The Phase One I - 710 Freeway Rehabilitation Project: I nitial - - PowerPoint PPT Presentation

the phase one i 710 freeway rehabilitation project i
SMART_READER_LITE
LIVE PREVIEW

The Phase One I - 710 Freeway Rehabilitation Project: I nitial - - PowerPoint PPT Presentation

The Phase One I - 710 Freeway Rehabilitation Project: I nitial Design to Perf ormance Af ter Six Years of Traf f ic Meeting with AAPA Study Tour Group UCPRC, CA 8/ 10/ 2010 Richmond Field Station, UC Berkeley I - 710 Project - Partnered


slide-1
SLIDE 1

The Phase One I - 710 Freeway Rehabilitation Project: I nitial Design to Perf ormance Af ter Six Years of Traf f ic

Meeting with AAPA Study Tour Group UCPRC, CA 8/ 10/ 2010 Richmond Field Station, UC Berkeley

slide-2
SLIDE 2

I - 710 Project - Partnered Ef f ort (most recent participants)

  • Caltrans

§T. Bressette, W. Farnbach, C. Suszko

  • I ndustry

§J. St. Martin,

  • University of Calif ornia PRC

§C. Monismith

slide-3
SLIDE 3

I - 710 Project - Partnered Ef f ort (some earlier participants)

  • Caltrans

§K. Herritt, R. Doty, J. Dobrowolski,

  • S. Shatnawi
  • I ndustry

§L. Nawrocki, J. Copley, R. Smith,

  • D. Chapman
  • University

§J. Harvey, F. Long

slide-4
SLIDE 4

Presentation

  • Mix designs
  • Structural section designs

§f ull- depth AC §overlay on cracked and seated PCC

  • Aspects of construction
  • Some lessons learned
  • Phase I I structures
slide-5
SLIDE 5

I-710 March 2003

slide-6
SLIDE 6

Rehabilitation of I nterstate - 710

  • Full- Depth Asphalt Concrete

§replacement under overpasses

  • Overlay of PCC (cracked-

seated)

slide-7
SLIDE 7

Design & Analysis

Trial cross section

Perf ormance Tests

Trial mix design Conditioning

(Aging & Water)

Analysis Perf ormance Prediction

Final mix design & structural section

Unacceptable Acceptable

slide-8
SLIDE 8

Long- Lif e Asphalt Pavement

  • QC/ QA specif ications
  • Polymer modif ied binders
  • I mproved aggregate

requirements

  • Modif ied mix design method
slide-9
SLIDE 9

Trial Mix Design

  • San Gabriel aggregate
  • Binders

§Conventional: AR- 8000 §Polymer modif ied: PBA- 6a*

  • Hveem Stabilometer- to establish

range of binder contents

slide-10
SLIDE 10

Trial Mix Design

  • Range of binder contents

§ 4. 2 - 5. 7% (by wt of aggregate)

  • Conventional dense- graded

mix, Caltrans specs.

  • All crushed materials
slide-11
SLIDE 11

Final Mix Design - Rutting

Nsupply = M x Ndemand

No

I nput Ndemand Traf f ic Nsupply Perf ormance test

Yes

slide-12
SLIDE 12

Shear Test

slide-13
SLIDE 13

Ndemand - (PBA- 6A)

  • Design ESALs - f irst f ive years

§30 x 106 ESALs

  • Ndemand = 660, 000

M x Design ESALs x TCF x SF §M = 5

§TCF = 0. 116 §SF = 0. 04

slide-14
SLIDE 14

Design Binder Content

1,000 10,000 100,000 1,000,000 10,000,000 3 3.5 4 4.5 5 5.5 6

Asphalt content (percent by weight of aggregate) N @γp = 5 %

PBA 6A AR 8000 Temperature = 50 C 660,000 repetitions 146,000 repetitions

slide-15
SLIDE 15

HVS Rutting Study

slide-16
SLIDE 16

Rutting Study Layout

25 m section 33 tonnes AC

Placed on jointed PCC 3 m 4 m 150 mm

K- barrier on

  • ne side of

section

slide-17
SLIDE 17

Mix Perf ormance Evaluation

5 10 15 20 25 30

  • 50,000

100,000 150,000 200,000 HVS Load Applications Rut Depth, mm 38-mm ARHM-GG 62-mm ARHM-GG 75-mm DGAC AR-4000 76-mm PBA-6A

½ inch rut depth

< 20,000 reps ~ 170,000 reps

slide-18
SLIDE 18

Thickness Design - Fatigue Analysis

Nsupply M x Ndemand

No

I nput Ndemand Traf f ic Nsupply Perf ormance test

Yes ≥

slide-19
SLIDE 19

Design Considerations

  • Fatigue in asphalt concrete
  • Def ormation in unbound layers
  • Subsequently, design checked

by CalME

slide-20
SLIDE 20

Design Considerations

Asphalt Concrete Base Subgrade

εt εv

slide-21
SLIDE 21

I nput

  • Structural section (f ull- depth)
  • Traf f ic (200 million ESALs)
  • Environment (T = 20° C)
  • Trial mixes & pavement

section

slide-22
SLIDE 22

I nput

  • Reliability (M=5)
  • f (traf f ic estimate & testing

variability)

  • Perf ormance criterion

§wheel path cracking ≤ 10%

slide-23
SLIDE 23

Trial Pavement Sections

AR- 8000

PBA- 6A*

AR- 8000

(rich bottom)

subgrade

slide-24
SLIDE 24

Fatigue

slide-25
SLIDE 25

Fatigue Test Results

1.E+03 1.E+04 1.E+05 1.E+06 1.E+07 1.E+08 1.00E-04 1.00E-03

Mean Strain

Nf

AR-8000, 4.7% AC, 6% AV AR-8000, 5.2% AC, 3% AV PBA-6A, 4.7% AC, 6% AV PBA-6A, 5.2% AC, 3% AV

slide-26
SLIDE 26

Nsupply ≥ M × Ndemand?

Fatigue Che heck vert i t ical subgrade st ra rain ! ! ! ! ! !

(co cont r t rolle lled t o t ot a t al l t hi t hick ckness)

slide-27
SLIDE 27

Final Design

AR-8000 (4.7%) PBA-6A (4.7%) AR-8000 (5.2%)

(rich bottom)

subgrade AR-OGFC

25 mm 75 150 75

6% air voids 6% 3%

slide-28
SLIDE 28

Overlays

Jointed PCC Cement treated Base Subgrade Asphalt Concrete Fabric Leveling Course 150 – 250 mm 200 mm 150 mm 30 mm

slide-29
SLIDE 29

Calculated Conf iguration

Traf f ic loads applied statically symmetrical boundaries

p =725 kPa 250 mm

Cracks @ 1 m

AC

slide-30
SLIDE 30

Finite Element Mesh

~ 12,000 elements, NIKE2D

slide-31
SLIDE 31

Bending Strains in Mix just above Fabric

  • 120
  • 80
  • 40

40 80 120 160

  • 4
  • 2

2 4 6 DISTANCE FROM CENTER (ft) BENDING STRAIN (us)

5"@900, 4"@150 ksi 3"@900, 5"@150 ksi 3"@900, 3"@150 ksi

slide-32
SLIDE 32

Composite Overlay

Final overlay thickness

25 mm OGFC

Fabric

225 mm 75 mm PBA-6A 125 mm AR-8000

Broken and seated PCC

slide-33
SLIDE 33

Full- Depth AC Comparisons

  • The Asphalt I nstitute
  • United Kingdom
  • Australia
  • Asphalt Pavement Alliance- U. S.
slide-34
SLIDE 34

Perpetual Pavement Design Concepts

Max Tensile Strain

Pavem ent Foundation

High Modulus Rut Resistant Material 4.5 - 6”

Flexible Fatigue Resistant Material 3 - 4” 1.5 - 3” SMA, OGFC or Superpave

}

4” to 6”

Zone Of High Compression

slide-35
SLIDE 35

Construction Specif ications

  • Perf ormance requirements

based on shear and f atigue testing

  • More stringent compaction

requirements

  • Tack coat between layers

§Asphalt cement (AR- 4000)

slide-36
SLIDE 36

Construction

  • Six stages
  • Stages 1 and 2 preliminary to
  • rehab. of traf f icked sections
  • Stages 3- 6 - rehab. of traf f icked

sections in 8 - 55 hr. weekend closures (vs. 10 originally planned)

  • Use of CA4PRS (construction

management program)

slide-37
SLIDE 37

Construction

  • Stages 3 - 6

§Traf f ic closure §Crack, seat, and overlay (CSOL) §Full depth AC construction (FDAC) §Traf f ic opening

slide-38
SLIDE 38

Contractor Staging Plan

Crack, Seat, and Overlay (CSOL) = 2.8 centerline

  • km

Full

  • Depth AC Replacement (FDAC) = 1.6 centerline
  • km

Stage 4A (2

nd

)

N N

Stage 3A (1

st

) Stage 4B and 4C (3

rd and 4 th

) Stage 6A (8

th

) Stage 5A and 5B (5

th and 6 th

)

FDAC: 362m CSOL: 1,259m FDAC: 406m CSOL: 1,035m FDAC: 840m CSOL: 480m FDAC: 342m CSOL: 760m FDAC: 321m CSOL: 959m FDAC: 840m CSOL: 1,160m

Stage 5C (7

th

) Crack, Seat, and Overlay (CSOL) = 2.8 centerline

  • km

Full

  • Depth AC Replacement (FDAC) = 1.6 centerline
  • km

Stage 4A (2

nd

)

N N N

Stage 3A (1

st

) Stage 4B and 4C (3

rd and 4 th

) Stage 6A (8

th

) Stage 5A and 5B (5

th and 6 th

)

FDAC: 362m CSOL: 1,259m FDAC: 406m CSOL: 1,035m FDAC: 840m CSOL: 480m FDAC: 342m CSOL: 760m FDAC: 321m CSOL: 959m FDAC: 840m CSOL: 1,160m

Stage 5C (7

th

)

N

slide-39
SLIDE 39

Placement of Leveling Course

slide-40
SLIDE 40

I nst allat ion of Pavement Fabric

slide-41
SLIDE 41

Placement of PBA- 6A* Mix

slide-42
SLIDE 42
slide-43
SLIDE 43

Digout and Placement of Aggregate Base – Working Platf orm

slide-44
SLIDE 44
slide-45
SLIDE 45

Rich Bottom Layer Construction

slide-46
SLIDE 46
slide-47
SLIDE 47

Monday, March 3 0 , 2 0 0 3 0 5 :0 0 am

slide-48
SLIDE 48

Some Lessons Learned

  • Pre- bid conf erence mandatory

f or all potential bidders

  • For projects of this importance

a “partnering” meeting at the

  • utset is mandatory

§ Partnering on the technical aspects extremely important!

slide-49
SLIDE 49

Some Lessons Learned (cont. )

  • For new test procedures

included in Special Provisions insure that all involved groups perf orm tests and analyze resulting data the same way:

§ equipment calibration essential § preliminary testing of comparable specimens

slide-50
SLIDE 50

Some Lessons Learned (cont. )

  • I mproved specif ication

requirements based on statistical considerations desirable

  • For QC/ QA activities adequate

staf f ing imperative (large quantities of materials, up to 15, 000 tonnes per weekend)

slide-51
SLIDE 51

Some Lessons Learned (cont. )

  • Timely QA results required
  • Human resources – 3 to 5

weekend closures in a row maximum; if more required, allow 1 to 2 weekend interval

slide-52
SLIDE 52

Some Lessons Learned (cont. )

  • I n digout areas (FDAC) :

§Exploratory testing imperative §Exact location of underground utilities

slide-53
SLIDE 53

Some Lessons Learned (cont. )

  • Contingency plan important

§Digout areas - working platf orm; materials easily accessible §Standby HMA plant(s)

  • Meteorologist f or contractor

(construction in digout areas)

slide-54
SLIDE 54

Perf ormance Evaluation

  • FWD Def lection testing (2003 through

2008)

  • Back calculation of layer moduli and

strains in HMA layers using MLEA

  • Condition surveys
  • Longitudinal and transverse prof ile

measurements

  • Noise measurements
  • Laboratory testing of cores (RSST- CH)

and slabs (Fatigue)

slide-55
SLIDE 55

Perf ormance Evaluation

  • Non- destructive HWD tests

§11/ 03, NB and SB §9/ 04, NB; 2/ 5, SB §12/ 05, NB; 2/ 06, SB

slide-56
SLIDE 56

CENTER DEFLECTIONS LANE 3 I-710 SOUTHBOUND (ADJUSTED TO 19C)

100 200 300 400 500 600 700 800 50 100 150 200 250 300 350 LOCATION DEFLECTION (MICRONS) 2003 2004 2005 2008 Section 1(FD) Section 2(CSOL) Section 3(FD) Section 4(CSOL) Section 5(FD) PCH 405

Deflections – SB Lane 3

X 03 03 05 08

slide-57
SLIDE 57

CENTER DEFLECTIONS LANE 3 I-710 NORTHBOUND (ADJUSTED TO 19C)

100 200 300 400 500 600 700 800 900 1000 50 100 150 200 250 LOCATION DEFLECTION (MICRONS) 2003 2004 2006 2008 Section 1(FD) Section 2(CSOL) Section 3(FD) Section 4(CSOL) Section 5(FD) PCH 405

Deflections – NB Lane 3

X 03 03 05 08

slide-58
SLIDE 58

I-710 Northbound Lane 3 Full Depth Sections - Layer Moduli with Time

3,000 6,000 9,000 12,000 15,000 2002 2003 2004 2005 2006 2007 2008 2009

Year Tested

Modulus (MPa)

Section 1 AC Section 3 AC Section 5 AC Section 1 Base Section 3 Base Section 5 Base

NB Lane 3 – Layer Moduli

slide-59
SLIDE 59

Tensile Strain, Underside HMA Layer, in/ in x 10- 6

Section NB SB 1 18 49 3 17 18 5 16 8.5

slide-60
SLIDE 60

Rut Depth Measurements

SB Lane 3

3 6 9 12 15

0+00 5+00 10+00 15+00 20+00 25+00 30+00 35+00 40+00 45+00

Station (m) Rutting (mm) Left WP Right WP

12.5 mm

slide-61
SLIDE 61

Rut Depth Measurements

NB Lane 3

3 6 9 12 15

0+00 10+00 20+00 30+00 40+00

Station (m) R u t t i n g ( m m ) Left WP Right WP

12.5 mm

slide-62
SLIDE 62

I - 710 Traf f ic

slide-63
SLIDE 63

I - 710 Traf f ic

slide-64
SLIDE 64

I - 710, Phase I I

  • Modif ications

§Design traf f ic: - 330x106 ESALs §Thickness of HMA base layer [PG 70- 10 (AR- 8000)] increased §Surf ace course: RAC- G instead

  • f RAC- O
slide-65
SLIDE 65

Concluding Thoughts

  • I mplementation of New Technology f or Mix &

Structural Design

  • Strict Attention To Pavement Construction
  • Constructability Considerations -

Use of CA4PRS

  • Successf ul partnering – agency, contractor and

academia.

  • Paving perf orming as expected.
slide-66
SLIDE 66

Summary

  • I mplementation of SHRP

developed technology

  • Strict attention to pavement

construction

  • Constructability considerations;

(CA4PRS)