update
play

Update June, 2019 SEMCO Energy Gas Company Natural gas utility - PowerPoint PPT Presentation

Marquette Connector Update June, 2019 SEMCO Energy Gas Company Natural gas utility serving approximately 300,000 customers throughout Michigan 150 miles of transmission line 6,000 miles of distribution main 2 Marquette


  1. Marquette Connector Update June, 2019

  2. SEMCO Energy Gas Company • Natural gas utility serving approximately 300,000 customers throughout Michigan • 150 miles of transmission line • 6,000 miles of distribution main 2

  3. Marquette Connector Pipeline Northern Natural Gas SEMCO Proposed Pipeline Great Lakes Pipelines SEMCO Dist. Mains Northern Natural Gas TransCanada’s Great Lakes Pipelines 3

  4. Marquette Connector Pipeline Route The 20” Pipeline • Southern end begins near Arnold, Michigan • Extends north parallel to the ATC Corridor to near Gwinn, Michigan • Progresses northeast toward the Marquette County Sawyer Airport • Extends parallel to the CN Railway & NNG corridor to the NNG interconnect near the intersection of M-35 and County Rd. 480 The 10” Pipeline • Begins near County Rd. 480 near the existing ATC corridor • Extends north, then east along the UPPCO corridor to M-553 • Follows the road into Marquette 4

  5. MCP Benefits • 42-mile pipeline linking the existing NNG pipeline with the Great Lakes Gas Transmission system also running through the U.P. – Provides much needed “back - up” source of natural gas needed to reliably meet the area’s energy demands – Expands the area’s tax base – Greatly enhances the reliability and security of the natural gas delivery system in the U.P. – Expands the tax base • New tax dollars to invest in roads, schools, public safety and other local needs – Accommodates future growth and economic development • Energy stability = economic stability • An attractive selling point for business leaders and investors • Provides the added capacity the region needs to grow 5

  6. Administrative Update Regulatory Approval (Act-9) – Received August, 2017 Right of Way acquisition- completed – Pipeline crosses approximately 220 parcels and 122 landowners – The majority of property acquisition was completed in 2018 – The remaining parcels were completed in 2019 Cost Recovery – Will be determined in SEMCO’s current rate case 6

  7. Project Status A snowy winter in Marquette ROW flag tied to a branch in February is about 14’ off the ground in May. 7

  8. Construction Update • Pipeline construction is underway and on schedule – Tree felling was completed in May, 2019 – Pipeline construction began in June, 2019 • In service expected in November, 2019 – Ahead of our original schedule – Full Cleanup scheduled in 2019 – Some remediation may extend into 2020 8

  9. Details • 20” Pipeline – 76% of pipeline follows existing electrical or pipeline corridors – Land use is rural forest, low density-residential, mostly flat • 10” Pipeline – 66% of the pipeline follows existing electrical, pipeline and road ROW – Land use is rural forest, low density residential – Does enter Marquette city limits in order to connect with SEMCO’s existing infrastructure 9

  10. Pipe at Sawyer storage location Dun Transportation and Stringing excavator with vacuum pipe handling attachment adjacent to 20” Quadruple Random Length (QRL/80’) pipe stacked at Sawyer pipe yard 10

  11. Construction Mat Storage Price Gregory International mat yard at Sawyer storing approximately 14,000 mats 11

  12. Environmental • Marquette Connector Pipeline is being constructed to have minimal impact on the environment – Brush and trees have been cleared to accommodate construction • No permanently filled wetlands • Environmental inspections are taking place throughout construction to ensure conformance environmental best practices and compliance with all permitting requirements 12

  13. Local Impact • SEMCO is striving to minimize the impact of construction – Working with local areas to manage the impact when it occurs • NTN Trails • Marquette Trails Festival 13

  14. Questions 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend