Update on Canadian Forces GBHEC PoD Study to MAPoDWG 20 April 2007 - - PowerPoint PPT Presentation

update on canadian forces gbhec pod study to mapodwg 20
SMART_READER_LITE
LIVE PREVIEW

Update on Canadian Forces GBHEC PoD Study to MAPoDWG 20 April 2007 - - PowerPoint PPT Presentation

Aerospace and Telecommunications Engineering Support Squadron Update on Canadian Forces GBHEC PoD Study to MAPoDWG 20 April 2007 Capt DJ Butcher NDTO/SMM 27 Feb 2007 Outline Past Updates ASNT 2006 Progress to Date (BHEC real)


slide-1
SLIDE 1

Aerospace and Telecommunications Engineering Support Squadron

Capt DJ Butcher NDTO/SMM 27 Feb 2007

Update on Canadian Forces GBHEC PoD Study to MAPoDWG 20 April 2007

slide-2
SLIDE 2

Outline

  • Past Updates
  • ASNT 2006
  • Progress to Date (BHEC real)
  • Remaining Work (BHEC Modeling)
  • Future Research
  • Conclusion
slide-3
SLIDE 3

Past Updates

  • Originally presented work to

MAPoDWG at ATA 2005

– Focus of project on updating current a90/95 assumption of 0.050” and to investigate modeling PoD

  • Further presentations have been

made at:

– Aging Aircraft 2006 – ASNT Fall 2006 (presented by NRC)

  • Project completion planned for End

Jun 2007

slide-4
SLIDE 4

ASNT 2006

  • Fatiguing of panels

completed and cracks developed

– Crack sizing in progress

  • Coupons being water-

jet cut from panels

– in progress

  • Blank coupons
  • In process of labeling
  • Coupons with EDM

notches

– In progress of notching

slide-5
SLIDE 5

Progress to Date (BHEC Real)

  • 1st set of coupons have been

assembled into 16 boxes (26 coupons per box) and inspected by 24 different CGSB Level 2 NDT Techs

– 1st layer 0.090” – 2nd layer 0.312” – 71 lab grown cracks

  • Measured by acetate replicas
  • Crack density reported at ASNT 2006
  • Lengths being confirmed by fracto

– 35 EDM notches – 362 blanks – Cracks and EDM notches located on the corner of the 2nd layer faying surface

slide-6
SLIDE 6

Progress to Date (BHEC Real)

Laregst crack missed by different inspector (IAR 0.3125" Corner Cracks)

0.01 2 0.01 6 0.009 0.009 0.01 2 0.009 0.021 0.023 0.009 0.009 0.009 0.009 0.002 0.009 0.004 0.009 0.009 0.009 0.028 0.01 1 0.022 0.023 0.009 0.009

0.000 0.003 0.006 0.009 0.012 0.015 0.018 0.021 0.024 0.027 0.030 L-1 N-1 S-1 V-1.0 U-1.3 C-1.8 F-2 K-2 M-2 T-2 Q-2.5 A-3 W-3 J-3.5 R-5 D-6 H-6 P-6 E-7 X-7 I-10 O-10 G-18 B-23

Inspector ID-Exp (Yrs) Crack size (inch)

Largest crack missed (inch)

Plot of Largest Missed Crack (inch) vs Inspector (years of experience) at 2nd Layer Faying Surface

slide-7
SLIDE 7

Progress to Date (BHEC Real)

Laregst crack missed by different inspector (IAR 0.3125" EDM)

0.01 4 0.049 0.01 4 0.025 0.037 0.01 3 0.01 6 0.01 6 0.020 0.01 3 0.01 3 0.01 6 0.009 0.01 4 0.01 3 0.032 0.01 4 0.01 0.032 0.01 6 0.027 0.01 0.01 4 0.01 3

0.000 0.004 0.008 0.012 0.016 0.020 0.024 0.028 0.032 0.036 0.040 0.044 0.048 0.052 L-1 N-1 S-1 V-1.0 U-1.3 C-1.8 F-2 K-2 M-2 T-2 Q-2.5 A-3 W-3 J-3.5 R-5 D-6 H-6 P-6 E-7 X-7 I-10 O-10 G-18 B-23

Inspector ID-Exp (Yrs) EDM Size (inch)

Largest EDM missed (inch)

Plot of Largest Missed EDM Notch (inch) vs Inspector (years of experience) at 2nd Layer Faying Surface

slide-8
SLIDE 8

Progress to Date (BHEC Real)

Cracks size (inch) at 90/95 POD by different Inspector-Experience and method (IAR Con 7, CC)

0.0000 0.0030 0.0060 0.0090 0.0120 0.0150 0.0180 0.0210 0.0240 0.0270 0.0300 0.0330 0.0360 0.0390

A-3 B-23 C-1.8 D-6 E-7 F-2 G-18 H-6 I-10 J-3.5 K-2 L-1 M-2 N-1 O-10 P-6 Q-2.5 R-5 S-1 T-2 U-1.3 V-1.0 W-3 X-7

Inspector ID - Experience in Yrs Cracks size (inch) at 90/95 POD

Spencer (Excel) GLM (R') a-hat vs a (Berens)

Plot of a90/95 (inch) vs Inspector (years of experience) for 2nd Layer Faying Surface Corner Crack

slide-9
SLIDE 9

Progress to Date (BHEC Real)

EDM size (inch) at 90/95 POD by different Inspector-Experience and method (IAR Con 7, EDM)

0.0000 0.0030 0.0060 0.0090 0.0120 0.0150 0.0180 0.0210 0.0240 0.0270 0.0300 0.0330 0.0360 0.0390 0.0420 0.0450 0.0480 A-3 B-23 C-1.8 D-6 E-7 F-2 G-18 H-6 I-10 J-3.5 K-2 L-1 M-2 N-1 O-10 P-6 Q-2.5 R-5 S-1 T-2 U-1.3 V-1.0 W-3 X-7

Inspector ID - Experience in Yrs Cracks size (inch) at 90/95 POD

Spencer (Excel) GLM (R')

Plot of a90/95 (inch) vs Inspector (years of experience) for 2nd Layer Faying Surface EDM Notch

slide-10
SLIDE 10

Progress to Date (BHEC Real)

  • False Call Rate Fatigue Cracks:

– Min 0% – Max 3.8% – Ave 1.1%

  • False Call Rate EDM Notches:

– Min 0% – Max 2.3% – Ave 1.8%

slide-11
SLIDE 11

Progress to Date (BHEC Real)

  • a90/95 for Fatigue Cracks (average):

– Hit-Miss (Spencer): 12.1 mils – MH 1823-2 Using R (Annis)*: 14.6 mils – a-hat vs a (Berens): 12.6 mils

  • a90/95 for EDM Notches (average):

– Hit-Miss (Spencer): 20.5 mils – MH 1823-2 Using R (Annis)*: 26.6 mils – a-hat vs a (Berens): 27.4 mils**

* Generalized Linear Model as proposed by Charles Annis ** Trenton Only (4 Inspectors)

slide-12
SLIDE 12

Remaining Work (BHEC Real)

  • Three remaining sets to be inspected:

– CC in 0.090” back surface – Mid-Bore cracks in 0.090” – Mid-Bore cracks in 0.312”

  • Inspection of induced cracks in real structure

complete – waiting for fracto to confirm measurements

  • Inspection of EDM notches in real structure

complete – waiting for fracto to confirm measurements

  • Comparison of modeled results and actual results
  • Explanation of why a90/95 is larger for EDMs as

compared to cracks

slide-13
SLIDE 13

Progress to Date (Modeling)

  • Up to this point we

have the ECSim package to model:

  • Defect length
  • Defect depth
  • Probe lift-off
  • Off-centre scanning
  • Frequency
  • Probe tilt
  • Material

conductivity

slide-14
SLIDE 14

Progress to Date (Modeling)

  • semi-elliptical crack
  • crack depth=0.25mm
  • f=500kHz
  • lift-off=0.1mm
  • σ=18.5MS/m
  • semi-elliptical crack
  • crack length=1mm
  • f=500kHz
  • lift-off=0.1mm
  • σ=18.5MS/m
slide-15
SLIDE 15

Progress to Date (Modeling)

  • semi-elliptical crack
  • crack length=1mm
  • crack depth=0.25mm
  • f=500kHz
  • σ=18.5MS/m
  • semi-elliptical crack
  • crack length/depth=1mm/0.25mm
  • f=500kHz
  • lift-off=0.1mm
  • σ=18.5MS/m
slide-16
SLIDE 16

Progress to Date (Modeling)

  • semi-elliptical crack
  • crack length=1mm
  • crack depth=0.25mm
  • lift-off=0.1mm
  • σ=18.5MS/m
  • semi-elliptical crack
  • crack length/depth =1mm/0.25mm
  • f=500kHz
  • lift-off=0.1mm
  • σ=18.5MS/m
slide-17
SLIDE 17

Progress to Date (Modeling)

  • semi-elliptical crack
  • crack length=1mm
  • crack depth=0.25mm
  • lift-off=0.1mm
  • f=500kHz
  • At this point 7 variables

have been modeled

  • Most of the changes in

variables have given the anticipated results with the exception of crack depth

  • Further investigation on

next slide

slide-18
SLIDE 18

Progress to Date (Modeling)

  • semi-elliptical crack: crack length=1mm
  • f=500kHz, lift-off=0.1mm, σ=18.5MS/m
  • There are some software issues with crack depth
slide-19
SLIDE 19

Progress to Date (Modeling)

  • When crack length and

depth are changed at the same time the eddy current impedance plane diagram has a typical appearance

slide-20
SLIDE 20

Remaining Work (Modeling)

  • Once all the empirical data is recorded

direct comparisons will be made between the models and real responses from real cracks

  • Explanations of odd behaviors

– Odd Modeling behavior for 0.23mm - 0.30mm deep cracks

  • Handbook will be developed on how to use

the modeling to estimate PoD on other similar structures (ie LM Box Wing Struct)

– Use of Modeling – Discussion on Transfer Functions

slide-21
SLIDE 21

Future Work After Project Completion

  • Further analysis of Data (to be determined)
  • More inspections to assess other variables

(to be determined)

  • Further investigations of Eddy Current

Modeling (to be determined)

  • Royal Military College NDT Graduate

Program

– Capt Holly Lemire Thesis - improving reliability estimates as part of technique development – Will use current PoD project to baseline her work – She will continue to work with the MAPoDWG

  • nce the GBHEC PoD project is complete
slide-22
SLIDE 22

Questions?

Final Results will be presented at ASIP 2007