SLIDE 17 Relevant Events Caused by? Relevant Matters
2.29 .1 Variations Employer 4.24 .1 Variations .2 CA's instructions to: .2 CA's instructions to: .2 .1 correct a discrepancy in the Contract Documents (cl. 2.15); Employer .2 .3 correct a discrepancy in the Contract Documents (cl. 2.15) .2 .1 postpone part of the Works (cl. 3.15); Employer 2 .1 postpone part of the Works (cl. 3.15); .2 .1 execute work represented by an undefined Provisional Sum (cl. 3.16); Employer .2 .1 execute work represented by an undefined Provisional Sum (cl. 3.16); .2 .1 completing works that would have been under a Schedule 2 Quotation had the Contractor not
- bjected to it being so (cl. 5.3.2)
Contractor .2 .2 opening up of works for inspection if work found to be in accordance Employer .2 .2 opening up of works for inspection if work found to be in accordance .3 deferment of possession of the site Employer .4 discovery of antiquities on the site (cls. 3.22.1, 3.22.2) Neither .3 discovery of antiquities on the site (cls. 3.22.1, 3.22.2) .5 execution of work described by an inaccurate Approximate Quantity Employer .4 execution of work described by an inaccurate Approximate Quantity .6 suspension of the Works by the Contractor due to non-payment Employer .7 actions or inactions of anyone employed by the Employer Employer .5 actions or inactions of anyone employed by the Employer .8 actions of a Statutory Undertaker Neither .9 exceptionally adverse weather conditions Neither .10 loss or damage caused by a Specified Peril Neither .11 civil commotion, terrorism Neither .12 strike Neither .13 a change in Statute directly affecting the Works Neither .14 force majeure Neither