Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 - - PowerPoint PPT Presentation

transmission planning annual stakeholder outreach meeting
SMART_READER_LITE
LIVE PREVIEW

Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 - - PowerPoint PPT Presentation

Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11 Purpose of This Meeting To allow stakeholders the opportunity to participate in Tri-States transmission planning process consistent with: Development of Tri-States


slide-1
SLIDE 1

Transmission Planning Annual Stakeholder Outreach Meeting 10.17.11

slide-2
SLIDE 2

Purpose of This Meeting

To allow stakeholders the opportunity to

participate in Tri-State’s transmission planning process consistent with:

 Development of Tri-State’s long-term

transmission plans

 Attachment L of Tri-State’s OATT  CPUC 3627  Generator Interconnection Procedures

slide-3
SLIDE 3

Blane Taylor Senior Manager, Power Systems Planning 303-254-3659 btaylor@tristategt.org

slide-4
SLIDE 4

Agenda

Overview of Tri-State Tri-State Planning Process 2011-2020 L&R Resource Assumptions Transmission Capital Construction Plan Generation Interconnections OATT update

slide-5
SLIDE 5

Background

 Tri-State is a member owned, not-for-profit, generation

and transmission cooperative

 44 member owners across NM (12), CO (18), NE (6), WY (8)  Members serve approximately 1.4 million  200,000 square miles of service territory

 Mission Statement:

 “Provide our member owners a reliable, cost-based supply of

electricity while maintaining a sound financial position through effective utilization of human, capital and physical resources in accordance with cooperative principles.”

slide-6
SLIDE 6

Tri-State G&T Member Cooperative Systems

slide-7
SLIDE 7

Basic Statistics

 Peak Member Load (Summer 2011) ~ 2834 MW  5 meters / line mile average  Load by State

 New Mexico

471 MW ~ 17%

 Colorado

1729 MW ~ 61%

 Nebraska

357 MW ~ 12%

 Wyoming

277 MW ~ 10%

 Diverse Membership

 United Power– Brighton, CO – 65,000 meters – 300 MW  Garland L&P- Powell, WY – 1,900 meters – 6 MW

slide-8
SLIDE 8

Tri-State’s Transmission System

 Tri-State wholly or jointly owns 5,177 miles of transmission

 1220 miles - 345 kV  984 miles - 230 kV  184 miles - 138 kV  2740 miles - 115 kV  49 miles - 69 kV

 ~ 220 Stations  ~ 400 Communication Sites  DC Tie (Stegall, NE)  Operations Center / Backup Control Center

slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Tri-State Generation Resources

 1,408 MW coal  797 MW gas  30 MW solar (PPA)  51 MW wind (PPA)

 Additional co-op member renewable projects

 Contracts

 ~ 600 MW federal hydroelectric allocation  Basin Electric purchase

slide-14
SLIDE 14
slide-15
SLIDE 15

Tri-State Planning Process

slide-16
SLIDE 16

About WestConnect

 WestConnect is composed of utility companies

providing transmission of electricity in the United States.

 The members work collaboratively to assess

stakeholder and market needs and to develop cost- effective enhancements to the western wholesale electricty market.

 WestConnect is committed to coordinating its

work with other regional industry efforts to achieve as much consistency as possible in the Western Interconnection.

slide-17
SLIDE 17

WestConnect Footprint

slide-18
SLIDE 18

Tri-State Planning Process

Tri-State performs and participates in transmission planning consistent with FERC 890 principles for coordinated, open and transparent planning. Tri-State coordinates its planning with other transmission providers and stakeholders at the regional and sub regional levels of the Western Interconnection. CCPG SWAT WestConnect WECC

slide-19
SLIDE 19

Tri-State Planning Process

Tri-State performs and participates in transmission planning consistent with FERC 890 principles for coordinated, open and transparent planning. Tri-State coordinates its planning with other transmission providers and stakeholders at the regional and sub regional levels of the Western Interconnection. CCPG SWAT WestConnect WECC

slide-20
SLIDE 20

2011-2020 L&R Resource Assumptions

slide-21
SLIDE 21

2011-2020 L&R Resource Assumptions

Resource additions:

 50 MW wind, Lamar, CO 2015  50 MW wind Archer, WY 2015  588 MW combined cycle, Lamar, CO 2017  100 MW wind Archer, WY 2018  200 MW wind Lamar, CO 2020

slide-22
SLIDE 22

Transmission Capital Construction Plan

slide-23
SLIDE 23

Gladstone 230 kV Phase Shifting Transformer

Gladstone

slide-24
SLIDE 24

230 kV Santa Rosa-Gladstone Line

Santa Rosa Gladstone

slide-25
SLIDE 25

Dulce Chama

Chama-Dulce 69 to 115 kV Line Upgrade Project

Santa Rosa Gladstone

slide-26
SLIDE 26

Dulce Chama

Dulce-Navajo Dam 115 kV Line

Santa Rosa Gladstone Navajo Dam

slide-27
SLIDE 27

Nucla

Nucla-Telluride 115 kV Line

Telluride Sunshine

slide-28
SLIDE 28

Plaza Waverly Nucla

Plaza-Waverly 115 kV Loop Project

Telluride Sunshine

slide-29
SLIDE 29

Plaza Waverly Nucla

San Juan Project

Telluride Sunshine Shiprock Iron Horse

slide-30
SLIDE 30

Big Sandy Midway Lincoln

230 kV Big Sandy-Lincoln-Midway Line Uprate

slide-31
SLIDE 31

Big Sandy Midway Lincoln

230 kV Big Sandy-Calhan Line

Calhan

slide-32
SLIDE 32

Big Sandy Midway Lincoln Calhan Falcon Paddock

115 kV Midway-Falcon Line Uprate Falcon-Paddock 69>115 kV Line Upgrade 115 kV Paddock-Calhan Line

slide-33
SLIDE 33

Comanche Calumet To San Luis Valley Sub Big Sandy Midway Lincoln Calhan Falcon Paddock

San Luis Valley-Calumet-Comanche Transmission Project

slide-34
SLIDE 34

Comanche Calumet To San Luis Valley Sub Big Sandy Midway Lincoln Calhan Falcon Paddock

Wayne Child-Cheyenne Project

Wayne Child Cheyenne

slide-35
SLIDE 35

Comanche Calumet To San Luis Valley Sub Big Sandy Midway Lincoln Calhan Falcon Paddock

230 kV Burlington-Wray Line

Wayne Child Cheyenne Burlington Wray

slide-36
SLIDE 36

Comanche Calumet To San Luis Valley Sub Big Sandy Midway Lincoln Calhan Falcon Paddock

Ogallala-Roscoe 115 kV Line Rebuild

Wayne Child Cheyenne Burlington Wray Ogallala Roscoe

slide-37
SLIDE 37
slide-38
SLIDE 38

Questions?

38

slide-39
SLIDE 39

Ray A. LaPanse, P.E. Transmission Interconnection Administrator (303) 254-3154 rlapanse@tristategt.org

slide-40
SLIDE 40

Generator Interconnection Procedures

Summary of GIP Basics & GIR Queues

slide-41
SLIDE 41

41

Generator Interconnection Procedures - Reform & Basics

 GIP reform process began in November 2008.  Final Generator Interconnection Procedures (GIP) went

into effect July 1, 2010, and continues to be updated periodically as necessary (next Rev. planned for 12/1/2011).

 Covers all sizes of generation projects connected to Tri-

State’s transmission system.

 Does not cover interconnections to Tri-State member

cooperative systems.

 NOTE – The GIP does not discuss or address Tri-State

Transmission Service or Generation Network Resource issues (Energy Resources - Merchant Group).

slide-42
SLIDE 42

First Ready-First Served

Option A) First Come-First Served

Option B) Fast track (expedited SIS, sec. 7.1.1) with confirmed customer

Review Published Load & Resource Trans- mission Study Two month windows to submit application. IR Applications reviewed on semi-annual basis. Attend Information Session at Beginning of IR Application Window Customer may have access to Base Case Data (with confidentiality agreement) and may perform own Studies

Facilities Study

Customer submits deposit

  • f 25% of

Facility Cost & TSR or proceeds at own risk

Defer FacSA up to 18 months

Submit IR Network Upgrade Studies

Customer

TSR Path At Risk or non- designated Network Resource Path

Detailed Modeling data + Deposit: > 75 MW--$250,000; 21 to 75 MW--$75,000 11-20 MW--$50,000; <= 10 MW-- $25,000 (Includes non-refundable portion) Proof of 25% Site Control at time of application

SIS Scoping Meeting Three levels of generation allowed and specified for study at time of meeting: 1.Network Upgrades for IR MW Request; 2.Max MW with no internal NUs; 3.Alt. MW level, if agreed to, up to 60% less than MW

  • f IR.

SIS

After power flow portion

  • f SIS,

meet with Customer, customer must select

  • ne

generation level & POI

SIS Review

(with cost estimates)

and FS Scoping Meeting and Agreement Shows Designation as Network Resource & submits deposit of 25% of Facility Cost, 50% Site Control, signs FacSA.

LGIA

100% Site Control + 100% of Facility Cost

slide-43
SLIDE 43

GIP Process Implementation

43

  • Update on recent efforts and progress made in the Generation

Interconnection Study process:

  • Major work completed in developing power flow “TSGT GIP base

case” models (2012 & 2015, HS & LA, PSSE-V32 & PSLF-V17) that have been reviewed and included input from regional entities (TSGT, XE/PSCo, BHC, CSU, WAPA, BEPC, etc.).

  • Tracking of study costs and implementing quarterly cost account

summary reports to be issued to Interconnection Customers.

  • Improved review of IR filings , customer facilities model data,

clarification of TSGT interconnection and operational criteria (voltage regulation, dynamics, etc.) to minimize need for re-study.

  • Pre-GIR Application Information:
  • Phone call and single meeting discussion of Tri-State’s GIP process

/ requirements, and Queue & completed reports on OASIS;

  • Tri-State Transmission Map with GIR locations, and GIP Base

Cases available upon request, once NDA signed with Tri-State (and WECC).

slide-44
SLIDE 44

Major Changes in the GIP

44

Sec. Topic Interim LGIP (2/2009 – 7/2010) GIP (7/2010) 3.3, 3.4 IR Filing Deposits 3.3 - $125k Dep (<75MW) $250k Dep (>75MW) (plus model data, 50% Site Control) 3.4 – (New) $25k Dep (<10MW) (New) $50k Dep (10 - 20MW) (New) $75k Dep (20 – 75MW) $250k Dep (>75MW) (plus model data, (new) 25% Site Control) 5.1 Study Deposits (add’l info.) IR filed before 2/2009 requires additional $$ required as needed to bring total dep to $125k. IR filed before 7/2010 (*8/2010) requires additional $$ required as needed to bring total dep to (new) $250k. 7.1.1 System Impact Study (SIS) Expedited study option for projects with LOI / PPA. Same

slide-45
SLIDE 45

45

Sec. Topic Interim LGIP (2/2009 – 7/2010) GIP (7/2010) 8.1 Facilities Study (FacS) – Items required from IC to begin study. For IR designated as a Network Resource (NR): a) Site Control - 50%. b) Ltr Of Intent / PPA for NR. For IR designated as an Energy Resource (ER): a) Site Control 50%. b) No LOI / PPA necessary. 180 days (6 months) allowed for signing FacSA and supplying documentation of Site Control and LOI / PPA. a) Site Control – 50%. b) (New) Dep or Ltr Of Credit for 25% of cost of Interconnection Facilities and Network Upgrades. c) (New) Either:

  • Designation as a NR or;
  • TSR with TSGT or;
  • A written statement

acknowledging IC’s acceptance of risk of TP system operating limits. (New) 18 months allowed for supplying evidence of site control and LOI / PPA, and (new) 25% of

  • Intercon. Facilities & Network

Upgrade costs, followed by signing GIR Facilities Study Agreement (FacSA).

Major Changes in the GIP

slide-46
SLIDE 46

46

Sec. Topic Interim LGIP (2/2009 – 7/2010) GIP (7/2010) 11.3 Gen. Intercon. Agreement (GIA) 11.3 – Once final LGIA tendered to IC, it must be signed and returned to TP (TSG&T) within 21 days, along with: a) Site Control 100%. b) Evidence of project milestones achieved, such as either:

  • Fuel supply contract (if

applicable);

  • Cooling water supply

contract (if applicable);

  • Contract signed for E&P
  • f major equipment /

construction of IC facilities;

  • Contract signed for air /

land / water use permit. 11.3 – Once final GIA tendered to IC, it must be signed and returned to TP (TSG&T) within 21 days, along with: a) Site Control 100%. b) (New) Deposit or LOC for balance of the 100% cost of Interconnection facilities and Network Upgrades as identified in the final FacS.

Major Changes in the GIP

slide-47
SLIDE 47

47

Generation Interconnection Requests (GIR) Queues & Applications

  • Total # of IRs in Queue as of 10/12/11: 21
  • (13 in CO, 3 in NM, 5 in WY, 0 in NB)
  • Total MW of IRs in Queue as of 10/12/11: 2,683 MW
  • (1,888 MW in CO, 145 MW in NM, 650 MW in WY, 0 MW in NB)
  • Last Semiannual GIR Application Window closed:
  • Aug. 31,

2011

  • Only 2 new GIRs received in each of the last 2 GIR Application

Windows;

  • Next semi-annual GIR Application Window opens: Jan. 1, 2012
slide-48
SLIDE 48

Questions?

48

slide-49
SLIDE 49

Ron Steinbach Senior Manager, Transmission, Contracts, Rates & Policy (303) 254-3355 rsteinbach@tristategt.org

slide-50
SLIDE 50

OATT Update

slide-51
SLIDE 51

Open Access Transmission Tariff

 In place since 2001  Formula Rate—updated annually  2011 Point-to-Point Rate:

 $3.48 per kW month

 Non-firm rates currently discounted up to 70%  WestConnect Pricing Experiment

 Non-pancaked hourly non-firm transmission

slide-52
SLIDE 52

Tri-State Open Access Transmission Tariff

 Tri-State is not FERC jurisdictional, but uses FERC pro

forma tariff model

 Reviewed annually and revised when needed  Formula Rate—updated annually  Non-firm rates currently discounted up to 70%  WestConnect Pricing Experiment

 Non-pancaked hourly non-firm transmission

slide-53
SLIDE 53

Recent Changes to OATT and GIP

 OATT

 Added Hourly Firm product  Eliminated deposit for sales of three months or less  Modified Billing procedures

 Default  Distribution of penalty revenue

 Updated Attachment C—ATC methodology  Updated Attachment L—Transmission Planning

 GIP

 Clarified method for reimbursement of network credits

when Tri-State is an Affected System

slide-54
SLIDE 54

Historical Transmission Usage (12 month average)

 Sum of Point-to-Point reservations and coincident

peak network load

 2007:

2,442 MW

 2008:

2,543 MW

 2009:

2,509 MW

 2010:

2,587 MW

 2011:

2,626 MW (through August)

 2011 System peak in August = 3,105 MW

54

slide-55
SLIDE 55

55

Rate Design

 Monthly Network Service Charge =

ATRR / 12 * Load Ratio Share Load Ratio Share = Customer 12 CP/Total 12 CP

 Point to Point Transmission Rate =

ATRR / Total Load

 On-Peak Non-Firm Point to Point Rate =

 Annual Transmission rate / 4160 hours

 Off-Peak Non-Firm Point-to-Point Rate 

Annual Transmission rate / 8760 hours

slide-56
SLIDE 56

56

2012 Transmission Rates

Annual Transmission Revenue Requirement $109,992,813 Point-to-Point Transmission Rates - $ / MW-Month $3,570.53 Schedule 1--Scheduling and Dispatch $ / MW-Month $328.99 Schedule 2--VAR Support $ / MW-Month $87.82

slide-57
SLIDE 57

OASIS Information

Go to: www.tristategt.org/Operations OATT Queues and Studies

Interconnection requests Transmission Service requests Study Reports

slide-58
SLIDE 58

Questions?

58

slide-59
SLIDE 59

For More Information

 www.tristategt.org/AboutUs/TransmissionPlanning

 Comment Form  Transmission Planning Documents  Presentation

 Email: TransmissionPlanning@tristategt.org