U PTOWN W ATERLOO S TREETSCAPE C ONSTRUCTION King Street from ION Tracks south of Erb Street to Elgin Street CONSTRUCTION PROGRESS UPDATE J ULY 6, 2017 Purpose of the Meeting 1. Provide an update on the progress of the King Street Improvement
SLIDE 1
SLIDE 2
Purpose of the Meeting
- 1. Provide an update on the progress of the King
Street Improvement Project;
- 2. Learn more about the next stages of construction
and the project schedule;
- 3. Review how vehicular and pedestrian traffic will be
affected during construction;
- 4. Ask questions of staff from the City, Region and the
Contractor, Clearway Construction Inc; and
- 5. Provide any comments you may have at this time
(eg. special needs, scheduled deliveries, etc).
SLIDE 3
PROJECT SCHEDULE:
SEQUENCING OF WORK
- Replacement of deep underground pipes
- Installation of shallower utilities
- Replacement of the road
- Replacement of sidewalks
- Streetlights and landscape work
*Note: Accesses to businesses to be maintained throughout each aspect of the work, existing sidewalks to be maintained as long as reasonably possible (similar approach as ION work).
SLIDE 4
PROJECT SCHEDULE:
WHERE ARE WE NOW
- BIA Membership Meeting – April 13
- King Street construction commenced on
April 26 (initially planned for April 17)
- Watermain and sanitary sewer has been
completed in Stage 1
- Currently in the process of installing new
services to buildings
SLIDE 5
2016-10-21
STAGE 1: ERB STREET TO BRIDGEPORT ROAD Planned Duration: April to July 2017 Progress Update: August – Roadway Complete September – Sidewalk Complete PROJECT SCHEDULE: CONSTRUCTION UPDATE
*Started April 26
WHERE ARE WE NOW
SLIDE 6
PROJECT SCHEDULE:
WHERE ARE WE NOW
- Erb to Dupont – roadway to be completed by the
end of July, followed by work in the sidewalk area in August
- Streetlights and trees will be completed in
September - October with other stages
- Dupont to Bridgeport – roadway anticipated to be
completed by end of August with sidewalk work in September
- King Street to remain closed to through traffic until
September when is completed at King-Erb intersection
SLIDE 7
2016-10-21
PROJECT SCHEDULE: STAGE 2 CONSTRUCTION
KING STREET INTERSECTION KING STREET, ERB STREET TO ION TRACKS ERB STREET, KING STREET TO ALBERT STREET Progress Update: July to September 2017 ERB STREET, WATERLOO TOWN ENTRANCE TO ALBERT STREET
Progress Update: September to November 2017
WHERE ARE WE GOING "King – Erb intersection scheduled to
- pen in September as planned"
Start of Stage 2 work
Bell work underway
SLIDE 8
2016-10-21
PROJECT SCHEDULE: STAGE 2 – CONSTRUCTION UPDATE WHERE ARE WE GOING STAGE 2: Traffic Control Traffic detour via Albert Street while King and Erb intersection closed from July to September
SLIDE 9
2016-10-21
PROJECT SCHEDULE: STAGING OF CONSTRUCTION UPDATE STAGE 3: BRIDGEPORT ROAD TO ELGIN STREET
Planned Duration: August to November 2017 Progress Update: September to November 2017
WHAT’S PLANNED NEXT
*Start date to be confirmed
Deferred to Spring 2018 or 2019 2-way detour during Stage 2
SLIDE 10
WHAT’S PLANNED NEXT "THEMATIC TREE LIGHTING"
Champs-Élysées Paris, France
SLIDE 11
MOVING FORWARD COMMUNICATIONS:
- BIA is provided daily updates on construction
progress
- Weekly construction updates are provided by the BIA
- n behalf of the Region (via email)
- Business directional signage facilitated by the BIA for
installation on the fencing
- BIA "Choose Local” campaign has commenced
- Additional marketing and directional signage to be
placed on other Region Roads
- On-site construction ambassadors to provide direction
and guidance for pedestrians
SLIDE 12