Transportation Roundtable Executive Committee July 31, 2017 GDOT PROJECTS WITH UNFUNDED PHASES TO COMPLETION Middle Georgia Regional Commission area 2 BIBB COUNTY : I-75 from I-16 to PIERCE AVE. (PHASE VI) Road Widening: 1.17 mi.


  1. Transportation Roundtable Executive Committee July 31, 2017

  2. GDOT PROJECTS WITH UNFUNDED PHASES TO COMPLETION Middle Georgia Regional Commission area 2

  3. BIBB COUNTY : I-75 from I-16 to PIERCE AVE. (“PHASE VI”) Road Widening: 1.17 mi. UTIL $ 1,000,000 CONST $ 40,000,000 Total: $ 41,000,000 GDOT PI # 311400 3

  4. BIBB COUNTY: COLLEGE STREET @ N-S R.R. (#718370R) in MACON Bridge Replacement UTIL $ 160,000* CONST $ 1,400,000* Total: $ 1,560,000* GDOT PI # 0014899 *Does not include local match 4

  5. BIBB COUNTY: OGLETHORPE STREET @ N-S R.R. (#718371X) in MACON Bridge Replacement UTIL $ 160,000* CONST $ 1,200,000* Total: $ 1,360,000* GDOT PI # 0014898 *Does not include local match 5

  6. HOUSTON COUNTY: SR 7/US 41 @ FLAT CREEK (3.5 mi. southwest of Perry) Bridge Replacement UTIL $ 50,000 CONST $ 2,100,000 Total: $ 2,150,000 GDOT PI # 0015552 6

  7. HOUSTON COUNTY: SR 7/SR 127/US 41 @ BIG INDIAN CREEK in PERRY Bridge Replacement UTIL $ 50,000 CST $ 4,500,000 Total: $ 4,550,000 GDOT PI # 0015553 7

  8. JONES COUNTY: FOLENDORE ROAD @ COMMISSIONER CREEK (5.1 mi. east of Gray) Bridge Replacement CONST $ 1,200,000 Total: $ 1,200,000 GDOT PI # 0015655 8

  9. MONROE COUNTY: JOHNSTONVILLE ROAD @ ROCKY CREEK (5 mi. north of Forsyth) Bridge Replacement UTIL $ 50,000 CONST $ 1,300,000 Total: $ 1,350,000 GDOT PI # 0015643 9

  10. PULASKI COUNTY: SR 11/US 129 @ BLUFF CREEK (4.7 mi. east of Finleyson) Bridge Replacement R-O-W $ 150,000 UTIL $ 130,000 CONST $ 2,500,000 Total: $ 2,780,000 GDOT PI # 0005533 10

  11. PUTNAM COUNTY : SR 24/US 441 from EATONTON BYPASS to MORGAN CO. Road Widening: 9.19 mi. UTIL $ 1,250,000 CONST $ 46,250,000 Total: $ 47,500,000 GDOT PI # 0013615 11

  12. PUTNAM / GREENE COUNTIES: SR 44 from SR 24/US 441 to LINGER LONGER ROAD Road Widening: 11.8 mi. UTIL $ 10,200,000 CONST $ 66,750,000 Total: $ 76,950,000 GDOT PI # 0006252 12

  13. PUTNAM COUNTY: MARTINS MILL ROAD @ LITTLE RIVER (4.5 mi. northwest of Eatonton) Bridge Replacement CONST $ 1,600,000 Total: $ 1,600,000 GDOT PI # 0015658 13

  14. TWIGGS COUNTY: SR 96 from 0.48 mi. west of SR 87/US 23 to I-16 Road Widening : 7.64 mi. UTIL $ 1,100,000 CONST $ 45,325,000 Total: $ 46,425,000 GDOT PI # 322470 14

  15. WILKINSON COUNTY: ROSE JUSTICE ROAD @ BIG SANDY CREEK (2.5 mi. south of Irwinton) Bridge Replacement CONST $ 2,200,000 Total: $ 2,200,000 GDOT PI # 0015648 15

  16. Houston County Project Types (26) Type Number Aviation 3 Bike / Ped 1 Improvements 16 Construction 6

  17. Houston County Projects Airport Projects MGRC-062 Runway Rehab and Extension (5,000 to 6,000 ft) * MGRC-063 New terminal (to meet Level II airport requirements) * MGRC-064 Hangars (2) * Bike / Pedestrian Projects MGRC-009 Collins Avenue Sidewalks (2 miles) * * 2012 Final Investment List

  18. Houston County Projects (cont) MGRC-163 St. Patrick’s Drive Extension (to North Perry Bypass/ Thompson Road) * MGRC-164 West Perry Bypass Extension (Industrial Park Drive to Perry Parkway) * MGRC-068 US 341 Widening (north of Perry Parkway to SR 96) MGRC-162 Langston / Arena Road Connector (to Arena Road) MGRC-072 US 341 Widening (Arena to Golden Isles Parkway) MGRC-074 Boutwell Road Widening (Golden Isles Parkway to US 341) MGRC-070 SR 247 Widening (96 to Houston Pulaski County Line) see also MGRC-203 MGRC-067 SR 247 Passing Lanes (Big Indian Creek to Kovac Rd) MGRC-065 Thompson Mill Road Extension (to SR 247) * 2012 Final Investment List

  19. Houston County Projects (cont) MGRC-180 SR 96 Widening (Thompson Mill to SR 87/ US 23) * MGRC-175 South Davis Drive Extension (to Sandy Run Road) MGRC-177 US 41 Widening (SR 96 to SR 49) MGRC-178 SR 247C Operational Improvements (US 41 to Carl Vinson) * MGRC-066 Gunn Road (SR 247C to US 41) * see also MGRC-161 MGRC-010 Houston Lake Road (Thompson Road to US 41) * MGRC-069 Dunbar Road (US 41 to Elberta Road) see also MGRC-022 MGRC-208 Houston Road (SR 49 to Sardis Church) * 2012 Final Investment List

  20. Houston County Projects (cont) MGRC-181 SR 49 Widening (75 to US 41) MGRC-207 Carl Vinson Parkway Extension (Dunbar to Sardis Church) MGRC-179 Elberta Road (Northside to SR 247) MGRC-176 Davis Drive (SR 247C to SR 247 to J-STARS) MGRC-071 SR 247 Widening (SR 247C to US 41)

  21. Peach County Project Types (25) Type Number Bike / Ped 1 Improvements/ Maintenance 21 Construction 3

  22. Peach County Projects Road Projects MGRC-020 Chapman Road Widening and Resurfacing (49 to Benjamin Hawkins)* MGRC-013 Chapman Road Extension (Benjamin Hawkins to Sardis Church Road) MGRC-014 Boy Scout Road Widening and Resurfacing MGRC-015 Old Macon Road Widening and Resurfacing MGRC-019 Woodland Drive Intersection (with Old Macon Road) MGRC-022 Dunbar Road Widening and Resurfacing (49 to US 41) see also MGRC-069 * 2012 Final Investment List

  23. Peach County Projects (cont) Road Projects MGRC-016 WE Green Road (Byron) MGRC-021 New Dunbar Street (Byron) MGRC-017 Main Street Resurfacing (Byron) MGRC-018 Moseley Road Resurfacing (Byron) MGRC-012 Green Street Realignment (Byron) MGRC-011 White Road Realignment (Byron) (Linda to SR 49) * MGRC-023 White Road (Byron) (SR 49 to US 41) * 2012 Final MGRC-025 Walker Road (Byron) Investment List

  24. Peach County Projects (cont) Roadway Projects MGRC-206 Housers Mill (SR247C to Sledge) MGRC-024 Peavy Road (White Road to SR247C) MGRC-161 Gunn Road Realignment (with SR 247C) (see also MGRC-66) MGRC-159 SR 49 Connector Extension (to SR 96) MGRC-160 SR 96 (Fire Tower Road to Housers Mill) MGRC-205 Sign Replacement (Byron)

  25. Peach County Projects (cont) Road Projects MGRC-030 Taylors Mill Resurfacing (Fort Valley) MGRC-031 Sidewalk Rehab (1.1 miles on Hwy 96 West) MGRC-028 Montrose Street Resurfacing (Fort Valley) MGRC-029 Spruce Street Resurfacing (Fort Valley) MGRC-027 Oakland Heights / 341 Intersection (Fort Valley)

  26. Pulaski County Project Types (4) Type Number Airport 1 Transit 1 Improvement 2

  27. Pulaski County Projects Airport Projects MGRC-200 Hawkinsville / Pulaski County Airport Improvements* Transit Projects MGRC -202 Transit Van; operational support Roadway Improvement Project MGRC-201 SR 11 / SR 230 Intersection Improvements* * 2012 Final MGRC-203 Passing Lanes 247 (US 341 to Pulaski/ Houston line) * Investment List

  28. Twiggs County Project Types (17) Type Number Construction 1 Improvement / Maintenance 13 Bridge 1 Bike / Ped 2

  29. Twiggs County Projects Bike and Pedestrian Projects MGRC-041 Hwy 80 Sidewalks MGRC-042 MLK Sidewalks Bridge Project MGRC-170 SR 19 Bridge Replacement (at Dry Branch) * * 2012 Final Investment List

  30. Twiggs County Projects (cont) Resurfacing and Maintenance Projects MGRC-032 Highway 19 (in Jeffersonville) MGRC-033 Solomon Drive MGRC-034 Walnut Street Total Distance: 7.94 miles MGRC-035 Evert Street MGRC-036 Family Circle MGRC-037 Railroad Street MGRC-038 School Drive MGRC-039 Park Street MGRC-40 Hwy 96 (in Jeffersonville)

  31. Twiggs County Projects (cont) Intersection Improvements MGRC-043 Hwy 80 and Magnolia Street Roadway Construction/ Improvements MGRC-044 Worsham Lane (Jeffersonville) MGRC-026 Williams Road (Danville) MGRC-173 Widening SR 18 from Jeffersonville to CR 185 Asbury Church Road MGRC-174 Widening SR 96 (I-16 to US 23/ SR 87) * * 2012 Final Investment List

  32. Putnam County Request

  33. Further Consideration Discussions BY TYPE

  34. Constrained List As of June 12, 2017 April 2018-March 2028 Total Revenue Projected $637,746,847 75% for Project Investment List $478,310,135 Less Project Delivery Cost (4.8%) ($23,000,000) Less Inflation (3.6%) ($85,752,026) Balance (2017 $) $369,558,109

  35. Overview of Unconstrained List Airport $48,172,384 Bike / Ped $20,359,187 Bridge $12,741,660 Transit $38,528,174 Roads $1,427,882,838 Total Estimated Costs (2017 $) $1,502,497,823 Budget $369,558,109

  36. Further Consideration Discussions Project Type Airport Blue Bike / Pedestrian (Stand Alone) Green Bridge (Stand Alone) Pink Transit Yellow

  37. Further Consideration Discussions - Roads BY COUNTY AND BY TYPE

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.