Salt Flat Bridge - 6000cfs – May 3, 2002 Salt Flat Bridge Salt Flat Bridge -
- 6000cfs
6000cfs – – May 3, 2002 May 3, 2002
Trinity River Restoration Trinity River Restoration
CVPIA Public Meeting CVPIA Public Meeting – – May 16, 2005 May 16, 2005
Trinity River Restoration Trinity River Restoration CVPIA Public - - PowerPoint PPT Presentation
Trinity River Restoration Trinity River Restoration CVPIA Public Meeting CVPIA Public Meeting May 16, 2005 May 16, 2005 Salt Flat Bridge Salt Flat Bridge - - 6000cfs 6000cfs May 3, 2002 May 3, 2002 Salt Flat Bridge -
Salt Flat Bridge - 6000cfs – May 3, 2002 Salt Flat Bridge Salt Flat Bridge -
6000cfs – – May 3, 2002 May 3, 2002
CVPIA Public Meeting CVPIA Public Meeting – – May 16, 2005 May 16, 2005
PL 84 PL 84-
386, Trinity River Division, Central Valley Project, August 12, 1955 12, 1955 -
“…the Secretary…shall adopt appropriate measures to insure the preservation and propagation of fish and wildlife… to insure the preservation and propagation of fish and wildlife…” ” PL 102 PL 102-
575, Central Valley Project Improvement Act. Section 3406(b)(23) 3406(b)(23) – – “…If the Secretary and the “…If the Secretary and the Hoopa Hoopa Valley Tribe Valley Tribe concur in the recommendations (the Trinity River Flow concur in the recommendations (the Trinity River Flow Evaluation Study)… increase to the … Evaluation Study)… increase to the … instream instream fishery releases fishery releases shall be implemented accordingly”. shall be implemented accordingly”. Section 3407 Section 3407 – – Authorizes Authorizes the CVP Restoration Fund and appropriations from that fund to the CVP Restoration Fund and appropriations from that fund to “… carry out programs, projects, plans, and habitat restoration… “… carry out programs, projects, plans, and habitat restoration… provisions of this title.” provisions of this title.”
Record of Decision (ROD) Record of Decision (ROD) – – Trinity River Trinity River Mainstem Mainstem Fishery Fishery Restoration, Page 15, December 19, 2000 Restoration, Page 15, December 19, 2000
Biggers Road Bridge
Biggers Biggers Road Bridge Road Bridge
Biggers Road Bridge
Biggers Road Bridge
Biggers Road Bridge
Buctail Road
Bucktail Road
Bucktail Road
Poker Bar Bridge
Poker Bar Bridge
Poker Bar Bridge
Poker Bar Bridge
Salt Flat Bridge
Salt Flat Bridge
Salt Flat Bridge
Salt Flat Bridge
Salt Flat Bridge
floodplain lowering, tributary enhancement
Pre-Project Condition Post-Project Condition 450 cfs 6000 cfs 450 cfs 6000 cfs Confined River Bank Rehab
(5.3 acres inundated) (17.3 acres inundated) 3.3x More Habitat
$ 0 $ 0 $ 1,000,000 $ 1,000,000 $ 3,000,000 $ 3,000,000 $ 6,000,000 $ 6,000,000 $ 10,00,0000 $ 10,00,0000 Total Program Budget Total Program Budget $ 3,000,000 $ 3,000,000 $ 800,000 $ 800,000 $ 3,800,000 $ 3,800,000 Monitoring and Analysis Monitoring and Analysis 3 3 $ 0 $ 0 $ 1,000,000 $ 1,000,000 $ 3,100,000 $ 3,100,000 $ 4,100,000 $ 4,100,000 Implementation Implementation (Restoration/Rehabilitation) (Restoration/Rehabilitation) 2 2 $ 2,100,000 $ 2,100,000 $ 2,100,000 $ 2,100,000 Program Administration Program Administration 1 1 State State CVPIA CVPIA US Fish & US Fish & Wildlife Wildlife Service Service Bureau of Bureau of Reclamation Reclamation Total Cost Total Cost Task Task # # Funding Sources Funding Sources
$ 4,100,000 $ 4,100,000 RIG Total RIG Total $ 225,000 $ 225,000 Tributaries (7100) Tributaries (7100) $ 490,000 $ 490,000 Sediment Management (7100) Sediment Management (7100) $ 1,140,000 $ 1,140,000 Channel Restoration Channel Restoration $ 1,520,000 $ 1,520,000 Bridges and Structure Bridges and Structure $ 725,000 $ 725,000 AEAM Team AEAM Team REHABILITATION AND REHABILITATION AND RESTORATION RESTORATION $ 2,100,000 $ 2,100,000 ADM Total ADM Total $ 45,000 $ 45,000 Information Management Information Management $ 145,000 $ 145,000 Independent Review committees Independent Review committees $ 60,000 $ 60,000 Trinity Adaptive Management Working Trinity Adaptive Management Working Group Group $ 775,000 $ 775,000 Trinity Management Council Trinity Management Council $ 1,075,000 $ 1,075,000 AEAM Team AEAM Team-
Weaverville Office PROGRAM ADMINISTRATION PROGRAM ADMINISTRATION $ 3,800,000 $ 3,800,000 TMAG Total TMAG Total $ 255,000 $ 255,000 Wildlife Studies Wildlife Studies $ 85,000 $ 85,000 Riparian Vegetation Riparian Vegetation $ 1,153,000 $ 1,153,000 Run Size/Angler Harvest Run Size/Angler Harvest $ 340,000 $ 340,000 Hatchery Practices Hatchery Practices $ 545,000 $ 545,000 Migration Studies Migration Studies $ 212,000 $ 212,000 Adult Health Studies Adult Health Studies $ 415,000 $ 415,000 Sediment Management Sediment Management $ 415,000 $ 415,000 Stream Stream Gaging Gaging $ 380,000 $ 380,000 AEAM Team AEAM Team MODELING AND ANALYSIS MODELING AND ANALYSIS $ 10,000,000 $ 10,000,000 Grand Total Grand Total
Trinity River Restoration Program Trinity River Restoration Program
Draft FY 2004 Budget Draft FY 2004 Budget
2009 2008 2007 2006 2005 2004 Rehab Sites
Hocker Flat Hocker Flat (n=1) (n=1) Sites Below Sites Below Canyon Creek Canyon Creek (n=4) (n=4) Indian Creek Indian Creek (n=3) (n=3) Lewiston 4 Lewiston 4 and Dark Gulch and Dark Gulch (n=8) (n=8) Remaining Remaining Phase 1 Sites Phase 1 Sites (n=8) (n=8)
5/16/05
Total: 24 Rehabilitation Sites Total: 24 Rehabilitation Sites
Design, NEPA/CEQA, Design, NEPA/CEQA, Permits, Contracting Permits, Contracting Construction Construction Revegetation Revegetation
Floodplain Implementation Schedule
2004 2005 2006 Task
Inventory Inventory Prepare Prepare Floodplain for Floodplain for 8,500 cfs 8,500 cfs Prepare Prepare Floodplain for Floodplain for 11,000 cfs 11,000 cfs Well & Septic Grant Well & Septic Grant Program Program
Inventory Design, NEPA/CEQA, Permits, Contracting Construction
4/15/05