TII National Roads Conference 2019 Update to TII Cost Management Procedures 27/09/19 CHANGES TO COST MANAGEMENT MANUAL 1.ESTIMATING PROCESS 2.GENERAL UPDATE 3.REFERENCE CLASS FORECASTING ESTIMATING PROCESS CHANGES TO ESTIMATING PROCESS


slide-1
SLIDE 1

27/09/19

TII National Roads Conference 2019

Update to TII Cost Management Procedures

slide-2
SLIDE 2

CHANGES TO COST MANAGEMENT MANUAL 1.ESTIMATING PROCESS 2.GENERAL UPDATE 3.REFERENCE CLASS FORECASTING

slide-3
SLIDE 3

ESTIMATING PROCESS

slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

CHANGES TO ESTIMATING PROCESS 1.ESTIMATE SUMMARY BACKUP SHEET 2.ESTIMATE PREPARATION CHECKLIST 3.BACKUP TRACKER SHEET 4.ESTIMATE TRACKER SHEET

slide-7
SLIDE 7
slide-8
SLIDE 8
slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14
slide-15
SLIDE 15

GENERAL UPDATE

  • 1. CHANGE CONTROL REVISIONS
  • MOVE TO THRESHOLD BASED SYSTEM
  • ACCOMPANYING TII SOFTWARE
  • 2. UPDATE FRAMEWORK MANAGEMENT SYSTEM
slide-16
SLIDE 16

27/09/19

TII National Roads Conference 2019

Update to TII Cost Management Procedures - Reference Class Forecasting

slide-17
SLIDE 17

Reference Class Forecasting – what is it?

  • Methodology for forecasting future overruns on projects using

data from previously completed projects

  • Builds on existing TII procedures for cost estimation
  • Removes ‘Optimism Bias’, uses outside view
  • Incorporates ‘unknown unknowns’
  • Does NOT replace the need for accurate and comprehensive base cost

estimates

slide-18
SLIDE 18

Reference Class Forecasting – Why use it?

slide-19
SLIDE 19

Reference Class Forecasting – How does it work?

slide-20
SLIDE 20

Reference Class Forecasting – How does it work?

slide-21
SLIDE 21

How is RCF applied to TII Projects?

Base Cost Estimate QRA Target Cost (a) RCF Target Cost (b) Expert Judgement Target Cost

slide-22
SLIDE 22
  • Reference Class of over

120 National Road projects identified

  • Cost & Schedule data

gathered at pre CPO (TC1), Pre Tender (TC2), pre Award (TC3) and Outturn

  • Initial Analysis

complete

Work Done to Date

slide-23
SLIDE 23
  • Reference Class of over

120 National Road projects identified

  • Cost & Schedule data

gathered at pre CPO (TC1), Pre Tender (TC2), pre Award (TC3) and Outturn

  • Initial Analysis

complete

Work Done to Date

slide-24
SLIDE 24
  • Reference Class Charts to be

finalised

  • Reference Class Forecasting

Publication to be finalised and published

  • Cost Management Manual

update including Reference Class Forecasting to be published

Future Work