Update: Day-Ahead Market Enhancements and Extended Day- Ahead Market Initiatives Don Tretheway Sr Advisor, Market Design Policy April 16, 2020 ISO Public ISO Public Agenda: Time: Topic: Presenter: 11:00 11:05 Introduction Kristina


  1. Update: Day-Ahead Market Enhancements and Extended Day- Ahead Market Initiatives Don Tretheway Sr Advisor, Market Design Policy April 16, 2020 ISO Public ISO Public

  2. Agenda: Time: Topic: Presenter: 11:00 – 11:05 Introduction Kristina Osborne 11:05 – 11:45 Overview of Initiative Updates Don Tretheway 11:45 – Noon Questions ISO Public Page 2

  3. Key Drivers of Shifting Policy Development Timelines • New work conditions necessitate additional time for policy development and for stakeholders to provide feedback • Shorter virtual meetings are more productive • Minimize overlap between DAME and EDAM given design synergies • More time to evaluate alternative DAME formulations to address stakeholder concerns • More time to do targeted stakeholder outreach for EDAM ISO Public Page 3

  4. Bundle topics for workshops and reach solid straw proposal before moving to next bundle • Bundle 1 – Resource Sufficiency Evaluation, Transmission Provision, Congestion Revenue • Bundle 2 – Accounting for GHG costs, ancillary services, FNM Phase 2, EDAM administrative fee • Bundle 3 – Price formation, convergence bidding, external resource participation, market power mitigation, other issues ISO Public Page 4

  5. Proposed 2020 Schedule WEEK OF DAME EDAM May 18 Revised Straw Proposal June 1 Stakeholder meeting June 15 Comments due EDAM Straw Proposal (Bundle 1) June 22 Stakeholder meeting 2 nd Revised Straw Proposal July 20 July 27 Stakeholder meeting Comments due Aug 10 Comments due Sept 14 EDAM Revised Straw Proposal (Bundle 1) Sept 21 Stakeholder meeting Q4 2020 Bundle 2 Workshop Oct 12 Draft Final Proposal Oct 19 Stakeholder meeting Oct 26 Comments due Nov 2 Comments due Nov 30 EDAM Draft Final Proposal (Bundle 1) Dec 7 Stakeholder meeting Mid-Jan 2021 Comments due (EDAM Bundle 1 DFP) Q2 2021 Bundle 3 Workshop ISO Public Page 5

  6. Additional Information Day-Ahead Market Enhancements: http://www.caiso.com/StakeholderProcesses/Day-ahead- market-enhancements Extended Day-Ahead Market: http://www.caiso.com/StakeholderProcesses/Extended- day-ahead-market Please email questions to initiativecomments@caiso.com ISO Public Page 6

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.