Tsilhqot’in Solar Farm
Clean Energy BC - GENERATE November 6, 2019
Tsilhqotin Solar Farm Clean Energy BC - GENERATE November 6, 2019 - - PowerPoint PPT Presentation
Tsilhqotin Solar Farm Clean Energy BC - GENERATE November 6, 2019 Solar Farm Team Michel deSpot Head Engineer Gabe Pukacz Construction Manager Dolly Kershaw Economic Development Officer FROM FEASIBILITY TO REALITY OUR STORY 2014
Clean Energy BC - GENERATE November 6, 2019
Michel deSpot – Head Engineer Gabe Pukacz – Construction Manager Dolly Kershaw – Economic Development Officer
WL Substation Solar Farm End of the line
The Chilcotin is served by a weak 250 Km-long power line that runs from Williams Lake to Tatla Lake. The low capacity of the grid throttles economic activities and must be supplemented by diesel generators.
Nits’il’in Russel Myers Ross – Yunesit’in Government Considering a small scale solar farm in the community
Yunesit’in commissioned a 2014 Feasibility Study to look at two projects:
site – 1 MW
solar farm;
BIRDS EYE VIEW OF THE SITE 35 Kv Distribution Line beside hwy.
Geotechnical and Pile Testing – November 2017
2014 2016 2017 2018 Solar Farm Time Line
Pre- Feasibility Study Completed
Council of Chiefs approve the development
Solar Farm Pre work and seek Government Funding ➢ Clarifications for land usage ➢ Land ownership ➢ March BC Hydro Application Accepted ➢ Summer BC Hydro SOP under review ➢ December BC Hydro notifies us that no more EPA’s will be issued ➢ Dialogue and Discussions between both parties March - BC Hydro announces to pursue negotiations with 5 First Nations clean energy projects August 8 Dually signed EPA received Order equipment and construction period Ballasts Trainees hired Site
repair Internet Rack Installation completed
April May June July August September Solar Farm Time Line - 2019
Start Installing PV modules Repair Winter damage
Construction Continues Construction Lots of Elementary School visits Trenching PV Modules Cables Wiring Substation Installation And Electrical Installation Construction Completed High voltage installation
Financing – Estimated cost $2.8 Million ➢ Proposal Writing and securing grants ➢ Bank Loan Contractors ➢ Expression of Interest – Engineering, Construction, Electrical ➢ RFP – Main equipment suppliers: PV modules, inverters, racks, substation ➢ Conflict of Interest
October – November 2018
April – July 2019