ASIA PACIFIC COPPER MINER DREW SIMONSEN MANAGING DIRECTOR IIIII MAY - - PowerPoint PPT Presentation

asia pacific copper miner
SMART_READER_LITE
LIVE PREVIEW

ASIA PACIFIC COPPER MINER DREW SIMONSEN MANAGING DIRECTOR IIIII MAY - - PowerPoint PPT Presentation

ASIA PACIFIC COPPER MINER DREW SIMONSEN MANAGING DIRECTOR IIIII MAY 2011 DISCLAIMER No representation or warranty is or will be made by any person (including Hillgrove Resources Limited ACN 004 297 116 (Hillgrove) and its officers, directors,


slide-1
SLIDE 1

ASIA PACIFIC COPPER MINER

DREW SIMONSEN MANAGING DIRECTOR IIIII MAY 2011

slide-2
SLIDE 2

DISCLAIMER

No representation or warranty is or will be made by any person (including Hillgrove Resources Limited ACN 004 297 116 (Hillgrove) and its officers, directors, employees, advisers and agents) in relation to the accuracy or completeness of all or part of this document (the Presentation), or the accuracy, likelihood of achievement or reasonableness of any forecasts, prospects or returns contained in, or implied by, the Presentation or any part of it. The Presentation includes information derived from third party sources that has not been independently verified. The Presentation contains certain forward-looking statements with respect to the financial condition, results of operations and business of Hillgrove and certain plans and objectives of the management of Hillgrove. Forward-looking statements can generally be identified by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar expressions. Indications of, and guidance on, production targets, targeted export output, expansion and mine development timelines, infrastructure alternatives and financial position and performance are also forward-looking

  • statements. Any forecast or other forward-looking statement contained in the Presentation involves known and unknown risks and uncertainties and may

involve significant elements of subjective judgment and assumptions as to future events which may or may not be correct. Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond the control of Hillgrove, and may cause actual results to differ materially from those expressed or implied in such statements. There can be no assurance that actual

  • utcomes will not differ materially from these statements. Factors that could cause actual results or performance to differ materially include without limitation

the following: credit risk; levels of supply and demand and market prices; legislation or regulations throughout the world that affect Hillgrove's business; insurance expenses; the risk of an adverse decision or other outcome relating to governmental investigations; class actions or other claims; growth in costs and expenses; risk of adverse or unanticipated market, financial or political developments (including without limitation in relation to commodity markets). You are cautioned not to place undue reliance on forward-looking statements. These forward-looking statements are based on information available to us as of the date of this presentation. Except as required by law or regulation (including the ASX Listing Rules) we undertake no obligation to update these forward- looking statements. The Presentation is provided for informational purposes only and is subject to change without notice. Subject to any obligations under applicable laws, regulations or securities exchange listing rules, Hillgrove disclaims any obligation or undertaking to release any updates or revisions to the Presentation to reflect any change in expectations or assumptions. Nothing in the Presentation should be interpreted to mean that future earnings per share of Hillgrove will necessarily match or exceed its historical published earnings per share, or that there has been no change in the affairs of Hillgrove since the date of the Presentation. Nothing contained in the Presentation constitutes investment, legal, tax or other advice. The information in the Presentation does not take into account the investment objectives, financial situation or particular needs of any recipient. Before making an investment decision, each recipient of the Presentation should make their own assessment and take independent professional advice in relation to the Presentation and any action taken on the basis of the Presentation. All references to dollars, cents or $ in this presentation refer to Australian currency unless otherwise stated.

2

slide-3
SLIDE 3

Drew Simonsen, Managing Director & Chief Executive Officer BE (Mining); Dip Geo Sci (Min Eco); GAICD

 Appointed MD & CEO in August 2010  35 years in resources, investment and commercial banking and financial markets in Australia, the USA and Hong Kong  Involved with advising on or financing of many energy, resources and infrastructure projects and corporate financings in

Australia and overseas

 Has worked for CRA (now Rio Tinto), Bank of America and Westpac, before operating his own consultancy business  Significant senior management and team leadership experience  Non-Executive Director of Highlands Pacific Limited

Russell Middleton, Chief Financial Officer B.Bus.; MBA; FCPA; F.Fin; GAICD

 Appointed CFO in January 2008, with 20 years experience in the resources industry  Senior management positions in accounting, commercial and planning roles  Significant experience with mine project evaluations and construction of new mines  Previously held a number of roles at BHP  Held the position of Commercial Manager for the construction, development and production of a major underground mine  More recently has been Chief Financial Officer for contracting and services companies in the mining sector

Cam Schubert, General Manager – Kanmantoo Project BSc (Hons); MAppSc; MEngSc; MAusIMM

 Appointed late 2009, with 21 years experience in the resource industry  Previously served as Mine Operations Development Manager for BHP Billiton's Olympic Dam Expansion Project from

2007 to 2009

 A significant portion of Cam’s career was spent at Xstrata's Ernest Henry open-cut copper/gold mine in North

Queensland initially as a Geotechnical Engineer and leading to Site Senior Executive & General Manager, a position he held from 2004 to 2007

 Additional experience with MIM Holdings, including Mount Isa Mines, McArthur River Zinc Mine, Tick Hill Gold Mine and

Carpentaria Gold 3

MANAGEMENT TEAM & BOARD OF DIRECTORS

EXPERIENCED MANAGEMENT TEAM WITH PROVEN TRACK RECORD

slide-4
SLIDE 4

4

MANAGEMENT TEAM & BOARD OF DIRECTORS

EXPERIENCED MANAGEMENT TEAM WITH PROVEN TRACK RECORD

Jim Kerr, General Manager – Exploration BSC(Geology); MSc(Mineral Economics)

 Joined Hillgrove Resources in late 2009 and was appointed to the role of General Manager – Exploration in July 2010  Over 20 years experience in the Resources industry  Has a broad operational background with a successful record of discovery, acquisition, development and profitable

asset disposal

 Has worked for Lithic Metals and Energy, a London AIM listed company (formerly Zambezi Nickel Limited) where he

was the Managing Director

 Integral in the acquisition, listing and development of the Tethyan Copper Company and its 4 billion tonne copper /

gold resource prior to its takeover by Barrick and Antofagasta

 Spent a large portion of his career at Mincor Resources NL as Business Development Manager where he managed a

diverse portfolio of gold and base metal exploration assets in Australia, the South Pacific and various African jurisdictions Geoff Stewart, General Manager – Business Development B.Com. (Acc.)

 Joined Hillgrove in June 2007  He has an extensive network cultivated through 30 years of trusted interaction and cooperation  Strong entrepreneurial and marketing background identifying and processing new business matching and project

development opportunities

 For over 10 years Geoff was a member of the PricewaterhouseCoopers Corporate Advisory team, following many

years in marketing and promotional roles.

 He is responsible for designing and presenting strategic initiatives using his lateral skills and market knowledge to

identify, catalyse and initiate new transaction scenarios

slide-5
SLIDE 5

COMPANY OVERVIEW

AUSTRALIAN MINING COMPANY WITH AUSTRALIAN-INDONESIAN GROWTH PIPELINE

5

 Principal asset is the Kanmantoo

Copper Mine project (100% owned), currently under construction in South Australia

Sumba project Bird’s Head project Kanmantoo Hillgrove Resources’ main projects Gold Base metals + Gold

 Hillgrove Resources (“HGO”) is an

Australian based minerals exploration and development company

 HGO also has highly prospective,

advanced exploration assets in Indonesia

 Sumba gold project (80% owned)  Bird’s Head copper/gold project

(80% owned)

slide-6
SLIDE 6

6

 Our Strategy:

 Construct Kanmantoo,

  • n time and within

budget

 Expand the Kanmantoo

resource base

 Expand Kanmantoo

throughput

 Explore/develop copper

& gold in Australia and Indonesia

 Become a multi-mine

producer within 5 years

 Apply focus and discipline

– execute well

NEAR TERM PRODUCTION, HIGHLY PROSPECTIVE EXPLORATION

STRATEGIC DIRECTION AND FOCUS

slide-7
SLIDE 7

7

CORPORATE SNAPSHOT

ASX listed: HGO

Shares on issue: 793.7 million

Share price: A$ 0.30 (6 May 2011)

Market capitalisation: A$238 million (6 May 2011)

Cash and cash equivalents: A$113 million (28 February 2011)

Zero debt (project loans not yet drawn)

EV A$125 million (6 May 2011)

45% Institutional shareholders

DETAILS AND SHAREHOLDER DISTRIBUTION

Source: Orient Capital

Institutions 39.0% JP Morgan Metals & Concentrates 7.0% Retail 54.0%

SHAREHOLDER DISTRIBUTION

slide-8
SLIDE 8

8

CORPORATE SNAPSHOT

TOP 20 SHAREHOLDER LIST

Investor 31 Mar 2011 % of isc 1 JP Morgan Metals & Concentrates 55,886,772 7.0% 2 BT Investment Management 53,988,749 6.8% 3 Renaissance Smaller Companies 31,420,354 4.0% 4 Colonial First State - Growth Australian Equities 20,600,000 2.6% 5 Dimensional Fund Advisors 18,147,565 2.3% 6 Dr Dirk Ruttgers Vermogensverwaltung; (Crocodile) 17,031,277 2.1% 7 AMP Capital Investors 16,078,677 2.0% 8 JPMorgan Securities 15,567,560 2.0% 9 Wilson HTM 14,480,825 1.8% 10 Scott Family 14,378,781 1.8% 11 Zurcher Kantonalbank 13,207,000 1.7% 12 Macquarie Funds Group 11,765,000 1.5% 13 Mr David S Archer 10,357,500 1.3% 14 Paradice Investment Management 9,361,746 1.2% 15 Smorgon Family 8,887,500 1.1% 16 Investors Mutual 8,243,000 1.0% 17 Thorney Investments 8,000,000 1.0% 18 Credit Suisse 6,435,334 0.8% 19 Liechtensteinische Landesbank 6,000,000 0.8% 20 Mr Tony R Glucina 4,732,380 0.6% Total 344,570,020 43.4%

slide-9
SLIDE 9

Kanmantoo Copper Mines Project

slide-10
SLIDE 10

RESOURCE MODEL VIDEO

KANMANTOO COPPER MINES

10

SEE SEPARATE VIDEO FILE TO VIEW

slide-11
SLIDE 11

11

ALL MAJOR SERVICES CLOSE BY

KANMANTOO COPPER MINES – CLOSE TO ADELAIDE

100%-owned by Hillgrove

Located just 55km from Adelaide, in South Australia

Copper has been mined in the area for

  • ver 150 years

Exploration License area of 500km2, and relatively unexplored

Exploration potential considered high

The project enjoys commensurate capital cost advantages

 Close to power (National Grid connection)  Recycled water pipeline  3km from main highway  50km to export port

Attractive employment costs compared to remote fly-in/fly-out mine operations

Wheal Ellen Exploration Area EL4401 Exploration Area EL4401 Kanmantoo Copper Mine

slide-12
SLIDE 12

Plant

12

2010 – PRIOR TO CONSTRUCTION

KANMANTOO COPPER MINES

Kanmantoo was operated by North Broken Hill, South Broken Hill and Electrolytic Zinc from 1971-1976

Approximately 4.1Mt @ 0.9% Cu, at a strip ratio of about 5:1

Residual oxide ore currently being heap-leached by Hillgrove

New plant site Current pre-strip area Current heap- leach operation New Tailings Storage facility (TSF) behind

  • ld waste dump
slide-13
SLIDE 13

CURRENT VIEW OF PLANT SITE

KANMANTOO COPPER MINES

slide-14
SLIDE 14

VIEW OF PLANT SITE FROM TOP OF OLD WASTE DUMP

KANMANTOO COPPER MINES

14

 Further potential to increase to 3.5Mtpa  Estimated mine life of 10 years based on current resources  First copper/gold production is scheduled for November 2011  Configured as 2.4Mtpa, and ramping to 2.7Mtpa through operational efficiencies

slide-15
SLIDE 15

15

Project Total FID Capital Costs Construction Period Costs Total capital costs (AUD M) Capital costs spent to 31/8 (AUD M) Capital costs for FID (AUD M) Spend Period 1/9 to 28/2 (AUD M) Remaining Budget (AUD M) Pre-strip 26.7

  • 26.7

7.5 19.2 Mining, TSF & Grade Control 17.1 0.1 17.0 3.3 13.7 Pillara processing plant 67.9 21.3 46.6 15.7 30.9 Other infrastructure 9.3 0.4 8.9 5.7 3.2 Project management costs 13.2 1.1 12.1 3.7 8.4 Contingency 10.0 10.0 10.0 Total 144.2 22.9 121.3 35.9 85.4

FID AND CONSTRUCTION STARTED NOVEMBER 2010

CAPITAL AND DEVELOPMENT COSTS TO BRING KANMANTOO TO PRODUCTION TO 28/2/11

Cash Balance at 28 February was AUD 113 million

50-55% of projected Cu output hedged for 40 months (debt repayment period)

Average hedging price of AUD 8,230/tonne (USD 3.73/lb) commencing in June 2012 – no FX exposure on hedged volume

slide-16
SLIDE 16

16

KANMANTOO COPPER MINES

 As at 28 February 2011  AUD 35.9 million spent, AUD 85.4 million remaining to spend  Cash Balance AUD 113 million & AUD 30 million undrawn Project

Finance Debt facility

 Total cash resources of AUD 143 million to meet remaining capex

  • f AUD 85.4 million (net AUD 57.6 million)

 Working Capital and Debt Service Reserve Account “seeding” of

approximately AUD 25 million

 Corporate and Exploration expense AUD 15 million p.a.  Plant and Equipment already acquired – on site (no estimation,

escalation or FX risk on remaining capex)

 All cash and in expenditure in AUD – no FX exposure  On time, on budget for 1 November 2011 start-up

FINANCING PLAN SUMMARY & STATUS

slide-17
SLIDE 17

17

KANMANTOO COPPER MINES

Life-of-mine (“LOM”) average payable metals production

21k tonnes p.a. copper

9k ounces p.a. gold

177k ounces p.a. silver

Royalties 1.5% NSR for 5 years, 5% thereafter

Average LOM cash cost of USD 1.61/lb (excluding royalties, but after smelter charges and circa USD 0.25 in by-product credits, calculated @ USD 900 Au, and USD 13 Ag)

LOM off-take contract with J.P. Morgan Metals & Concentrates

  • LLC. Terms set for first 80k of

Cu in concentrate, then market

PLANNED PROJECT HIGHLIGHTS

slide-18
SLIDE 18

18

Second-hand Pillara plant disassembled and relocated from Western Australia by Abesque Engineering

Construction and commissioning contract also with Abesque Engineering

Standard flowchart and production process with additional regrind facility

5 months into 12 month construction program

JAW CRUSHER ROM BIN FEED BIN VIBRATING GRIZZLY FEEDER PRODUCT SCREEN SECONDARY CRUSHER STOCK PILE FLOATATION REAGENTS ROUGHER FLOATATION FLOATATION REAGENTS CLEANER FLOATATION CYCLONE REGRIND MILL Proposed CONCENTRATE THICKENER CONCENTRATE STORAGE TANK CONCENTRATE STOCKPILE TRUCK TO PORT CONCENTRATE FILTER TAILINGS DAM WATER STORAGE DAM TAILINGS THICKENER PEBBLE CRUSHER SAG MILL

HYDRO CYCLONE

PROCESS WATER TANK NEUTRAL- ISATION TANK Lime

PROCESSING OVERVIEW

KANMANTOO COPPER MINES

slide-19
SLIDE 19

19

KANMANTOO COPPER MINES

 Abesque Engineering

principal contractor

 Parsons Brinckerhoff

appointed to provide project management oversight of construction activities

 Construction to date 50%

complete, on time and within budget

 Civils nearing completion

CONSTRUCTION PROGRESS

slide-20
SLIDE 20

KANMANTOO COPPER MINES – CURRENT ACTIVITY

SITE VIEW WITH PLANT LOCATION SCHEMATIC (FROM LEFT TO RIGHT 2 OF 2)

York Civil Construction Office Hillgrove Administration Block Abesque Construction Office Concentrate Filter Shed Process Water Pond Concentrate Storage Area Floatation Area Mill Area Workshop & Stores Area Concentrate Thickener Tank Tailings Thickener Tank Stockpile Feed Conveyor

20

Base of Ore Stockpile

slide-21
SLIDE 21

21

KANMANTOO COPPER MINES

 Exact Mining – mining contractor  Pre-strip and Tailings Storage

Facility (TSF) initially

 Milestones to date include  TSF embankments and crusher ramp commenced  Initial piping system installed for Tailings Storage Facility (TSF)  TSF liner installation 70% complete, end June completion  Ore stockpiling underway (approximately 250kt Oxide and Transition ore

stockpiled for later processing)

 Expect circa 500,000 tonnes of sulphide ore stockpiled for plant start-up  Reclaimed water pipeline from Mt Barker to site >90% complete  ElectraNet has commenced construction of HV connections, with

“energisation” scheduled for 31 August 2011

MINING AND INFRASTRUCTURE PROGRESS

slide-22
SLIDE 22

22

KANMANTOO COPPER MINES

KEY MILESTONES THROUGH TO COMMISSIONING IN NOVEMBER 2011

Energisation MILESTONE 31st August 2011 Pre‐commissioning Phase COMMENCES: 7th September 2011 ‐ Bump tests ‐ Power to plant & equipment ‐ Duration 6‐8 weeks General Construction COMPLETE 30th September 2011 C2 Commissioning Phase COMMENCES: 5th October 2011 ‐ Water commissioning of plant ‐ Duration 4‐6 Weeks C3 Commissioning Phase PRACTICAL COMPLETION 1st November 2011 ‐ First ore delivered ‐ 180 days operation ‐ Ramp up to full production

slide-23
SLIDE 23

23

Class Total (0.25% Cu cut off grade model) Tonnes Kt Cu % Au g/t Ag g/t Cu Metal Tonnes Au Ounces Ag Ounces Measured 2,290 0.9 0.2 3.5 21,700 12,100 255,300 Indicated 22,525 0.9 0.2 3.3 204,400 139,900 2,381,200 Inferred 7,376 0.9 0.2 2.9 66,100 39,100 677,100 Total 32,192 0.9 0.2 3.2 292,200 191,100 3,313,600 Category Tonnes Mt Cu % Au g/t Ag g/t Proven 2.3 0.87 0.13 3.2 Probable 12.5 0.84 0.18 3.1 Ore reserve 14.8 0.85 0.17 3.1

8.5 18.4 28.0 31.8 32.2 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 Dec-03 Dec-04 upgrade Oct-06 upgrade Dec-07 upgrade Nov-08 upgrade Inferred Indicated Measured

Mt

11.1 14.8 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 DFS Dec-07 Apr-10 upgrade Probable Proved

Mt

Source: HGO’s ASX release dated 4 May 2010 Source: HGO’s ASX release dated 8 December 2008

RESOURCE GROWTH RESERVE GROWTH CURRENT RESOURCES CURRENT RESERVES

KANMANTOO COPPER MINES OVERVIEW

EXPLORATION HAS IMPROVED RESOURCE CERTAINTY AND RESOURCE-RESERVE CONVERSION RATIO

slide-24
SLIDE 24

24

ORE BODY AND NEAR MINE EXPLORATION

KANMANTOO COPPER MINES

 Exploration Manager appointed  Strategic review of all exploration

conducted to date to target and rank priorities within mining lease (ML 6345)

 Board approved AUD 1.5 million,

near-mine exploration budget through 2011

 Priority objective is to add to open

pit resources and reserves to extend mine life

 Two phase drilling program for

2011

Waste Rock Stockpile NW Zone NE Zone SE Zone Main Zone Green Zone O’Neil Emily Star Green Zone Sth Plant Site

slide-25
SLIDE 25

25

RESOURCE EXTENSION AND TARGET RESERVE CONVERSION

KANMANTOO MINES

 Phase 1 – Convert

inferred resources to indicated

 5,000m of RC drilling

and up to 400 m of DD

 Plan view of resources

around the pit

 Indicated (orange)  Inferred (yellow)  Sectional views provide

better explanation

 Existing pit shown dark

in centre (Section A-A)

slide-26
SLIDE 26

26

RESOURCE EXTENSION - TARGET NEAR MINE IP ANOMALIES

KANMANTOO COPPER MINES

FALCON EMILY STAR SOUTH PARINGA COOPER’S FIND GREEN ZONE SOUTH SLOT EXTENSION & NE ZONE McFARLANE’S MAIN ZONE SOUTH

Phase 1: Reserve Upgrade - 5000m Convert inferred resources to indicated Phase 2: Resource Extension - 2500m Identify new resources to extend mine life

slide-27
SLIDE 27

 Phase 1 ‐ Convert inferred resources to indicated

27

CROSS SECTION A – A’ LOOKING NORTH THROUGH FALCON & MAIN ZONE

KANMANTOO COPPER MINES

Open: No Drilling Open: No Drilling KTGC0073 – 19m @ 1.43% Cu

slide-28
SLIDE 28

 Phase 1 ‐ Convert inferred resources to indicated

CROSS SECTION B – B’ LOOKING NORTH THROUGH GREEN & MAIN ZONES

KANMANTOO COPPER MINES

Open: No Drilling Open: No Drilling KTRC077 – 20m @ 1.31% Cu

slide-29
SLIDE 29

 Phase 1 ‐ Convert inferred resources to indicated

CROSS SECTION C – C’ LOOKING NORTH THROUGH O’NEIL

KANMANTOO COPPER MINES

Open: No Drilling Open: No Drilling KTRCD284 – 21m @ 1.27% Cu KTRCD122 – 24m @ 1.00% Cu

slide-30
SLIDE 30

30

SUMMARY

 Next Australian

copper producer

 Construction on

time and on budget

 First production

November 2011

 Robust project

with near term cash flows

 Good potential for

Life of Mine extension

KANMANTOO COPPER MINES

slide-31
SLIDE 31

EXPLORATION

slide-32
SLIDE 32

32

EXPLORATION ASSETS: INDONESIA

HIGHLY PROSPECTIVE GOLD, COPPER EXPLORATION

Proven geological provenance for target commodities (Cu, Au)

Strengthened legislative and judicial environment

Favourable new mining laws allowing direct foreign ownership

Experienced local partners developed through existing relationships

Key exploration projects:

 Sumba Project (HGO 80%)  Bird’s Head Project (HGO 80%)

WHY INDONESIA?

Source: Companies’ filings

200 400 600 800 Batu Hijau Grasberg Ok Tedi Porgera Gosowong 500 1,000 1,500 2,000 2,500 3,000

Copper Gold

CY2009 PRODUCTION FOR REGIONAL MINES

kt copper kOz gold

slide-33
SLIDE 33

33

SUMBA ISLAND

HILLGROVE 80%

Hillgrove is an 80% shareholder in PT Fathi, holding an IUP over ~1,000km2 for a period

  • f six years

Hillgrove responsible for exploration and development activities and sole funding up to decision to mine

Two main project areas

Masu Project Area Tanah Daro Project Area Pelitalira

Masu (Southern) Project area

 17 high priority gold targets

  • Mapping/sampling/scout drilling
  • Air magnetics to be flown

Tanah Daro (Northern) Project area

 Pelitalira prospect in NW

  • Highly prospective gold/base metals
  • Drilling commenced February
slide-34
SLIDE 34

34

Recent exploration

Soil sampling over Project now covers over 10km²

Has identified 17 high priority gold anomalies (over up to1.5km in length)

Soil sampling continues to identify high quality gold targets for further investigation Next Steps:

Planned aeromagnetic and radiometric survey scheduled in May

After air mag, targets will be prioritised for drill testing in Q2

SUMBA ISLAND

MASU (SOUTHERN) PROJECT AREA

Masu Project Area

Masu Corridor Soil Gold Values And Prospect Locations

slide-35
SLIDE 35

35

SUMBA ISLAND

TANAH DARO (NORTHERN) PROJECT

Pelitalira Prospect

Located in Central Sumba

Accessible by road

Recent exploration

 Soil sampling delineated

two distinct gold anomalies with gold values up to 19.95g/t Au

 Earlier Waterfall Vein rock

chip samples to 72g/t Au, 3.68% Cu and 765g/t Ag

 Trenching across Waterfall Vein returned 12m @ 8.3g/t Au (not true width)  1,500m scout drilling programme commenced February  9 holes to 150m completed - assay results pending  Decision taken to extend aeromagnetic survey to this Northern area as well

Waterfall Vein

Tanah Daro Project Area

slide-36
SLIDE 36

36

INDONESIA BIRD’S HEAD PROJECT

REGIONAL SETTING

Bird’s Head covers part of the interpreted westward continuation of the New Guinea ‘Orogenic Belt’

Sorong

slide-37
SLIDE 37

37

BIRD’S HEAD PROJECT

HILLGROVE 80%

Hillgrove is an 80% beneficial shareholder in PT Akram

As with PT Fathi, we are moving to a corporatised ownership structure

IUP rights cover almost 1,000km2 , granted for six years

Hillgrove responsible for exploration and development activities and sole funding up to decision to mine

Ex Normandy project: Hillgrove has acquired drilling and geophysics data, amongst other key data

slide-38
SLIDE 38

38

BIRD’S HEAD PROJECT

GREEN CLIFFS PROSPECT

Note: Copper assays determined by multi element sweep using ICP methodology; Analyses completed by Intertek Laboratories, Jakarta; Intersections calculated as a weighted average, 0.1% Cu lower cutoff, maximum 2m consecutive internal waste

Magnetic High Inversion Modelling Outlines Green Cliffs Breccia Target

3D magnetic inversion modelling of West Delta area showing magnetic targets

Strong magnetic anomalies associated with intense hydrothermal alteration, Diorite intrusives and copper values to >1%Cu

West Delta channel sampling location and significant copper intersections

Landslip exposures have aided structural interpretation

slide-39
SLIDE 39

BIRD’S HEAD PROJECT

WEST DELTA PROSPECT

 Trenching highlights :  32m @ 0.73% Cu including 20m @ 0.95% Cu  52m @ 0.35% Cu including 12m @ 0.75% Cu  132m @ 0.29% Cu including 18m @ 0.65% Cu  54m @ 0.48%Cu including 22m @ 0.97% Cu  Rock chip sampling with geological mapping has encountered strongly

anomalous copper values, mostly >1% Cu with strong gold and molybdenum association

 Geological interpretation is of:  A young (Tertiary) intrusive complex  Overlapping hydrothermal alteration systems in a 6.5 x 1.5 km corridor  Multiple porphyry copper targets

slide-40
SLIDE 40

40

BIRD’S HEAD PROJECT

DELTA PROSPECT

Outcropping Copper Mineralization, Green Cliffs Prospect

 Very large remnant

litho-cap material on high ridge tops indicates the system is partially eroded

 Copper grades at

surface ~0.2%-0.6% are common

slide-41
SLIDE 41

41

BIRD’S HEAD PROJECT

COPPER PORPHYRY SIGNATURES AT WEST DELTA

Green Cliffs Breccia Target

WIDESPREAD SURFACE CU MINERALISATION ADVANCED ARGILLIC ALTERATION PROPYLITIC ALTERATION PHYLLIC ALTERATION POTASSIC ALTERATION MAGNETIC ANOMALIES

     

slide-42
SLIDE 42

42

BIRD’S HEAD PROJECT

WEST DELTA PROSPECT

Geological mapping, historical soil sampling, aeromagnetic survey results, trenching and alteration mapping

Zonation intensity increases towards Green Cliffs, determining core target area

There are multiple porphyry targets present in the West Delta area

Ideal geographic location i.e. close to coast

Po

Porphyry Targets

Porphys

Porphyry Targets

slide-43
SLIDE 43

BIRD’S HEAD PROJECT

WEST DELTA PROSPECT

 Have done as much as we can through surface exploration  Next step is to drill-test these porphyry targets (to 600m)  Experienced drilling contractor has been selected  Drill rig en-route to site  Awaiting necessary permitting to undertake drilling activities  Strong interest from “majors” in our property

Drill Pad preparation and core shed being built

slide-44
SLIDE 44

44

Hillgrove Resources Limited (HGO)

 Producing asset in November 2011 (7 months)  High optionality through:  Resource expansion at Kanmantoo (target

doubling of resources)

 Expanded throughput at Kanmantoo (2.4 to

3.5 mtpa), subject to resource definition

 Exploration success in Indonesia  Sumba  Bird’s Head  New property acquisitions

FINANCING PLAN STATUS

CORPORATE SNAPSHOT

slide-45
SLIDE 45

45

HILLGROVE RESOURCES vs BROKER VALUATIONS

CORPORATE SNAPSHOT

Broker Date Kanmantoo Indonesia Total Intersuisse 2/03/2011 $0.41 $0.00 $0.41 Austock 11/04/2011 $0.45 $0.09 $0.54 Wilson HTM 1/04/2011 $0.62 $0.02 $0.64

Broker valuations are significantly higher than the existing share price

Little or no value attributed to the Indonesian assets

$0.00 $0.20 $0.40 $0.60 $0.80 $1.00 04/2010 07/2010 10/2010 01/2011 HGO Share Price Kanmantoo Indonesia

Intersuisse $0.41 Austock $0.54 Wilson $0.64

April ‘10 1 year HGO share price graph April ‘11

Significant upside in Intersuisse’s valuation e.g. with successful project delivery and current spot prices valuation rises to 90c

slide-46
SLIDE 46

APPENDIX

slide-47
SLIDE 47
  • Hon. Dean Brown AO

Non-Executive Chairman

Former Premier and Minister of the South Australian Government and Member of the South Australian Parliament

Chairman of InterMet Resources Limited, a Director of Scantech Limited and Foodbank SA, the Premier’s Special Advisor on the Drought, and a member of several advisory boards

Previously a Director of AACM International Pty Ltd (1986-92) and a Senior Agricultural Scientist, SA Government John Gooding Non-Executive Director

Mining Engineer with 30 years' experience in the resources industry, especially in gold and base metal mining

Has held executive management positions with Normandy Mining, MIM, Xstrata (CEO Xstrata Copper Australia), Ok Tedi Mining and Roche Mining

Former board member of the Queensland Resource Council and has held directorships in a number of companies within the resources industry

Currently the Managing Director and Chief Executive Officer at Highlands Pacific Limited Edwin Zemancheff Non-Executive Director

Previously a partner at global law firm Baker & McKenzie with 25 years experience in commercial and land use law

Has held a number of directorships, including (NED) Fortius Funds Management Pty Ltd and Chairman of NSW Rugby Union; Mr. Zemancheff is currently Chairman of Waratah Rugby Ronald Belz Non-Executive Director

Tax Agent since 1978, a member of CPA Australia since 1982 and a Certified Practising Accountant since 1987

Currently Treasurer and Board Member of the Academy BJE, the New South Wales Board of Jewish Education

Chairman of Audit Committee John Quirke Non-Executive Director

Former Federal Senator with State and Federal committee experience in mining and economics

He is a Trustee to the Australia/ Cambodia Foundation and Director of Operation Flinders

Chairman of Remuneration Committee

47

MANAGEMENT TEAM & BOARD OF DIRECTORS

EXPERIENCED BOARD OF DIRECTORS WITH PROVEN TRACK RECORD