLIDE 14

Comanche Project Overview (New)

slide-15
SLIDE 15

US-69 Peaceable-to-Comanche at end of Phase 1

slide-16
SLIDE 16

Village Road (Kinkead) Functional Plan Overview (Previous)

slide-17
SLIDE 17

Village Road (Kinkead) Functional Plan Overview (Previous)

slide-18
SLIDE 18

Village Road Project Proposed Typical Section

slide-19
SLIDE 19

Village Road Project Overview Phase 1 (New)

slide-20
SLIDE 20

Project Extends almost to 14th Street with new ramps

slide-21
SLIDE 21

Village Road Project Overview Phase 1 (New)

slide-22
SLIDE 22

Village Road Interchange South

  • f Present Intersection
slide-23
SLIDE 23

Village Road Project – Interchange Bridge with Turnaround Lanes

slide-24
SLIDE 24

Village Road Project – Interchange Bridge with Turnaround Lanes

slide-25
SLIDE 25

Village Road Project Overview Phase 1 (New)

slide-26
SLIDE 26

Add 2nd Northbound Exit Ramp

slide-27
SLIDE 27

Village Road Project Overview Phase 1 (New)

slide-28
SLIDE 28

Ramps North of Village Road

slide-29
SLIDE 29

Village Road Project Overview Phase 2 (New)

slide-30
SLIDE 30

Finished Project Peaceable to Comanche

slide-31
SLIDE 31

Environmental Studies Update

  • Environmental Assessment (EA) & Finding
  • f No Significant Impact (FONSI) issued

by FHWA in 2003

  • Re-Assessment of existing EA document
  • Public & agency involvement
  • Public meeting
  • Agency solicitations
  • Updated Studies
  • Re-Assessment will determine if the findings
  • f the original EA still apply
slide-32
SLIDE 32

Environmental Studies Update

  • Updated Studies to be completed for:
  • Relocation impacts
  • Noise impacts
  • Wetland impacts
  • Threatened and endangered species
  • Cultural resources
  • Floodplain impacts
  • Hazardous waste issues
  • Cultural Resources
  • Tribal Concerns
slide-33
SLIDE 33

Environmental Studies Update

  • Residential and Commercial Properties
  • Based on final plans
  • Parks & Recreational Areas
  • None identified
slide-34
SLIDE 34

Environmental Studies Update

  • Noise Study
  • A noise study will be completed in

accordance with ODOT noise policy.

  • FHWA Traffic Noise Model to predict existing &

future noise levels.

  • FHWA approved sound level meter for field

measurements will be conducted to validate the noise model.

  • The majority of the land use adjacent to the project

is commercial.

  • The noise study will include those noise sensitive

receivers such as homes, apartments, schools, parks, places of worship, etc. nearest the project.

slide-35
SLIDE 35

Environmental Studies Update

  • Wetlands and Stream Impacts
  • Section 404 permit with Army Corps of

Engineers

  • Threatened & Endangered Species
  • American Burying Beetle
  • Northern Long Eared Bat
  • Interior Least Tern
  • Piping Plover
  • Red Knot
  • Sprague’s Pit
slide-36
SLIDE 36

Environmental Studies Update

  • Floodplain
  • Project will not increase base flood

elevation or require flood map revisions.

  • Hazardous Waste Study
  • Cultural Resources & Archeological Sites
  • Tribal Consultation
  • Coordinate with State Historic Preservation Office

and Oklahoma Archeological Survey

  • No historic properties or archaeological sites

affected in original EA

slide-37
SLIDE 37

Next Steps in Process

  • Comanche Project
  • Right-of-Way and Utilities Relocation

Complete

  • Public Comment
  • Move Forward with Final Design
  • 2016 Begin Construction
slide-38
SLIDE 38

Next Steps in Process

  • Village Road Project
  • Public Comment
  • Update Environmental Studies
  • Move Forward with Design
  • 2017 Right-of-Way and Utilities Relocation
  • 2017 Utilities Relocation Complete
  • 2019 Begin Construction
slide-39
SLIDE 39

US-69 McAlester

  • More information is available online at

www.odot.org/publicmeetings

  • Comments may be provided as follows:
  • Leave your comment form here tonight
  • Download and fill out a form online
  • Mail or fax forms to ODOT at:

Oklahoma Department of Transportation Environmental Programs Division 200 NE 21st Street Oklahoma City, OK 73015 Fax No. (405) 522-5193 Email comment to : odot-environment@odot.org

Questions / Comments Comments are due by: November 19, 2015