Transmission Developers Inc. update to Stony Point Residents - - PowerPoint PPT Presentation
Transmission Developers Inc. update to Stony Point Residents - - PowerPoint PPT Presentation
Transmission Developers Inc. update to Stony Point Residents regarding Champlain Hudson Power Express June 18, 2013 DRAFT Welcome Transmission Developers Inc. (TDI) welcomes the opportunity to update the community of Stony Point This
DRAFT
Welcome
- Transmission Developers Inc. (TDI) welcomes
the opportunity to update the community of Stony Point
- This meeting tonight is to continue the dialogue
2
- This meeting tonight is to continue the dialogue
- n the Champlain Hudson Power Express
(CHPE) project development
DRAFT
Project Overview
- In-development since 2008, proposed in-
service by Q4-2017
- 333-mile underground 1,000 MW High
Voltage Direct Current (HVDC) transmission line
- Once constructed, the project will:
- Deliver renewable hydro power to meet the
demands of a growing population and economy
- Create construction and permanent jobs
3
- Create construction and permanent jobs
- Fuel economic growth through lower consumer
costs estimated to be $650 million a year
- Diversify the fuel supply mix for power supply in
the state
- Alleviate existing constraints, enhance system
reliability and add Black Start capability for system emergencies
- Lower greenhouse gas emissions
- Privately financed ($2.2B) capital project
- Over $20 million a year in property taxes
with an estimated $800,000 per year for Rockland County
DRAFT
Significant Developments
Order Granting Certificate of Environmental Compatibility and Public Need
– Application filed March 2010 – Public Service Commission approved Article VII Certificate on April 18, 2013
4
– Broadly supported by Consumer Organizations, Environmental Organizations and State Agencies – The PSC is an independent body charged with determining the public need and environmental compatibility of power transmission projects of this kind
DRAFT
Significant Developments
Order Granting Certificate of Environmental Compatibility and Public Need States the New Power Line Would:
– Enhance fuel diversity – Help reduce strain on the gas transportation system – Provide significant environmental benefit
5
– Provide significant environmental benefit – Shield ratepayers from project construction and operation costs – Provide stronger transmission ties into New York City, one of the most congested load pockets in the nation – Be consistent with the State Energy Plan and PlaNYC
DRAFT
Significant Developments
- New York City “A Stronger more Resilient New York” –
June 11, 2013
– Comprehensive plan that contains actionable recommendations both for rebuilding the communities impacted by Hurricane Sandy and increasing the resilience of infrastructure and buildings citywide
6
buildings citywide – Strategy: Reconfigure utility networks to be redundant and resilient – The City actively supported the issuance of a State permit to construct and operate a 333-mile transmission line from Quebec that would allow for the importation of 1,000 MW of clean, low carbon Canadian hydropower directly to New York City
DRAFT
- The project will provide the background to the new
and reinforced grid in NYC
- Hardened infrastructure helps the State of New York
- Geographic and fuel diversity helps the entire State
Significant Developments Significant Developments
7
- Geographic and fuel diversity helps the entire State
through significant weather events
- The project will provide Blackstart capabilities for
southern New York
DRAFT
Significant Developments
- CHPE launched a contractor portal on its website
www.chpexpress.com to solicit input from local contractors to help build the project
- TDI and Hydro-Quebec signed a Joint Development
8
- TDI and Hydro-Quebec signed a Joint Development
Agreement to coordinate the projects on both sides of the border
- TDI engaged Rick Chase as Senior Public Affairs
Consultant
DRAFT
Going Forward
There is still a significant amount of work to complete this project including important upcoming public consultation
- Community outreach program
- Office Expansion
9
- Office Expansion
– Albany (2009) – New York City (2010) – Stony Point (Summer of 2013) – North Country (Fall of 2013)
- Public hearings
- EM&CP development
DRAFT
Schedule of Approvals
2010 2011 2012
Mar Aug Nov Jan July Aug July Feb
- Feb. 28,
2012 Filing Updated To Reflect Presidential Permit Application Filed Public Comment New York State Article VII Filing Jun NY State Issues Conditional Coastal Zone Consistency Ruling Under The Federal Coastal Zone Management Act New York State Completeness Determination Dec NYS Article VII Negotiated Settlement Discussions with Parties Begin Public Scoping Report Complete Feb
- Feb. 24, 2012
Joint Proposal of Settlement filed with NY State PSC Blackstone investment in TDI January 25, 2010 Mar Mar 30, 2012 DOE noticed Continued… Jan
10
2012 Application Updated To Reflect Joint Proposal To Reflect Conditions In CZMA Ruling Application Filed With DOE www.chpexpresseis.org Public Scoping Meetings Completed Comment Period Closed Dec Clean Water Act 404 Dredge And Fill/Rivers and Harbors Act, Section 10 Permit Applications Filed With Army Corps July Filing Updated To Reflect Conditions In CZMA Ruling Feb
- Feb. 28, 2012
Application Updated To Reflect Joint Proposal June New York State Issues Conditional Coastal Zone Consistency Ruling Under The Federal Coastal Zone Management Act Mar Consultation TDI DOE noticed planned reopening
- f scoping process
NY State Regulatory Process Presidential Permit Army Corps
- f Engineers
Permitting CZMA Consistency Determination
DRAFT
Schedule of Approvals
Dec Jun Apr ALJ Recommendation To PSC Apr PSC issues Article VII Certificate Dec Final EIS Issued 6 Public Hearings On Joint Proposal July
- Sept. 18, 2012
DOE Issues Sept DEIS released for PSC issues Water Quality Certificate Feb
2012 2013
DOE circulates DEIS for Internal Review Presidential Permit Sep Environmental Management & Construction Plan (EM&CP)
- Sept. – Nov.
development & review Dec July-Aug 60 Day Public Nov Dec
11
June 14, 2012 Comment period closed on scope of DEIS 404 Permit And Section 10 Permits Issued DEIS Review Complete Issued Apr DOE Issues Scoping Report released for public comment for Internal Review by Federal Agencies; including Secretaries
- f Defense and State
for PP concurrence Permit Issued
NY State Regulatory Process Presidential Permit Army Corps
- f Engineers
Permitting CZMA Consistency Determination
60 Day Public Comment & Public Meetings Dec Submission Deemed Complete July Least Environmentally Damaging Partible Alternative (LEDPA) added to DEIS May Public Comment July-Aug Preparation
- f the Public
Comment Response Document Oct Key design review with ACOE Feb
DRAFT
New York State Future Energy Need
The New York Energy Highway Blueprint provides a plan for carrying forward a dynamic public-private partnership that will rebuild and rejuvenate New York State’s electric power system and enable the State to meet the needs of a 21st century economy and society.
- Includes a wide range of measures to provide up to 3,200 megawatts (MW)
- f additional electric generation and transmission capacity and clean power
generation
12
- Most of State’s transmission lines are more than 50 years old and many need
to be replaced in the next ten years
- 67% of State’s generation is 30 years or older. Repowering or replacing older,
less efficient sources of electricity is necessary
- A rebounding economy could push the need for power beyond current
projections Source: www.nyenergyhighway.com
DRAFT
Federal Permitting Process
United States Department of Energy - Case No. PP-362
The United States Department of Energy (DOE) is preparing an environmental impact statement (EIS) to evaluate potential environmental impacts associated with the proposed Champlain Hudson Power Express (CHPE) transmission line between the U.S. and Canada.
13
between the U.S. and Canada. Public comment can be submitted to the DOE at: http://www.chpexpresseis.org/public-involvement.php www.energy.gov
DRAFT
Additional Information
Transmission Developers Inc. Pieter Schuyler Building 600 Broadway
14