TITLE TEXT Long Range Planning and Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019 TITLE TEXT New Construction Updates Middle School/High School Projects o Schematic Designs Available for view in


slide-1
SLIDE 1

TITLE TEXT Long Range Planning and Construction Update

Presented By: Ed Holder and Scott Nielsen

February 12, 2019

slide-2
SLIDE 2

TITLE TEXT New Construction Updates

  • Middle School/High School Projects
  • Schematic Designs
  • Available for view in Johannsen Support Services Center

(JSSC) Lobby through February 15 and posted online

  • Shared with local municipal partners
  • Next steps

– Design continues to develop more detailed construction documents – We will update the Board and community with more detailed design documents later this spring

slide-3
SLIDE 3

TITLE TEXT New Construction Updates

  • Site Plan: Prospect Site
slide-4
SLIDE 4

TITLE TEXT New Construction Updates

  • Site Plan: Wellington Site
slide-5
SLIDE 5

TITLE TEXT New Construction Updates

  • Middle School/High School Floorplan
slide-6
SLIDE 6

TITLE TEXT New Construction Updates

  • Middle School/High School Projects
  • Athletics Complex at Prospect Site
  • Design for a 4,000 seat district stadium at Prospect

underway

  • Planning a 2,500 seat stadium at Wellington

– This will allow Wellington to host home games

  • Lighting at the Prospect and Wellington Sites
  • Athletics complex will be lit
  • Area at and around the school will also be lit
  • PSD will use directional lighting and LED technology
  • Closing on the Wellington Property: January 25,

2019

slide-7
SLIDE 7

TITLE TEXT New Construction Updates

  • Middle School/High School Projects
  • Construction Management General Contractor

(CMGC) to Manage Projects

  • Advantages include:

– Consistent management – Access to resources, including dedicated subcontractor pool – Potential for acceleration of completion timelines on new construction

  • Anticipated opening: Fall 2022
  • The Athletics Complex at the Prospect Site is anticipated to
  • pen in Fall 2021
slide-8
SLIDE 8

TITLE TEXT New Construction Updates

  • Zach Elementary School Addition
  • Schematic Design
  • Available for view in Johannsen Support Services Center

(JSSC) Lobby through February 15 and posted online

  • Construction of addition to replace existing

modulars will take place while school is in session

  • One modular will be removed before the 2019-2020 school

year

  • Two modulars will likely remain on site for the 2019-2020

school year, with at least one being removed for the 2020- 2021 year

slide-9
SLIDE 9

TITLE TEXT New Construction Updates

  • Zach Elementary School Addition
  • Construction Management General Contractor

(CMGC) for Project

  • Anticipated completion: late 2019
  • Design work: Fall 2018
  • Construction begins: Spring 2019
slide-10
SLIDE 10

TITLE TEXT New Construction Updates

  • Zach Elementary School Addition
slide-11
SLIDE 11

TITLE TEXT New Construction Updates

  • Southeast Elementary School
  • Infrastructure Projects Continue
  • HCM Selected as Architect and Approved by

Board of Education on January 22, 2019

  • Design is underway and will continue through

early 2020

  • Anticipated opening: Fall 2021
slide-12
SLIDE 12

TITLE TEXT Ongoing Facilities Update

  • $40 Million in Ongoing Facilities Improvements
  • Project List Finalized
  • Project Timelines and Budget Codes Underway
  • Purchasing for Furniture Proceeding
  • Shared with Office Managers and Principals on February 5
  • Projects administered by Operations will be

implemented over a three to four year period

slide-13
SLIDE 13

TITLE TEXT New Construction Updates

  • PSD Futures Lab
  • 2019-2020 Programming at Fort Collins High

School

  • Entrepreneurship
  • iOS App Development
  • Unmanned Aerial Systems (Drones)
  • AP Seminar
  • Anticipated Enrollment for 2019-2020: Up to 100

Students

  • Programming Slated to Expand in 2020-2021
  • Continuing to Explore Permanent Facility Options
slide-14
SLIDE 14

TITLE TEXT Interim Growth Management

  • Modular Placements for 2019-2020:
  • Riffenburgh Elementary School
  • Possible Modular Placements for 2020-2021 Will

Continue to be Monitored

  • Longer Term Growth Management Options Under

Consideration

slide-15
SLIDE 15

TITLE TEXT Looking Ahead

  • Growth is anticipated to continue in the district
  • District leadership is meeting internally to discuss

potential long-term facility needs – the next long range plan

  • The next 2016 bond program update to the

Board is scheduled for April 2019