to the year 2019 and for the planned activities for 2020 Helcom - - PowerPoint PPT Presentation

to the year 2019 and for the
SMART_READER_LITE
LIVE PREVIEW

to the year 2019 and for the planned activities for 2020 Helcom - - PowerPoint PPT Presentation

Finnish Contribution to the Subject Wreck Introduction to the year 2019 and for the planned activities for 2020 Helcom Submerged Correspondence Group 7 th -8 th January 2020 Kiel, Germany Jorma Rytknen Finnish Environment Institute


slide-1
SLIDE 1

Finnish Contribution to the Subject “Wreck” – Introduction to the year 2019 and for the planned activities for 2020

Helcom Submerged Correspondence Group 7th -8th January 2020 Kiel, Germany

Jorma Rytkönen Finnish Environment Institute (SYKE)

slide-2
SLIDE 2

Contents

  • Executive Summary – status quo
  • National wreck project
  • Year 2019 main phases
  • Integration to the Submerged time

line

  • Year 2020 planned activities
  • Chapter ”Wreck” plan
  • More information

2

Dredger VELI

slide-3
SLIDE 3

Project’s Status Quo

3

  • The governmental project to protect water environment

has been started officially 3/2019.

  • Sub project ”WRECKS” has a duration of 3…5 years, and

continues in 2020 - 2021.

  • Main results for this national wreck project in 2019

were:

  • - two separate wreck surveying missions by Turva – 9

wrecks studied;

  • - two missions onboard SYKE’s ARANDA – two new

wrecks were studied and 3d models performed;

  • - new R&D devices for ARANDA, bottom profilers, side

can sonar and multibeam sonar

  • - plans for 2020 done and in execution phase

ROV’s sonar over the Wieschaffen wreck

  • utside of RAUMA photo: J. Rytkönen
slide-4
SLIDE 4

WRECKS project – Oil Removal Operations – integration of governmental bodies and private sector

4

  • Project is an elementary part of the

governmental water protection programme for 2019 – 2023, and is linked to the Baltic Sea Action Plan.

  • Sub-project WRECKS is planned for

the years 2019 – 2021, if the Parliament will admitt the annual budget for the project execution.

  • Total budget is 4 M€ for the WRECKS
slide-5
SLIDE 5
  • National wreck project is run by SYKE, ander the coordination of the

Finnish Ministry of the Environment

  • Year 2019 main goal was to be prepared to the oil removal operations

and to define the status quo of the governmental and private sector ability for wreck salvage operations;

  • Nine wrecks were studied by The Finnish frontier Guard and SYKE –

two of those objects were deeper than 70 m.

  • Glider was used for underwater hydrocarbon level measurements;
  • ARANDA got new devices for wreck studies
  • Bucket Dredger VELI outside Hanko was emptied by a joint operation

by the Finnish Navy and SYKE

  • Two smaller coastal wreighters sunk in the Archipelago Sea were

studied and 3D modelled – preparations are under way for the oil removal operations in 2020.

5

Execution in 2019

slide-6
SLIDE 6
  • Responsible organisation,

SYKE – under the coordination of the Ministry

  • f the Environment
  • Finnish Navy,
  • Finnish Frontier Guard
  • Traficom (Finnish Transport

Safety Agency)

  • Maritime Museum
  • Private Sector, such as diving

companies, sub sea professionals etc…

6

National Wreck Project - Resources

Divers in the Archipelago Sea , November

  • 2019. Photo: H. Kankaanpää
slide-7
SLIDE 7
  • Governmental resources and facilities

have been identified, equipments tested and trainings performed

  • SYKE’s R&D vessel ARANDA is linked to

the subsea operations due to the new devices and the modern laboratory

  • nboard.
  • Various sub tasks have been

performed with the aid of the private sector.

7

Some phases in 2019

slide-8
SLIDE 8
  • Oil removal objects for 2020 have been selected
  • Additional operations will be performed (removal of two

paravans – for example)

  • 1-2- oil removal operations will be performed by divers
  • One object in deeper water will be given for private sector
  • Risk assessment under preparation
  • Tender processes will be started
  • Oil removal operation for 2021
  • Recommendations, sampling plans under writing process
  • Wreck seminar planned for August – September.

8

Status quo in the beginning of the 2020

slide-9
SLIDE 9
  • Participants: Torsten Frey, Uwe Wichert, Michał Czub, Jacek

Bełdowski, Claus Böttcher, Jann Wendt, Jens Sternheim, Benedykt Hac, Ewa Makowska, Jorma Rytkonen

9

Time line made in the Submerged meeting in Poland, 5.-6.6.2019

slide-10
SLIDE 10

Veli Dredger – 3D model

slide-11
SLIDE 11

11

slide-12
SLIDE 12

12

War ship Ilmarinen – studied in November – 80 – 100 tons of oil

  • nboard
slide-13
SLIDE 13

13

Anttila, M et al. Panssarilaiva Ilmarisen hylyn dokumentointi. Raportti Merivoimille. 2015

Artist drawing on the Ilmarinen – all fuel tanks both sides of the centre keel –douple bottom.

slide-14
SLIDE 14
slide-15
SLIDE 15

15

Fortuna is one of the wrecks selected for the oil removal operation in 2020

slide-16
SLIDE 16

16

M/s Hanna-Marjut – both she and Fortuna has around 10 m3 fuel oil in their fuel tanks

slide-17
SLIDE 17

17

slide-18
SLIDE 18

Chapter Wreck

18

  • Draft report ready for review of the

Submerged experts in coming weeks

  • Some new Russian Statistics will be

received after their New Year Holiday Season, and added to the text

  • No Statistics from Lihuania, Latvia.

German data need to be added; Mr Rytkönen has got unofficial data from Latvia and Lithuania and will visit both countries to check their validity for the report. Sediment samples taken in the Archipelago Sea - wreck Fortuna

slide-19
SLIDE 19

More Information:

jorma.rytkonen@ymparisto.fi

19