transformation programme
play

Transformation Programme Health Board Chief Executives April 2018 - PowerPoint PPT Presentation

B/18/53 CHI & Child Health Transformation Programme Health Board Chief Executives April 2018 Full Business Case Issues with Legacy Systems Inflexibility: 30 35 year old legacy CHI and GPPRS and Child Health systems are poor at


  1. B/18/53 CHI & Child Health Transformation Programme Health Board Chief Executives April 2018

  2. Full Business Case Issues with Legacy Systems • Inflexibility: 30 – 35 year old legacy CHI and GPPRS and Child Health systems are poor at supporting changing business priorities and at meeting new requirements. Cannot support Health and Social Care Integration. • Poor Architecture: CHI processes are batch based and compete for a very limited batch window. Both CHI and Child Health have poor data quality. Legacy Technology: hosted on the Fujitsu VME, old mainframe technology and expensive to maintain. Cannot support access control, audit, legitimate relationships. • See Page 6 of FBC Executive Summary

  3. Full Business Case New Systems Support and Enable Strategies • Digital Health and Social Care Strategy • eHealth Strategy – Declared legacy systems obsolete in 2014 • Children and Young People Strategies • Vaccination Transformation Programme • See Page 10 of FBC Executive Summary

  4. Programme Progress • Tranche 1: December 2014 – February 2017 Procurement – CHI and GPPRS – Wipro – SCPHWS - Servelec • Tranche 2: February 2017 – 28 March 2018 Due Diligence, Proof of Concept and Full Business Case – Programme Board approved the FBC on 28 March (subject to funding). – FBC is now with SG for decision. – If approved the Programme Team will work with Health Board Lead Officers and suppliers to complete the implementation plan. • Tranches 3 and 4: Implementation (Partially funded with additional funding requested) • Tranches 5: Transformation (No funding requested as yet)

  5. Tranches 3, 4 and 5 • Many Benefits delivered within Tranches 3 & 4 whilst Tranche 5 is transformational. • Tranches 3 & 4 Benefits ( Examples ): – Flexible modern solutions and increased automation – Single CHI record as source of the truth – Access control, legitimate relationships, improved security – One database across all Health Boards – Increased efficiency and fewer operators • Tranche 5 Benefits ( Examples ): – Real Time messaging instead of daily broadcasts – Introduction of the Record Locator Service (RLS) – Full audit capability on all transactions – Mobile working for Child Health – Integration with other national indices - English Patient Demographic Service (PDS), Welsh Demographic Service

  6. Funding and Costs Position Funding 10 Year Total (£) eHealth Leads Reinvestment Fund 15.060 eHealth Leads/ SG Requested for past funding 7.410 ( * assuming that it will be approved) Additional Funding SG eHealth (total agreed to SG 12.206 eHealth Leads Feb 2017 letter to NSS £12.206m) Total 34.676 Funding Released after Switchover to New Systems Old CHI & Child Health System Savings 27.623 Total 62.30 Cost 10 Year Total Costs to Implement and operate new solutions 67.74 Funding shortfall over 10 years is £67.74 – 62.30 = 5.44 million (£3 million contingency is also being sought)

  7. Legal Position Terminate after Tranche 2 • There is a specific right for NSS to terminate before issue of the Implementation Start Notice, subject to payment of the PoC and DD charges. • The contracts are in NSS’s favour proceeding to Implementation - there was no guarantee that the project would proceed to full implementation and roll out. • However, a case for compensation beyond the sums agreed for the PoC and DD charges is open to question, there may be advantages in reaching some sort of accommodation with a contractor with regard to reputational damage, avoid a formal legal dispute.

  8. Implementation Who Does What? Health Board Local Programme Implementation Groups (LIGs)

  9. Health Board Activities & Costs • Health Board Local Implementation activities, including local testing or activities needed to implement new working practices, are the responsibility of the respective NHS Health Boards. • As with the procurement, the programme funding does not cover payment to Health Boards to pay for Subject Matter Experts who support the Programme team – for example to support configuration decision making, or to carry out National User Acceptance Testing. • GGC worked with the programme team to estimate some Health Board Activities and costs which can be extrapolated for other Boards. Activity Cost (£) Child Health Testing 17,000 Child Health Migration 46,000 New CHI Testing(pre go live) 18,000 CHI Migration 11,000 Total 92,000

  10. Commission • Scottish Government (as primary funders of this Programme) will commission a Board / multiple Boards / a consortia to lead on the implementation phase … • Key content of commissions – Introduction / Background – driven by FBC – Commissioned Organisation or Consortia – decision required … – Scope / Objectives / Deliverables – driven by FBC – Governance Arrangements – decision required … – Conditions, Constraints and Limits – decision required … • Response from Commissioned organisation – Recommendations / Risks / Assumptions – decision required … – Projected Costs – See FBC – Programme Plan / Timeline – See FBC – Confirmation of Acceptance through own Governance – when ready

  11. Implementation Risk Factors • Large Scale • Multiple sub-projects • New technologies (systems and platforms / infrastructure) • Scope certainty / knowledge of existing systems • Mission critical systems / high cost of failure • Multi-supplier / overall design risk sits with client • High levels of dependency – supplier and client side • Dual running of environments / high cutover costs • High level of local collaboration / activity required

  12. Mitigating the Risks - 1 • OWNERSHIP – Commissioned organisation – Joint ownership (NSS + territorial Board) ? – Board Chief Executive involvement / engagement / SRO ? – Scottish Government directorate involvement • MULTIPLE SUPPLIERS – How to best manage – Retain strong procurement / commercial / legal help – Ensure implementation phase CCNs are watertight – Create supplier sub-group within Programme Governance – Integrated plan with formal acceptance of all parties • COLLABORATION WITHIN NHSS – How to assure – Formal commitments through each Board Chief Executive – High visibility through Health Board governance structures – Board Lead Officers represented on governance groups

  13. Mitigating the Risks - 2 • COST CONTROL – Risk mitigation – Clear delineation of programme costs ownership – Strong programme level financial tracking regime – Contingency arrangements/limits – Strong supplier contract management/billing oversight – Risk sharing across NHSS ? • QUALITY ASSURANCE – Oversight / Control – Continued high level of project/programme board scrutiny – External QA/Board assurance on regular basis – Adherence to MSP/PRINCE 2 methodology – Resilience/sustainability of team addressed/assured • OTHER KEY ISSUES FROM CHIEF EXECUTIVES?

  14. Major Decisions Required - 1 • SG Oversight / Commissioning Directorate – SG eHealth department lead / GG ? • Joint Ownership Model – NSS (holds contracts) + AN Other ? • Governance Structure – As per current structure + linkage with CE Group ? – New SG Digital governance link tbd • Chief Executives involvement / engagement – Programme Board membership / leadership ? – Regular Review / Major Decision consultation ?

  15. Major Decisions Required - 2 • Supplier Management Group – NSS, Servelec, Wipro, Atos, Health Board linkage ? • Resource Commitment / Risk Sharing – Chief Exec letter / MOU / written commitment ? – SG role / underwriting of risk ? • External Assurance – Programme Delivery - Ongoing / Gateway / Internal Audit ? – Clinical Assurance arrangements tbd ? • Conditions, Constraints & Limits – Tolerances and Contingencies / Escalation routes ? – External dependencies ?

  16. Approval / Timeline • FBC / Commission Consultation / Approval / Governance – CHI / CHS Programme Board (FBC approval complete) – SG Funding & Sponsoring Directorates / DoF – eHealth Leads Group – SG Digital Assurance Board / Delivery Board – Chief Executives Group – Commissioned Health Boards Governance Groups – Local Health Boards Governance Groups • Timeline for Commission – Discussion with Programme Board: December 15 – Review with SG eHealth: January 12 – Discussion with Chief Executives: January 16 – Draft in correspondence for Programme Board: January 26 – FBC: February 23rd – Back to Chief Executives Now

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend