This presentation is for a project on US 12 in the St. Croix County - PowerPoint PPT Presentation

This presentation is for a project on US 12 in the St. Croix County towns of Hudson and Warren. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current


  1. This presentation is for a project on US 12 in the St. Croix County towns of Hudson and Warren. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current health information from state, federal and local health departments. All meeting materials, including the handout with a comment form, are posted on the design website for this project. https://wisconsindot.gov/Pages/projects/by-region/nw/us12scc/default.aspx If you have any questions, please contact WisDOT Project Supervisor, James Koenig at (715) 838-8391.

  2. Public Involvement Meeting US 12 Towns of Hudson and Warren County U to West Junction WIS 65 St. Croix County

  3. Project Team • James Koenig • WisDOT Project Supervisor • Brett Hollister • WisDOT Consultant Project Manager • Ashley Seibel • WisDOT Consultant Real Estate Specialist

  4. Presentation Agenda • Project Location • Project Purpose and Need • Proposed Improvements • Construction Staging • Real Estate • Project Schedule • Contact Information

  5. Project Location

  6. Purpose and Need • Purpose  Rehabilitate the US 12 driving surface and drainage structures • Need  Deteriorated pavement  Deteriorated drainage structures  Deteriorated beam guard  Narrow paved shoulder

  7. Proposed Improvements • Resurface US 12 with asphalt pavement • Remove or replace beam guard • Widen the paved shoulder • Replace and clean out culverts • Install centerline and shoulder rumble strips • Replace concrete approaches and add flumes at the bridge structure over the railroad tracks • Replace pavement marking

  8. Proposed Construction Staging • 2021 construction season (June-October) • US 12 closed to through traffic • Detour route: US 12 to I-94 to WIS 65 • US 12 will be open to residences and businesses located within the project limits • Temporary driveway closure will be coordinated with property owners

  9. Detour Route

  10. Real Estate • Real estate acquisition for US 12 improvements • Strip takings, both permanent and temporary • Real estate acquisition process • Contact: Ashley Seibel, (715) 830-0544, ext. 205, or ashley@rowpros.org

  11. Real Estate

  12. Project Schedule • Environmental Document July 2019 • Preliminary Plans September 2019 • Real Estate Plat June 2020 • Public Involvement Virtual Presentation August 2020 • Final Plans November 2020 • Construction Summer 2021

  13. What we need from you Share your concerns or comments https://wisconsindot.gov/Pages/projects/by-region/nw/us12scc/default.aspx Responses returned by Aug. 21, 2020 • By email: HollisterB@AyresAssocites.com • By mail: o James Koenig Wisconsin Department of Transportation 718 W. Clairemont Ave. Eau Claire, WI 54701 Thank you for your time

  14. Project Team • James Koenig • WisDOT Project Supervisor • (715) 838-8391 • james.koenig@dot.wi.gov • Brett Hollister • WisDOT Consultant Project Manager • (715) 831-7545 • HollisterB@AyresAssociates.com • Ashley Siebel • WisDOT Consultant Real Estate Specialist • (715) 830-0544 ext. 205 • ashley@rowpros.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.