The Phase One I - 710 Freeway Rehabilitation Project: I nitial - - PowerPoint PPT Presentation
The Phase One I - 710 Freeway Rehabilitation Project: I nitial - - PowerPoint PPT Presentation
The Phase One I - 710 Freeway Rehabilitation Project: I nitial Design to Perf ormance Af ter Six Years of Traf f ic Meeting with AAPA Study Tour Group UCPRC, CA 8/ 10/ 2010 Richmond Field Station, UC Berkeley I - 710 Project - Partnered
I - 710 Project - Partnered Ef f ort (most recent participants)
- Caltrans
§T. Bressette, W. Farnbach, C. Suszko
- I ndustry
§J. St. Martin,
- University of Calif ornia PRC
§C. Monismith
I - 710 Project - Partnered Ef f ort (some earlier participants)
- Caltrans
§K. Herritt, R. Doty, J. Dobrowolski,
- S. Shatnawi
- I ndustry
§L. Nawrocki, J. Copley, R. Smith,
- D. Chapman
- University
§J. Harvey, F. Long
Presentation
- Mix designs
- Structural section designs
§f ull- depth AC §overlay on cracked and seated PCC
- Aspects of construction
- Some lessons learned
- Phase I I structures
I-710 March 2003
Rehabilitation of I nterstate - 710
- Full- Depth Asphalt Concrete
§replacement under overpasses
- Overlay of PCC (cracked-
seated)
Design & Analysis
Trial cross section
Perf ormance Tests
Trial mix design Conditioning
(Aging & Water)
Analysis Perf ormance Prediction
Final mix design & structural section
Unacceptable Acceptable
Long- Lif e Asphalt Pavement
- QC/ QA specif ications
- Polymer modif ied binders
- I mproved aggregate
requirements
- Modif ied mix design method
Trial Mix Design
- San Gabriel aggregate
- Binders
§Conventional: AR- 8000 §Polymer modif ied: PBA- 6a*
- Hveem Stabilometer- to establish
range of binder contents
Trial Mix Design
- Range of binder contents
§ 4. 2 - 5. 7% (by wt of aggregate)
- Conventional dense- graded
mix, Caltrans specs.
- All crushed materials
Final Mix Design - Rutting
Nsupply = M x Ndemand
No
I nput Ndemand Traf f ic Nsupply Perf ormance test
Yes
≥
Shear Test
Ndemand - (PBA- 6A)
- Design ESALs - f irst f ive years
§30 x 106 ESALs
- Ndemand = 660, 000
M x Design ESALs x TCF x SF §M = 5
§TCF = 0. 116 §SF = 0. 04
Design Binder Content
1,000 10,000 100,000 1,000,000 10,000,000 3 3.5 4 4.5 5 5.5 6
Asphalt content (percent by weight of aggregate) N @γp = 5 %
PBA 6A AR 8000 Temperature = 50 C 660,000 repetitions 146,000 repetitions
HVS Rutting Study
Rutting Study Layout
25 m section 33 tonnes AC
Placed on jointed PCC 3 m 4 m 150 mm
K- barrier on
- ne side of
section
Mix Perf ormance Evaluation
5 10 15 20 25 30
- 50,000
100,000 150,000 200,000 HVS Load Applications Rut Depth, mm 38-mm ARHM-GG 62-mm ARHM-GG 75-mm DGAC AR-4000 76-mm PBA-6A
½ inch rut depth
< 20,000 reps ~ 170,000 reps
Thickness Design - Fatigue Analysis
Nsupply M x Ndemand
No
I nput Ndemand Traf f ic Nsupply Perf ormance test
Yes ≥
Design Considerations
- Fatigue in asphalt concrete
- Def ormation in unbound layers
- Subsequently, design checked
by CalME
Design Considerations
Asphalt Concrete Base Subgrade
εt εv
I nput
- Structural section (f ull- depth)
- Traf f ic (200 million ESALs)
- Environment (T = 20° C)
- Trial mixes & pavement
section
I nput
- Reliability (M=5)
- f (traf f ic estimate & testing
variability)
- Perf ormance criterion
§wheel path cracking ≤ 10%
Trial Pavement Sections
AR- 8000
PBA- 6A*
AR- 8000
(rich bottom)
subgrade
Fatigue
Fatigue Test Results
1.E+03 1.E+04 1.E+05 1.E+06 1.E+07 1.E+08 1.00E-04 1.00E-03
Mean Strain
Nf
AR-8000, 4.7% AC, 6% AV AR-8000, 5.2% AC, 3% AV PBA-6A, 4.7% AC, 6% AV PBA-6A, 5.2% AC, 3% AV
Nsupply ≥ M × Ndemand?
Fatigue Che heck vert i t ical subgrade st ra rain ! ! ! ! ! !
(co cont r t rolle lled t o t ot a t al l t hi t hick ckness)
Final Design
AR-8000 (4.7%) PBA-6A (4.7%) AR-8000 (5.2%)
(rich bottom)
subgrade AR-OGFC
25 mm 75 150 75
6% air voids 6% 3%
Overlays
Jointed PCC Cement treated Base Subgrade Asphalt Concrete Fabric Leveling Course 150 – 250 mm 200 mm 150 mm 30 mm
Calculated Conf iguration
Traf f ic loads applied statically symmetrical boundaries
p =725 kPa 250 mm
Cracks @ 1 m
AC
Finite Element Mesh
~ 12,000 elements, NIKE2D
Bending Strains in Mix just above Fabric
- 120
- 80
- 40
40 80 120 160
- 4
- 2
2 4 6 DISTANCE FROM CENTER (ft) BENDING STRAIN (us)
5"@900, 4"@150 ksi 3"@900, 5"@150 ksi 3"@900, 3"@150 ksi
Composite Overlay
Final overlay thickness
25 mm OGFC
Fabric
225 mm 75 mm PBA-6A 125 mm AR-8000
Broken and seated PCC
Full- Depth AC Comparisons
- The Asphalt I nstitute
- United Kingdom
- Australia
- Asphalt Pavement Alliance- U. S.
Perpetual Pavement Design Concepts
Max Tensile Strain
Pavem ent Foundation
High Modulus Rut Resistant Material 4.5 - 6”
Flexible Fatigue Resistant Material 3 - 4” 1.5 - 3” SMA, OGFC or Superpave
}
4” to 6”
Zone Of High Compression
Construction Specif ications
- Perf ormance requirements
based on shear and f atigue testing
- More stringent compaction
requirements
- Tack coat between layers
§Asphalt cement (AR- 4000)
Construction
- Six stages
- Stages 1 and 2 preliminary to
- rehab. of traf f icked sections
- Stages 3- 6 - rehab. of traf f icked
sections in 8 - 55 hr. weekend closures (vs. 10 originally planned)
- Use of CA4PRS (construction
management program)
Construction
- Stages 3 - 6
§Traf f ic closure §Crack, seat, and overlay (CSOL) §Full depth AC construction (FDAC) §Traf f ic opening
Contractor Staging Plan
Crack, Seat, and Overlay (CSOL) = 2.8 centerline
- km
Full
- Depth AC Replacement (FDAC) = 1.6 centerline
- km
Stage 4A (2
nd
)
N N
Stage 3A (1
st
) Stage 4B and 4C (3
rd and 4 th
) Stage 6A (8
th
) Stage 5A and 5B (5
th and 6 th
)
FDAC: 362m CSOL: 1,259m FDAC: 406m CSOL: 1,035m FDAC: 840m CSOL: 480m FDAC: 342m CSOL: 760m FDAC: 321m CSOL: 959m FDAC: 840m CSOL: 1,160m
Stage 5C (7
th
) Crack, Seat, and Overlay (CSOL) = 2.8 centerline
- km
Full
- Depth AC Replacement (FDAC) = 1.6 centerline
- km
Stage 4A (2
nd
)
N N N
Stage 3A (1
st
) Stage 4B and 4C (3
rd and 4 th
) Stage 6A (8
th
) Stage 5A and 5B (5
th and 6 th
)
FDAC: 362m CSOL: 1,259m FDAC: 406m CSOL: 1,035m FDAC: 840m CSOL: 480m FDAC: 342m CSOL: 760m FDAC: 321m CSOL: 959m FDAC: 840m CSOL: 1,160m
Stage 5C (7
th
)
N
Placement of Leveling Course
I nst allat ion of Pavement Fabric
Placement of PBA- 6A* Mix
Digout and Placement of Aggregate Base – Working Platf orm
Rich Bottom Layer Construction
Monday, March 3 0 , 2 0 0 3 0 5 :0 0 am
Some Lessons Learned
- Pre- bid conf erence mandatory
f or all potential bidders
- For projects of this importance
a “partnering” meeting at the
- utset is mandatory
§ Partnering on the technical aspects extremely important!
Some Lessons Learned (cont. )
- For new test procedures
included in Special Provisions insure that all involved groups perf orm tests and analyze resulting data the same way:
§ equipment calibration essential § preliminary testing of comparable specimens
Some Lessons Learned (cont. )
- I mproved specif ication
requirements based on statistical considerations desirable
- For QC/ QA activities adequate
staf f ing imperative (large quantities of materials, up to 15, 000 tonnes per weekend)
Some Lessons Learned (cont. )
- Timely QA results required
- Human resources – 3 to 5
weekend closures in a row maximum; if more required, allow 1 to 2 weekend interval
Some Lessons Learned (cont. )
- I n digout areas (FDAC) :
§Exploratory testing imperative §Exact location of underground utilities
Some Lessons Learned (cont. )
- Contingency plan important
§Digout areas - working platf orm; materials easily accessible §Standby HMA plant(s)
- Meteorologist f or contractor
(construction in digout areas)
Perf ormance Evaluation
- FWD Def lection testing (2003 through
2008)
- Back calculation of layer moduli and
strains in HMA layers using MLEA
- Condition surveys
- Longitudinal and transverse prof ile
measurements
- Noise measurements
- Laboratory testing of cores (RSST- CH)
and slabs (Fatigue)
Perf ormance Evaluation
- Non- destructive HWD tests
§11/ 03, NB and SB §9/ 04, NB; 2/ 5, SB §12/ 05, NB; 2/ 06, SB
CENTER DEFLECTIONS LANE 3 I-710 SOUTHBOUND (ADJUSTED TO 19C)
100 200 300 400 500 600 700 800 50 100 150 200 250 300 350 LOCATION DEFLECTION (MICRONS) 2003 2004 2005 2008 Section 1(FD) Section 2(CSOL) Section 3(FD) Section 4(CSOL) Section 5(FD) PCH 405
Deflections – SB Lane 3
X 03 03 05 08
CENTER DEFLECTIONS LANE 3 I-710 NORTHBOUND (ADJUSTED TO 19C)
100 200 300 400 500 600 700 800 900 1000 50 100 150 200 250 LOCATION DEFLECTION (MICRONS) 2003 2004 2006 2008 Section 1(FD) Section 2(CSOL) Section 3(FD) Section 4(CSOL) Section 5(FD) PCH 405
Deflections – NB Lane 3
X 03 03 05 08
I-710 Northbound Lane 3 Full Depth Sections - Layer Moduli with Time
3,000 6,000 9,000 12,000 15,000 2002 2003 2004 2005 2006 2007 2008 2009
Year Tested
Modulus (MPa)
Section 1 AC Section 3 AC Section 5 AC Section 1 Base Section 3 Base Section 5 Base
NB Lane 3 – Layer Moduli
Tensile Strain, Underside HMA Layer, in/ in x 10- 6
Section NB SB 1 18 49 3 17 18 5 16 8.5
Rut Depth Measurements
SB Lane 3
3 6 9 12 15
0+00 5+00 10+00 15+00 20+00 25+00 30+00 35+00 40+00 45+00
Station (m) Rutting (mm) Left WP Right WP
12.5 mm
Rut Depth Measurements
NB Lane 3
3 6 9 12 15
0+00 10+00 20+00 30+00 40+00
Station (m) R u t t i n g ( m m ) Left WP Right WP
12.5 mm
I - 710 Traf f ic
I - 710 Traf f ic
I - 710, Phase I I
- Modif ications
§Design traf f ic: - 330x106 ESALs §Thickness of HMA base layer [PG 70- 10 (AR- 8000)] increased §Surf ace course: RAC- G instead
- f RAC- O
Concluding Thoughts
- I mplementation of New Technology f or Mix &
Structural Design
- Strict Attention To Pavement Construction
- Constructability Considerations -
Use of CA4PRS
- Successf ul partnering – agency, contractor and
academia.
- Paving perf orming as expected.
Summary
- I mplementation of SHRP
developed technology
- Strict attention to pavement
construction
- Constructability considerations;