SLIDE 4 UpTown Waterloo - Southbound Loop
Caroline, from Erb to Allen and on Allen, from Caroline to King
4
- In September 2014, GrandLinq began to relocate and
upgrade existing utilities on Caroline, from Erb to Allen. This work will continue in spring
- In spring 2015, GrandLinq will relocate and upgrade
existing utilities on Allen, from Caroline to King
- Caroline is expected to be paved in spring 2015
- Allen is expected to be paved in summer 2015
- Work to build the rest of the ION infrastructure will
then begin (i.e., final curbs and LRT tracks, poles and
- verhead wires that bring power to the train)
- This work involves lane restrictions, not road
closures
- Work in the North Parking Lot to prepare the ground
for the LRT trackway will begin spring 2015
- Work to re-locate the railway tracks at the Caroline/Erb
intersection will begin summer 2015