Tim Smart 27th June 2016
Tunnel Presentation
P1509 (1)
HOL/10014/0002
Tunnel Presentation Tim Smart 27 th June 2016 P1509 (1) - - PowerPoint PPT Presentation
Tunnel Presentation Tim Smart 27 th June 2016 P1509 (1) HOL/10014/0002 Tunnel Briefing Agenda 1. Operational aspects of tunnels (1) Safety arrangements (2) Noise and vibration (3) Vent shafts and smoke control (4) Energy use in tunnels 2.
P1509 (1)
HOL/10014/0002
2
(1) Safety arrangements (2) Noise and vibration (3) Vent shafts and smoke control (4) Energy use in tunnels
(1) Tunnelling techniques (2) Shaft construction (3) Settlement (4) Construction aspects
(1) Costs of tunnelling
P1509 (2)
HOL/10014/0003
3
P1509 (3)
HOL/10014/0004
4
Euston
Clay/Lambeth/Chalk
Northholt
Chilterns
Mudstone
Long Itchington Wood
Mudstone
Bromford
Wendover
Mudstone
Greatworth
Marlstone/Mudstone
Chipping Warden
Mudstone
Long Itchington Wood
Mudstone
Burton Green P1509 (4)
HOL/10014/0005
5
P1509 (5)
HOL/10014/0006
6
P1509 (6)
HOL/10014/0007
7
P1509 (7)
HOL/10014/0008
8
P1509 (8)
HOL/10014/0009
9
P1509 (9)
HOL/10014/0010
10
P1509 (10)
HOL/10014/0011
11
P1509 (11)
HOL/10014/0012
12
P1509 (12)
HOL/10014/0013
quality environment.
air quality environment.
13
P1509 (13)
HOL/10014/0014
14
P1509 (14)
HOL/10014/0015
15
P1509 (15)
HOL/10014/0016
16
P1509 (16)
HOL/10014/0017
17
P1509 (17)
HOL/10014/0018
18
P1509 (18)
HOL/10014/0019
19
P1509 (19)
HOL/10014/0020
20
P1509 (20)
HOL/10014/0021
21
P1509 (21)
HOL/10014/0022
22
P1509 (22)
HOL/10014/0023
23
P1509 (23)
HOL/10014/0024
24
P1509 (24)
HOL/10014/0025
25
P1509 (25)
HOL/10014/0026
26
P1509 (26)
HOL/10014/0027
27
P1509 (27)
HOL/10014/0028
28
P1509 (28)
HOL/10014/0029
29
P1509 (29)
HOL/10014/0030
30
P1509 (30)
HOL/10014/0031
31
P1509 (31)
HOL/10014/0032
32
INDICATIVE
P1509 (32)
HOL/10014/0033
33
P1509 (33)
HOL/10014/0034
The primary form of settlement mitigation will be by good tunnelling practice, including continuous
Phase 1 Assessment: A preliminary assessment based on “green field” conditions will be
assessment required. Phase 2 Assessment: In the case of predicted settlement of more than 10mm or 1/500 slope an individual building assessment will be carried out. If the potential damage classification is category 2 (slight) or below no further assessment is required. Phase 3 Assessment: Where predicted settlement indicates potential damage classification of 3 (moderate) or higher a detailed evaluation will be carried out with the aim to reduce the effects to acceptable levels. Where this is not possible further protective measures will be implemented. Settlement Deed. Properties within 30 metres of tunnels may apply for a Deed as set out in information paper C3 to ensure that protective measures are implemented in accordance with the assessment criteria.
34
P1509 (34)
HOL/10014/0035
35
P1509 (35)
HOL/10014/0036
36
P1509 (36)
HOL/10014/0037
Fixed Costs
Linear Costs
Incremental Cost increases
37
P1509 (37)
HOL/10014/0038
38
P1509 (38)
HOL/10014/0039
P1509 (39)
HOL/10014/0040