Update June, 2019 SEMCO Energy Gas Company Natural gas utility - - PowerPoint PPT Presentation

update
SMART_READER_LITE
LIVE PREVIEW

Update June, 2019 SEMCO Energy Gas Company Natural gas utility - - PowerPoint PPT Presentation

Marquette Connector Update June, 2019 SEMCO Energy Gas Company Natural gas utility serving approximately 300,000 customers throughout Michigan 150 miles of transmission line 6,000 miles of distribution main 2 Marquette


slide-1
SLIDE 1

Marquette Connector Update

June, 2019

slide-2
SLIDE 2

SEMCO Energy Gas Company

  • Natural gas utility

serving approximately 300,000 customers throughout Michigan

  • 150 miles of

transmission line

  • 6,000 miles of

distribution main

2

slide-3
SLIDE 3

Marquette Connector Pipeline

3

TransCanada’s Great Lakes Pipelines Northern Natural Gas Northern Natural Gas SEMCO Proposed Pipeline Great Lakes Pipelines SEMCO Dist. Mains

slide-4
SLIDE 4

Marquette Connector Pipeline Route

The 20” Pipeline

  • Southern end begins near Arnold,

Michigan

  • Extends north parallel to the ATC

Corridor to near Gwinn, Michigan

  • Progresses northeast toward the

Marquette County Sawyer Airport

  • Extends parallel to the CN Railway &

NNG corridor to the NNG interconnect near the intersection of M-35 and County Rd. 480 The 10” Pipeline

  • Begins near County Rd. 480 near the

existing ATC corridor

  • Extends north, then east along the

UPPCO corridor to M-553

  • Follows the road into Marquette

4

slide-5
SLIDE 5
  • 42-mile pipeline linking the existing NNG pipeline with the

Great Lakes Gas Transmission system also running through the U.P.

– Provides much needed “back-up” source of natural gas needed to reliably meet the area’s energy demands – Expands the area’s tax base – Greatly enhances the reliability and security of the natural gas delivery system in the U.P. – Expands the tax base

  • New tax dollars to invest in roads, schools, public safety and other local needs

– Accommodates future growth and economic development

  • Energy stability = economic stability
  • An attractive selling point for business leaders and investors
  • Provides the added capacity the region needs to grow

5

MCP Benefits

slide-6
SLIDE 6

Regulatory Approval (Act-9)

– Received August, 2017

Right of Way acquisition- completed

– Pipeline crosses approximately 220 parcels and 122 landowners – The majority of property acquisition was completed in 2018 – The remaining parcels were completed in 2019

Cost Recovery

– Will be determined in SEMCO’s current rate case

6

Administrative Update

slide-7
SLIDE 7

7

Project Status

A snowy winter in Marquette ROW flag tied to a branch in February is about 14’ off the ground in May.

slide-8
SLIDE 8

8

Construction Update

  • Pipeline construction is underway and on schedule

– Tree felling was completed in May, 2019 – Pipeline construction began in June, 2019

  • In service expected in November, 2019

– Ahead of our original schedule – Full Cleanup scheduled in 2019 – Some remediation may extend into 2020

slide-9
SLIDE 9
  • 20” Pipeline

– 76% of pipeline follows existing electrical or pipeline corridors – Land use is rural forest, low density-residential, mostly flat

  • 10” Pipeline

– 66% of the pipeline follows existing electrical, pipeline and road ROW – Land use is rural forest, low density residential – Does enter Marquette city limits in order to connect with SEMCO’s existing infrastructure

9

Details

slide-10
SLIDE 10

10

Pipe at Sawyer storage location

Dun Transportation and Stringing excavator with vacuum pipe handling attachment adjacent to 20” Quadruple Random Length (QRL/80’) pipe stacked at Sawyer pipe yard

slide-11
SLIDE 11

11

Construction Mat Storage

Price Gregory International mat yard at Sawyer storing approximately 14,000 mats

slide-12
SLIDE 12
  • Marquette Connector Pipeline is being constructed

to have minimal impact on the environment

– Brush and trees have been cleared to accommodate construction

  • No permanently filled wetlands
  • Environmental inspections are taking place

throughout construction to ensure conformance environmental best practices and compliance with all permitting requirements

12

Environmental

slide-13
SLIDE 13
  • SEMCO is striving to minimize the impact of

construction

– Working with local areas to manage the impact when it

  • ccurs
  • NTN Trails
  • Marquette Trails Festival

13

Local Impact

slide-14
SLIDE 14

14

Questions