Day-Ahead Market Evolution Detailed Overview
Presentation to Technical Panel July 8, 2008
Day-Ahead Market Evolution Detailed Overview Presentation to - - PowerPoint PPT Presentation
Day-Ahead Market Evolution Detailed Overview Presentation to Technical Panel July 8, 2008 Focus of Presentation Provide some detail (nuts and bolts) of the common elements of the day ahead design Currently working on a
Presentation to Technical Panel July 8, 2008
2
3
4
5
6
7
8
9
10
Min Gen.
Incremental Energy
11
12
$30 $50 $20 $31 110MW 110MW
Generator A Generator B
13
14
15
16
17
Start‐up Cost Minimum
Incremental Energy Offer Minimum Load Point Minimum Run‐Time Generator A (400MW) $5000 $5500 $30/MWh 300MW 4 hours Generator B (500MW) $6000 $7000 $40/MWh 100 MW 2 hours Generator C (100MW) N/A N/A $50/MWh 0 MW N/A
18
Hour 1 400 MW Demand Hour 2 400 MW Demand Hour 3 400MW Demand Hour 4 500 MW Demand Hour 5 400 MW Demand Generator A schedule 400 MW 400 MW 400 MW 400 MW 300 MW Generator B schedule 100 MW 100 MW Generator C schedule
19
500 MW 400 MW 300 MW 200 MW 100 MW $5,000 Generator C Cost $29,000 $25,000 $21,000 $17,000 $13,000 Generator B Cost $13,500 $10,500 Generator A Cost
20
Hour 1 400MW Demand Hour 2 400MW Demand Hour 3 400MW Demand Hour 4 500MW Demand Hour 5 400MW Demand Generator A schedule 400MW 400MW 400MW 400MW 400MW Generator B schedule Generator C schedule 100MW
21
22
23
Pass 1 Constrained Run Based on Average Forecast to Obtain Unit Commitments Ontario demand forecast less dispatchable load bids Dispatchable load bids Import offers Generation
Export bids Pass 2 Constrained Run Based on Peak Forecast to Ensure Sufficient Unit Commitment to Meet Expected Peak Demand – Uses a bias to solve with internal bids and offers
Blocked on from pass 1:
Pass 3 Constrained Run Based on Average Forecast to Obtain Advisory Schedules
This should be a very quick pass of the algorithm as there is no additional unit commitment than what was determined in Pass 2 The schedules produced by Pass 3 are the day‐ahead constrained schedules (DACS)
24
25
26
Quantity (MW) 40 50 Price ($/MW)
$50
30
On‐going cost to maintain resource at minimum output level
$100
27
28
29
30
31
32
33
34
35
36