Transformation Programme Health Board Chief Executives April 2018 - - PowerPoint PPT Presentation

transformation programme
SMART_READER_LITE
LIVE PREVIEW

Transformation Programme Health Board Chief Executives April 2018 - - PowerPoint PPT Presentation

B/18/53 CHI & Child Health Transformation Programme Health Board Chief Executives April 2018 Full Business Case Issues with Legacy Systems Inflexibility: 30 35 year old legacy CHI and GPPRS and Child Health systems are poor at


slide-1
SLIDE 1

CHI & Child Health Transformation Programme

Health Board Chief Executives

April 2018

B/18/53

slide-2
SLIDE 2

Full Business Case

Issues with Legacy Systems

  • Inflexibility: 30 – 35 year old legacy CHI and GPPRS and

Child Health systems are poor at supporting changing business priorities and at meeting new requirements. Cannot support Health and Social Care Integration.

  • Poor Architecture: CHI processes are batch based and

compete for a very limited batch window. Both CHI and Child Health have poor data quality. Legacy Technology: hosted on the Fujitsu VME, old mainframe technology and expensive to maintain. Cannot support access control, audit, legitimate relationships.

  • See Page 6 of FBC Executive Summary
slide-3
SLIDE 3
  • Digital Health and Social Care Strategy
  • eHealth Strategy

– Declared legacy systems obsolete in 2014

  • Children and Young People Strategies
  • Vaccination Transformation Programme
  • See Page 10 of FBC Executive Summary

Full Business Case

New Systems Support and Enable Strategies

slide-4
SLIDE 4

Programme Progress

  • Tranche 1: December 2014 – February 2017 Procurement

– CHI and GPPRS – Wipro – SCPHWS - Servelec

  • Tranche 2: February 2017 – 28 March 2018 Due Diligence, Proof of

Concept and Full Business Case – Programme Board approved the FBC on 28 March (subject to funding). – FBC is now with SG for decision. – If approved the Programme Team will work with Health Board Lead Officers and suppliers to complete the implementation plan.

  • Tranches 3 and 4: Implementation (Partially funded with additional

funding requested)

  • Tranches 5: Transformation (No funding requested as yet)
slide-5
SLIDE 5

Tranches 3, 4 and 5

  • Many Benefits delivered within Tranches 3 & 4 whilst

Tranche 5 is transformational.

  • Tranches 3 & 4 Benefits (Examples):

– Flexible modern solutions and increased automation – Single CHI record as source of the truth – Access control, legitimate relationships, improved security – One database across all Health Boards – Increased efficiency and fewer operators

  • Tranche 5 Benefits (Examples):

– Real Time messaging instead of daily broadcasts – Introduction of the Record Locator Service (RLS) – Full audit capability on all transactions – Mobile working for Child Health – Integration with other national indices - English Patient Demographic Service (PDS), Welsh Demographic Service

slide-6
SLIDE 6

Funding and Costs Position

Funding 10 Year Total (£) eHealth Leads Reinvestment Fund 15.060 eHealth Leads/ SG Requested for past funding (*assuming that it will be approved) 7.410 Additional Funding SG eHealth (total agreed to SG eHealth Leads Feb 2017 letter to NSS £12.206m) 12.206 Total 34.676 Funding Released after Switchover to New Systems Old CHI & Child Health System Savings 27.623 Total 62.30 Cost 10 Year Total Costs to Implement and operate new solutions 67.74

Funding shortfall over 10 years is £67.74 – 62.30 = 5.44 million (£3 million contingency is also being sought)

slide-7
SLIDE 7

Legal Position Terminate after Tranche 2

  • There is a specific right for NSS to terminate before issue
  • f the Implementation Start Notice, subject to payment of

the PoC and DD charges.

  • The contracts are in NSS’s favour proceeding to

Implementation - there was no guarantee that the project would proceed to full implementation and roll out.

  • However, a case for compensation beyond the sums

agreed for the PoC and DD charges is open to question, there may be advantages in reaching some sort of accommodation with a contractor with regard to reputational damage, avoid a formal legal dispute.

slide-8
SLIDE 8

Implementation Who Does What?

Programme Health Board Local Implementation Groups (LIGs)

slide-9
SLIDE 9

Health Board Activities & Costs

  • Health Board Local Implementation activities, including local testing or

activities needed to implement new working practices, are the responsibility of the respective NHS Health Boards.

  • As with the procurement, the programme funding does not cover

payment to Health Boards to pay for Subject Matter Experts who support the Programme team – for example to support configuration decision making, or to carry out National User Acceptance Testing.

  • GGC worked with the programme team to estimate some Health

Board Activities and costs which can be extrapolated for other Boards.

Activity Cost (£) Child Health Testing 17,000 Child Health Migration 46,000 New CHI Testing(pre go live) 18,000 CHI Migration 11,000 Total 92,000

slide-10
SLIDE 10

Commission

  • Scottish Government (as primary funders of this Programme) will

commission a Board / multiple Boards / a consortia to lead on the implementation phase…

  • Key content of commissions

– Introduction / Background – driven by FBC – Commissioned Organisation or Consortia – decision required… – Scope / Objectives / Deliverables – driven by FBC – Governance Arrangements – decision required… – Conditions, Constraints and Limits – decision required…

  • Response from Commissioned organisation

– Recommendations / Risks / Assumptions – decision required… – Projected Costs – See FBC – Programme Plan / Timeline – See FBC – Confirmation of Acceptance through own Governance – when ready

slide-11
SLIDE 11

Implementation Risk Factors

  • Large Scale
  • Multiple sub-projects
  • New technologies (systems and platforms / infrastructure)
  • Scope certainty / knowledge of existing systems
  • Mission critical systems / high cost of failure
  • Multi-supplier / overall design risk sits with client
  • High levels of dependency – supplier and client side
  • Dual running of environments / high cutover costs
  • High level of local collaboration / activity required
slide-12
SLIDE 12

Mitigating the Risks - 1

  • OWNERSHIP – Commissioned organisation

– Joint ownership (NSS + territorial Board) ? – Board Chief Executive involvement / engagement / SRO ? – Scottish Government directorate involvement

  • MULTIPLE SUPPLIERS – How to best manage

– Retain strong procurement / commercial / legal help – Ensure implementation phase CCNs are watertight – Create supplier sub-group within Programme Governance – Integrated plan with formal acceptance of all parties

  • COLLABORATION WITHIN NHSS – How to assure

– Formal commitments through each Board Chief Executive – High visibility through Health Board governance structures – Board Lead Officers represented on governance groups

slide-13
SLIDE 13

Mitigating the Risks - 2

  • COST CONTROL – Risk mitigation

– Clear delineation of programme costs ownership – Strong programme level financial tracking regime – Contingency arrangements/limits – Strong supplier contract management/billing oversight – Risk sharing across NHSS ?

  • QUALITY ASSURANCE – Oversight / Control

– Continued high level of project/programme board scrutiny – External QA/Board assurance on regular basis – Adherence to MSP/PRINCE 2 methodology – Resilience/sustainability of team addressed/assured

  • OTHER KEY ISSUES FROM CHIEF EXECUTIVES?
slide-14
SLIDE 14

Major Decisions Required - 1

  • SG Oversight / Commissioning Directorate

– SG eHealth department lead / GG ?

  • Joint Ownership Model

– NSS (holds contracts) + AN Other ?

  • Governance Structure

– As per current structure + linkage with CE Group ? – New SG Digital governance link tbd

  • Chief Executives involvement / engagement

– Programme Board membership / leadership ? – Regular Review / Major Decision consultation ?

slide-15
SLIDE 15

Major Decisions Required - 2

  • Supplier Management Group

– NSS, Servelec, Wipro, Atos, Health Board linkage ?

  • Resource Commitment / Risk Sharing

– Chief Exec letter / MOU / written commitment ? – SG role / underwriting of risk ?

  • External Assurance

– Programme Delivery - Ongoing / Gateway / Internal Audit ? – Clinical Assurance arrangements tbd ?

  • Conditions, Constraints & Limits

– Tolerances and Contingencies / Escalation routes ? – External dependencies ?

slide-16
SLIDE 16

Approval / Timeline

  • FBC / Commission Consultation / Approval / Governance

– CHI / CHS Programme Board (FBC approval complete) – SG Funding & Sponsoring Directorates / DoF – eHealth Leads Group – SG Digital Assurance Board / Delivery Board – Chief Executives Group – Commissioned Health Boards Governance Groups – Local Health Boards Governance Groups

  • Timeline for Commission

– Discussion with Programme Board: December 15 – Review with SG eHealth: January 12 – Discussion with Chief Executives: January 16 – Draft in correspondence for Programme Board: January 26 – FBC: February 23rd – Back to Chief Executives Now