u ptown w aterloo s treetscape c onstruction
play

U PTOWN W ATERLOO S TREETSCAPE C ONSTRUCTION King Street from ION - PowerPoint PPT Presentation

U PTOWN W ATERLOO S TREETSCAPE C ONSTRUCTION King Street from ION Tracks south of Erb Street to Elgin Street CONSTRUCTION PROGRESS UPDATE J ULY 6, 2017 Purpose of the Meeting 1. Provide an update on the progress of the King Street Improvement


  1. U PTOWN W ATERLOO S TREETSCAPE C ONSTRUCTION King Street from ION Tracks south of Erb Street to Elgin Street CONSTRUCTION PROGRESS UPDATE J ULY 6, 2017

  2. Purpose of the Meeting 1. Provide an update on the progress of the King Street Improvement Project; 2. Learn more about the next stages of construction and the project schedule; 3. Review how vehicular and pedestrian traffic will be affected during construction; 4. Ask questions of staff from the City, Region and the Contractor, Clearway Construction Inc; and 5. Provide any comments you may have at this time (eg. special needs, scheduled deliveries, etc).

  3. PROJECT SCHEDULE: SEQUENCING OF WORK • Replacement of deep underground pipes • Installation of shallower utilities • Replacement of the road • Replacement of sidewalks • Streetlights and landscape work *Note: Accesses to businesses to be maintained throughout each aspect of the work, existing sidewalks to be maintained as long as reasonably possible (similar approach as ION work).

  4. PROJECT SCHEDULE: WHERE ARE WE NOW • BIA Membership Meeting – April 13 • King Street construction commenced on April 26 (initially planned for April 17) • Watermain and sanitary sewer has been completed in Stage 1 • Currently in the process of installing new services to buildings

  5. WHERE ARE WE NOW PROJECT SCHEDULE: CONSTRUCTION UPDATE *Started April 26 STAGE 1: ERB STREET TO BRIDGEPORT ROAD Planned Duration: April to July 2017 Progress Update: August – Roadway Complete 2016-10-21 September – Sidewalk Complete

  6. PROJECT SCHEDULE: WHERE ARE WE NOW • Erb to Dupont – roadway to be completed by the end of July, followed by work in the sidewalk area in August • Streetlights and trees will be completed in September - October with other stages • Dupont to Bridgeport – roadway anticipated to be completed by end of August with sidewalk work in September • King Street to remain closed to through traffic until September when is completed at King-Erb intersection

  7. WHERE ARE WE GOING PROJECT SCHEDULE: STAGE 2 CONSTRUCTION Start of Stage 2 work KING STREET INTERSECTION KING STREET, ERB STREET TO ION TRACKS ERB STREET, KING STREET TO ALBERT STREET Progress Update: July to September 2017 Bell work underway "King – Erb intersection scheduled to open in September as planned" ERB STREET, WATERLOO TOWN ENTRANCE TO ALBERT STREET Progress Update: September to November 2017 2016-10-21

  8. WHERE ARE WE GOING PROJECT SCHEDULE: STAGE 2 – CONSTRUCTION UPDATE STAGE 2: Traffic Control Traffic detour via Albert Street while King and Erb intersection closed from July to September 2016-10-21

  9. WHAT’S PLANNED NEXT PROJECT SCHEDULE: STAGING OF CONSTRUCTION UPDATE *Start date to be Deferred to Spring confirmed 2018 or 2019 2-way detour during Stage 2 STAGE 3: BRIDGEPORT ROAD TO ELGIN STREET Planned Duration: August to November 2017 Progress Update: September to November 2017 2016-10-21

  10. WHAT’S PLANNED NEXT "THEMATIC TREE LIGHTING" Champs-Élysées Paris, France

  11. MOVING FORWARD COMMUNICATIONS: • BIA is provided daily updates on construction progress • Weekly construction updates are provided by the BIA on behalf of the Region (via email) • Business directional signage facilitated by the BIA for installation on the fencing • BIA "Choose Local” campaign has commenced • Additional marketing and directional signage to be placed on other Region Roads • On-site construction ambassadors to provide direction and guidance for pedestrians

  12. Questions? THANK YOU FOR YOUR PATIENCE DURING CONSTRUCTION

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend