University of Delaware University of Delaware Center for the Arts - - PowerPoint PPT Presentation
University of Delaware University of Delaware Center for the Arts - - PowerPoint PPT Presentation
University of Delaware University of Delaware Center for the Arts Center for the Arts Newark, DE Newark, DE Karen Schulte Karen Schulte Mechanical Option Mechanical Option Spring 2006 Spring 2006 Presentation Outline Presentation
Presentation Outline Presentation Outline
- Project Information
Project Information
- Building Information
Building Information
- Existing Conditions
Existing Conditions
- Redesign Goals
Redesign Goals
- Mechanical Redesign
Mechanical Redesign
- Structural Analysis
Structural Analysis
- Acoustical Analysis
Acoustical Analysis
- Conclusions
Conclusions
- Acknowledgements
Acknowledgements
- Questions
Questions
Project Information Project Information
- Location
Location – – Newark, DE Newark, DE
- Building Use
Building Use – – Performing Arts Center Performing Arts Center
- Delivery Method
Delivery Method – – Design Design-
- Bid
Bid-
- Build
Build
- Construction
Construction – – May May 2004 to June 2006 2004 to June 2006
- 2
2nd
nd of 3 bid package
- f 3 bid package
construction project construction project
Project Team Project Team
- Owner
Owner – – University of Delaware University of Delaware
- Architect
Architect – – Ayers Saint Gross Ayers Saint Gross
- Construction Manager
Construction Manager – – Whiting Turner Whiting Turner
- MEP Engineer
MEP Engineer – – Mueller Associates Mueller Associates
- Structural Engineer
Structural Engineer – – McLaren McLaren Engineering Engineering Group Group
- Civil Engineer
Civil Engineer – – Tetra Tech Tetra Tech
- Acoustical Consultant
Acoustical Consultant – – Kirkegaard Kirkegaard Associates Associates
Building Information Building Information
- 92,000 sq ft
92,000 sq ft
- Building uses
Building uses
– – Recital Hall Recital Hall – – Proscenium Theater Proscenium Theater – – Orchestra Rehearsal Room Orchestra Rehearsal Room – – Theater Rehearsal room Theater Rehearsal room – – Practice Rooms Practice Rooms
- 2
2” ” Open joint complete separation Open joint complete separation between structural systems between structural systems
Existing Conditions Existing Conditions
- Mechanical
Mechanical
– – 6 Air Handling Units 6 Air Handling Units
- 4 constant volume single zone
4 constant volume single zone
- 2 variable air volume
2 variable air volume
– – Chilled water and steam provided by the Chilled water and steam provided by the university university
Redesign Goals Redesign Goals
- Primary redesign goal
Primary redesign goal
– – Implement an Implement an underfloor underfloor air distribution system in air distribution system in the Proscenium Theater the Proscenium Theater
- Secondary redesign goals
Secondary redesign goals
– – Improved indoor air quality Improved indoor air quality – – Reduced outdoor airflow Reduced outdoor airflow – – Reduced supply fan Reduced supply fan horsepower horsepower
Underfloor Underfloor Air Distribution Air Distribution
- Conditioned air supplied
Conditioned air supplied from plenum from plenum
– – Pressurized Plenum Pressurized Plenum
- Passive Diffusers
Passive Diffusers
– – Zero Zero-
- Pressure Plenum
Pressure Plenum
- Active Diffusers
Active Diffusers
- Warmer supply air
Warmer supply air temperatures temperatures
- Stratification
Stratification
- Ceiling plenum return
Ceiling plenum return
– – Collection of contaminants Collection of contaminants – – Ceiling lighting loads Ceiling lighting loads
Mechanical Redesign Mechanical Redesign
Zone 1 Zone 2 Zone 3 Zone 4 Spot Booth Orchestra Pit Stage
Barrier Ceiling Catwalk Roof
Mechanical Redesign Mechanical Redesign
- Underfloor
Underfloor System System
– – Airflow Airflow – – 14,200 14,200 cfm cfm – – Cooling Coil Capacity Cooling Coil Capacity – – 315 315 Mbh Mbh – – Minimum OA % Minimum OA % -
- 22%
22%
- 20% overall reduction
20% overall reduction
– – Supply Air Fan Static Supply Air Fan Static Pressure Pressure – – 2.5in WG 2.5in WG
- Overhead System
Overhead System
– – Airflow Airflow – – 7,900 7,900 cfm cfm – – Cooling Coil Capacity Cooling Coil Capacity – – 420 420 Mbh Mbh – – Minimum OA % Minimum OA % -
- 44%
44% – – Supply Air Fan Static Supply Air Fan Static Pressure Pressure – – 5.0in WG 5.0in WG
Structural Analysis Structural Analysis
- First Level
First Level
– – Depress foundation and slab on grade 4 Depress foundation and slab on grade 4’ ’ – – Elevated slab with grouted CMU blocks for support Elevated slab with grouted CMU blocks for support – – Cut minimum amount of rebar for diffusers Cut minimum amount of rebar for diffusers
- Second Level
Second Level
– – Elevated slab with grouted CMU blocks for support Elevated slab with grouted CMU blocks for support – – Increase beam and column sizes to support increased Increase beam and column sizes to support increased weight of balcony weight of balcony – – Cut minimum amount of rebar for diffusers Cut minimum amount of rebar for diffusers
1 1st
st Level Structural Analysis
Level Structural Analysis
2 2nd
nd Level Structural Analysis
Level Structural Analysis
2 2nd
nd Level Structural Analysis
Level Structural Analysis
Acoustical Analysis Acoustical Analysis
- Proscenium Theater
Proscenium Theater
– – Acoustically Critical Acoustically Critical
- RC 18
RC 18-
- 22 (N)
22 (N)
– – Underfloor Underfloor Air Distribution Air Distribution
- RC
RC-
- 17 (N)
17 (N)
- NC
NC-
- 16
16
Conclusions Conclusions
- Improved indoor air quality
Improved indoor air quality
- Increased required airflow
Increased required airflow
- Decreased minimum amount of outdoor
Decreased minimum amount of outdoor air air
- Decreased cooling coil load
Decreased cooling coil load
- Increased coordination with concrete
Increased coordination with concrete contractor and placement of diffusers contractor and placement of diffusers
- Meets acoustical criteria
Meets acoustical criteria
Acknowledgements Acknowledgements
- AE Faculty
AE Faculty
- AE Colleagues
AE Colleagues
- Mueller Associates
Mueller Associates
- Family
Family
- Friends (That means you,