Underground PD QC Tes0ng Dave Warner Colorado State University - - PowerPoint PPT Presentation
Underground PD QC Tes0ng Dave Warner Colorado State University - - PowerPoint PPT Presentation
Underground PD QC Tes0ng Dave Warner Colorado State University Philosophy/Strategy Basic philosophy Don t generate tes0ng as busywork But learn what you can early to allow you to change problems Have a plan for what you
SLIDE 1
SLIDE 2
Philosophy/Strategy
- Basic philosophy—
– Don’t generate tes0ng as busywork – But learn what you can early to allow you to change problems – Have a plan for what you will do if you find a problem with a test!
- Strategy—
– Test more extensively early in the installa0on campaign (first few APAs) to look for required improvement to installa0on planning – Reduce (as appropriate) to checkout upon receipt and in final posi0on once installa0on strategy proven
5/19/18 PD Installa0on QC Requirements 2
SLIDE 3
Descrip0on of QC Tests:
- A “Con0nuity check” is a check to the end of
the currently installed cable run to ensure the cable is s0ll connected to the module
– Needs to be understood in the context of ac0ve ganging
- “Opera0onal test” is a check in a dark room or
light box to test the con0nued opera0on of the SiPMs (possibly with LED illumina0on?)
5/19/18 PD Installa0on QC Requirements 3
SLIDE 4
Tes0ng upon Unpacking
- Ideally the APAs would be packaged in nearly-
light-0ght plas0c wrapping, which would allow us to do a final checkout prior to unpacking from the crate
- Perhaps with an LED in the package?
- All APAs would have an opera0onal test prior to
unpackaging throughout installa0on
- Es0mated 0me: 15 to 30 minutes per APA pair
- Remedia0on: TBD. Cable checks? Possible
replacement of damaged PD (depends on available space)
5/19/18 PD Installa0on QC Requirements 4
SLIDE 5
Tests upon Hanging Outside Cryostat
- Immediately following assembly of upper APA to
lower APA, a con0nuity check will be performed for all 20 cables at the top of the APA stack
- All assembled APA stacks would have a con0nuity
check throughout installa0on
- Es0mated 0me: 10 to 15 minutes?
- Remedia0on: Re-check cable connec0ons.
Possibly separate APA stack to access middle connectors if necessary?
5/19/18 PD Installa0on QC Requirements 5
SLIDE 6
Ini0al Tes0ng upon Posi0oning Inside Cryostat
- Immediately following the APA arriving in posi0on
inside the cryostat, but prior to connec0ng the APA- Flange feedthrough cable, a con0nuity check will be performed
- This checkout is envisioned early in the installa0on
process, and may be eliminated later.
- The goal of this checkout is to catch cabling issues
caused by the rail installa0on system early enough to allow us to gain access for remedia0on
- Es0mated 0me: 20 minutes (?) depending on ease of
access
- Remedia0on: Move APA stack enough to allow access
to cables for repair. Possible other remedia0on as agreed to.
5/19/18 PD Installa0on QC Requirements 6
SLIDE 7
Full Cable Run Checkout
- Following installa0on of APA-Flange
feedthrough cable, a con0nuity check will be performed
- This check will occur for all PDs as early as
possible ader installa0on.
- Es0mated 0me: 15 minutes
- Remedia0on: Check cable connec0ons. Note
issues in database.
5/19/18 PD Installa0on QC Requirements 7
SLIDE 8
Post-installa0on Opera0onal Test
- As soon as possible following installa0on and cable
checkout, it would be ideal if the cryostat lights could be turned off and an opera0onal (dark) check performed.
- Ideally, this would happen on an stack-by-stack basis in the
ini0al installa0on phase, then perhaps on a weekly basis as
- ur understanding evolves?
- Es0mated 0me: 1 hour per stack (during off-installa0on-
shid 0me)
- Test possible involves LED illumina0on?
- Remedia0on: Note module status in logbook, try to
improve handling procedures to eliminate sources of failures.
5/19/18 PD Installa0on QC Requirements 8
SLIDE 9
Tooling
- A con0nuity check tool will need to be developed to
allow for rapid tes0ng.
– Mul0-cable simultaneous connec0on? – No twist lock opera0on? – Automa0c test result evalua0on? – Automa0c data storage?
- A portable opera0onal tes0ng sta0on should be
developed
– 4 channel readout? – Automa0c test result evalua0on? – Automa0c data storage?
- Aim for opera0on by technicians, not scien0sts.
5/19/18 PD Installa0on QC Requirements 9
SLIDE 10
Data Storage/Evalua0on
- Ideally, the data from all installa0on QC checks would
be downloaded to the database automa0cally, no later than at the end of the shid where they were taken.
- Data flagged as outside opera0onal norms (TBD) would
be automa0cally flagged for expert interven0on
- Weekly (?) expert examina0on of QC data from
recently installed modules
- Performance trend lines maintained (automa0cally?)
to look for long-term changes to the system.
5/19/18 PD Installa0on QC Requirements 10
SLIDE 11
Summary:
- While underground remedia0on is difficult,
QC tes0ng during installa0on is important to improve procedures and make possible repairs.
- Tooling must be developed to allow tes0ng to
de made by non-PD experts
- Data must be automa0cally stored, and easily
retrievable, to be most useful.
5/19/18 PD Installa0on QC Requirements 11