1 Tri-State December 2013 Board Meeting
Tri-State December 2013 Board Meeting 1 Who We Are Tri-State is a - - PowerPoint PPT Presentation
Tri-State December 2013 Board Meeting 1 Who We Are Tri-State is a - - PowerPoint PPT Presentation
Tri-State December 2013 Board Meeting 1 Who We Are Tri-State is a not-for-profit, wholesale power supplier owned by 44 electric cooperatives and public power districts serving a population of approximately 1.4 million people. Purpose of
Who We Are
Tri-State is a not-for-profit, wholesale power supplier
- wned by 44 electric
cooperatives and public power districts serving a population of approximately 1.4 million people.
Purpose of This Public Meeting
- Involve all interested stakeholders in Tri-State’s
transmission planning process.
- Review current study plan.
- Solicit information from transmission customers
- n potential loads and resources.
- Answer your questions.
Transmission Planning Objectives
- Provide Transmission Service to all network
customers.
- Provide Reliable Service under NERC/WECC
Reliability Standards.
- Provide Low Cost Service to Member owners.
- Provide Access to other stakeholders for the
efficient planning, utilization and development
- f the transmission system.
Basic Statistics
- 5,396 miles of transmission in which Tri-State has an
- wnership or capacity interest:
1220 miles - 345 kV
1001 miles - 230 kV
184 miles - 138 kV
2942 miles - 115 kV
49 miles - 69 kV
- Over 220 bulk system substations
- David A. Hamil DC Tie at Stegall, NE
- Extensive high-speed communications system of fiber optics
and microwave links for operation and control of the transmission system.
Transmission System
Telecommunications System
1500 miles of fiber 455 radio sites
Inputs to study plan
- Network Customers identify load and resource
requirements annually.
- Other Transmission Providers update base case
assumptions (system topology, loads and resources).
- Tri-State Member Systems request new delivery
points throughout the year.
Inputs to study plan (continued)
- Generation Interconnection customers submit
applications (two open seasons).
- Regulatory and governmental agencies introduce
policy initiatives.
- Tri-State’s Board of Directors make decisions on
capital expenditures.
10 Tri-State December 2013 Board Meeting
Caballo – Mimbres 115 kV Rebuild
Caballo – Mimbres 115 kV Rebuild
Description: Rebuild / re-conductor existing 115kV line with 477 MCM ACSR and steel pole H-frame structures. Voltage: 115 kV Length: 57 miles Type: Line Status: Continuing Planned ISD: 2019 Purpose: Replace aging structures and conductor. Increase capacity and improve load-serving capability and reliability to Sierra Electric.
12 Tri-State December 2013 Board Meeting
Escalante – Gallup 115 kV Line Uprate
Escalante – Gallup 115 kV Line Uprate
Description: Uprate existing line to a minimum of 80 MVA (400 amps). Voltage: 115 kV Length: 42 miles Type: Line Status: Continuing Planned ISD: 2015 Purpose: A reliability improvement to eliminate potential overloading of the existing line for NERC Category B contingencies.
14 Tri-State December 2013 Board Meeting
Picacho – Las Cruces 115 kV Uprate
Picacho – Las Cruces 115 kV Uprate
Description: Uprate existing line to 100 degrees C thermal rating (932 amps). Voltage: 115 kV Length: 3.5 miles Type: Line Status: Continuing Planned ISD: 2015 Purpose: A reliability improvement to eliminate potential overloading of the existing line for a NERC Category B contingency.
16 Tri-State December 2013 Board Meeting
Gladstone 230 kV Phase Shifting Transformer
Gladstone 230 kV Phase Shifting Transformer
Description: Install 300 MVA 230 kV +/- 60 degree PST at Gladstone Substation. Voltage: 230 kV Type: Substation Status: Complete Planned ISD: 2015 Purpose: Permits control of north to south flows into northern New Mexico and mitigates potential
- verloads on the 115 kV system.
18 Tri-State December 2013 Board Meeting
Wayne Child Sub Additions
Wayne Child Sub Additions
Description: Tap LRS-Story line adjacent to Archer. Add 345/230 kV 600 MVA transformer and 230 kV tie to Archer Substation. Voltage: 345 kV and 230 kV Length: 0 miles Type: Substation / Line Status: Continuing Planned ISD: 2018 Purpose: Improve Tri-State’s power delivery and load serving capabilities from its LRS generation. Project increases TOT3 transfer capability.
20 Tri-State December 2013 Board Meeting
Southeast Wyoming Transmission Project
Southeast Wyoming Transmission Project
Description: Construct a 230/115 kV 150 MVA substation connecting to the LRS-DJ line and a 115 kV transmission line to Belle Fourche. Voltage: 115 kV Length: 50 miles Type: Line Status: Continuing Planned ISD: 2016 Purpose: Improve load-serving capability and reliability to Niobrara Electric Association’s 69 kV system.
22 Tri-State December 2013 Board Meeting
Wind River 115 kV Reliability Upgrade
Wind River 115 kV Reliability Upgrade
Description: Construct a 230/115 kV interconnection to the PACE Wyopo Substation, a 115 kV ring bus at Wind River and a 115 kV line connecting the two substations. Voltage: 115 kV Length: 17 miles Type: Substation / Line Status: Planned Planned ISD: 2019 Purpose: Mitigate potential voltage stability issues and improve power delivery and load serving capabilities to the Wind River area.
24 Tri-State December 2013 Board Meeting
Badwater–DJ 230 kV Project
Badwater-DJ 230 kV Project
Description: Construct a 230 kV line between the Badwater substation and a new station sectionalizing the Dave Johnston (DJ) to LRS 230 kV line. Voltage: 230 kV Length: 117 miles Type: Substation / Line Status: Planned Planned ISD: To be determined Purpose: Increase power delivery and load serving capabilities to the Badwater area by approximately 180 MW. Increase TOT 4B ATC.
26 Tri-State December 2013 Board Meeting
Big Sandy - Calhan
27 Tri-State December 2013 Board Meeting
Big Sandy - Calhan
Description: New 230 kV line between Big Sandy and Calhan Substations Voltage: 230 kV Length: 55 miles Type: Line Status: Planned Planned ISD: 2019 Purpose: Support Member load between Denver and Colorado Springs
28 Tri-State December 2013 Board Meeting
Boone – Walsenburg 230 kV Line
29 Tri-State December 2013 Board Meeting
Boone – Walsenburg 230 kV Line
Description: Construct a 230 kV transmission line from Boone Substation to Walsenburg Substation Voltage: 230 kV Length: 69 miles Type: Line Status: Planned Planned ISD: To be determined Purpose: Reliability – eliminate the need for the existing Walsenburg Remedial Action Scheme (RAS)
30 Tri-State December 2013 Board Meeting
Lamar – Boone 230 kV Line
31 Tri-State December 2013 Board Meeting
Boone – Walsenburg 230 kV Line
Description: Construct a 230 kV transmission line from Boone Substation to Lamar Substation Voltage: 230 kV Length: 100 miles Type: Line Status: Planned Planned ISD: To be determined Purpose: Accommodate potential increased resource injection at Lamar.
32 Tri-State December 2013 Board Meeting
Burlington – Lamar 230 kV Transmission Project
33 Tri-State December 2013 Board Meeting
Burlington – Lamar 230 kV Transmission Project
Description: Construct a 230 kV transmission line from Burlington to Lamar. Voltage: 230 kV Length: 107 miles Type: Line Status: Continuing Planned ISD: 2020 Purpose: Member network service, load-serving, reliability.
34 Tri-State December 2013 Board Meeting
Burlington – Wray 230 kV Line
35 Tri-State December 2013 Board Meeting
Burlington – Wray 230 kV Line
Description: Construct new 230 kV line from the existing Burlington Substation to the existing Wray Substation Voltage: 230 kV Length: 72 miles Type: Line Status: Under Construction Planned ISD: 2016 Purpose: Improve load-serving capability, remove generation operating restrictions and support renewable resource development in eastern Colorado.
36 Tri-State December 2013 Board Meeting
Falcon – Midway 115 kV Line Uprate Project
37 Tri-State December 2013 Board Meeting
Falcon – Midway 115 kV Line Uprate Project
Description: Planned uprate of existing 115 kV line between Falcon and Midway Voltage: 115 kV Length: 27miles Type: Distribution Status: Planned Planned ISD: 2017 Purpose: Increase conductor thermal rating
38 Tri-State December 2013 Board Meeting
Keota 345:115 kV
39 Tri-State December 2013 Board Meeting
Keota 345:115 kV
16-18 mile, double circuit 115 kV 8 mile, double circuit 115 kV
- Function:
- Serve increasing High West Energy and Morgan County Rural Electric
Association loads (Oil and Gas).
- Description:
- Sectionalize the existing LRS – Story 345 kV line.
- Construct 345/115 kV substation (2 x 225 MVA transformers)
- Construct a double circuit 115 kV line to two load serving substations:
Redbox and Redtail.
- Planned ISD:
- Keota substation: Complete.
- Keota – Redbox – Redtail 115 kV: 2015/2016.
- Regulatory Status:
- CPCN Granted.
0.5 mile, single circuit 115 kV
40 Tri-State December 2013 Board Meeting
Keota 345:230 kV (a.k.a. Pony Creek)
41 Tri-State December 2013 Board Meeting
- Function:
- Serve increasing Morgan County Rural Electric Association oil and gas
loads.
- Description:
- Construct 345:230 kV substation at Keota (2 x 600 MVA transformers).
- Construct single circuit 230 kV line to Pony Creek substation.
- Tie new 230 kV system with Redbox 115 kV through either a short 115 kV
line, or by expanding Redbox to include 230 kV yard.
- Planned ISD:
- To be determined
- Regulatory Status:
- CPCN Applied 11/26/2014
18 mile, single circuit 230 kV New 230/115kV Pony Creek substation
Keota 345:230 kV (a.k.a. Pony Creek)
3.5 mile, double circuit 115x230 kV
42 Tri-State December 2013 Board Meeting
Keota 3rd Source
43 Tri-State December 2013 Board Meeting
Keota 3rd Source
Description: New 230 kV transmission line to Keota Voltage: 230 kV Length: To be determined Type: Transmission Status: Planned Planned ISD: To be determined Purpose: Increase Keota load serving capability
44 Tri-State December 2013 Board Meeting
Lamar – Front Range Project
45 Tri-State December 2013 Board Meeting
Lamar – Front Range Project
Description: Two high voltage transmission paths from Lamar Substation to Pueblo area and a second path from Lamar to substations near Brush and/or Deer Trail Voltage: 345 kV Length: 300 – 350 miles Type: Line Status: Conceptual Planned ISD: To be determined Purpose: Tri-State reliability, system load-serving connectivity as regional power provider and future resources. Xcel Senate Bill07-100 and reliability.
46 Tri-State December 2013 Board Meeting
Western Colorado Transmission Upgrade Project
47 Tri-State December 2013 Board Meeting
Western Colorado Transmission Upgrade Project
Description: Upgrade existing transmission line and facilities from Montrose Substation to Cahone Substation from 115 kV operation to 230 kV. Voltage: 230 kV Length: 80 miles Type: Line Status: Under Construction Planned ISD: 2018 Purpose: Reliability – eliminate need for existing Nucla Remedial Action Scheme and replace failing structures.
48 Tri-State December 2013 Board Meeting
Pueblo West Tap Line Uprate
49 Tri-State December 2013 Board Meeting
Pueblo West Tap Line Uprate
Description: Upgrade existing 115 kV line conductor Voltage: 115 kV Length: 0.3 miles Type: Line Status: Under Construction Planned ISD: 2015 Purpose: Reliability, eliminate overloading of existing line for NERC Category B contingency
50 Tri-State December 2013 Board Meeting
San Juan Basin Energy Connect Project
51 Tri-State December 2013 Board Meeting
San Juan Basin Energy Connect Project
Description: New 230 kV transmission line between existing WAPA Shiprock Substation in New Mexico to a new 230 kV Iron Horse
- Substation. A new 230 kV Kiffen Canyon
Substation will also be required Voltage: 230 kV Length: 70 miles Type: Line Status: Under Construction Planned ISD: 2018 Purpose: Reliability for loss of Hesperus 345 kV source and to serve approximately 100 MW of new industrial load in SW Colorado
52 Tri-State December 2013 Board Meeting
Lost Canyon – Main Switch 115 kV Project
53 Tri-State December 2013 Board Meeting
Lost Canyon – Main Switch 115 kV
Description: New transmission line between Lost Canyon and Main Switch Voltage: 115kV Length: 20 miles Type: Line Status: Planned Planned ISD: To be determined Purpose: Increase load serving capability
54 Tri-State December 2013 Board Meeting
Southwest Weld Expansion Project
Southwest Weld Expansion Project
Description: Construct approximately 49 aggregated miles
- f 115 kV and 230 kV transmission lines with
six potential load-serving substations and/or line taps. Voltage: 115/230 kV Length: 49 miles Type: Line Status: Under Construction Planned ISD: 2017 Purpose: Load Serving Potential plans for project extension to the north are presently being evaluated by Tri- State and Xcel Energy.
56 Tri-State December 2013 Board Meeting
United Power System Improve Project Phase III
57 Tri-State December 2013 Board Meeting
United Power System Improve Project Phase III
Description: New 115 kV transmission line between Bromley and Prairie Center Substations Voltage: 115 kV Length: 4.1 miles Type: Distribution Status: Under Construction Planned ISD: 2016 Purpose: Provide transmission service between Bromley and Prairie Center
58 Tri-State December 2013 Board Meeting
Valley Corridor Transmission (SLV 230 kV Line Reliability)
59 Tri-State December 2013 Board Meeting
Valley Corridor Transmission (SLV 230 kV Line Reliability)
Description: New 230 kV transmission line from the existing San Luis Valley Substation to a new 230/345 kV substation located west of Taos,
- NM. The new 230/345 kV substation will tap
the existing Taos – Ojo 345 kV line and will include 230/345 kV transformation and phase shifting transformer. Voltage: 230 kV Length: To be determined Type: Line Status:
- Cancelled. New alternatives being studied in
Colorado Coordinated Planning Group. Planned ISD: To be determined Purpose: Mitigate N-1 voltage collapse in the San Luis Valley and corresponding Under Voltage Load Shedding (UVLS) needs. Provide looped service form alternative transmission corridor.
For more information
www.tristategt.org About Us Transmission Planning www.tristategt.org Operations OATT Queues and Studies
61 Tri-State December 2013 Board Meeting