The MIM System Refresh Project Stakeholder Working Group March 30, 2015 Agenda 1. Review IESO responses regarding Bid/Offer Report and Web Services 2. Changes to Web Services 3. Project schedule 4. RTEM mock-up user interface (Draft) 5.
Agenda
- 1. Review IESO responses regarding Bid/Offer
Report and Web Services
- 2. Changes to Web Services
- 3. Project schedule
- 4. RTEM mock-up user interface (Draft)
- 5. Next steps
2
Responses to Bid/Offer Report
Based on market participant feedback, IESO will create a new Bid/Offer report as one deliverable of the project.
- Frequency of Report - Daily
- Location of Report – Private Report Site
- Content of Report - Final Valid Bid/Offer
- Retention Period – 90 Days
- Format of Report – XML file which aligns with the XSD schema
defined in the MIM web services
3
Responses to Web Services
- OPG: When querying bid/offer status we can get all data (OPER_RESV,
Bilateral, RTEM, Schedule) in one request. Is there equivalent function through the web services interface? IESO Response: The MIM Web Services will provide a query operation for each type
- f data (i.e. RTEM, Schedule, Operating Reserve, Bilateral and DGD).
- Brady Energy: While the WSDL seems to contain all the necessary fields
that are currently in use in the MIM API, we discovered some technical issues when trying to use it in a Microsoft .NET 4 development environment. IESO Response: IESO will change the MIM Web Services design to resolve the identified technical issues. The responses are published on the IESO web site http://www.ieso.ca/Pages/Participate/Stakeholder-Engagement/SE-118.aspx
4
Web Services Changes
- Changes to resolve the issue with .NET4 platform by:
Distinguishing the faults for partially rejected submissions and completely rejected submissions.
- Changes to improve on the design by:
1. Extracting the HOURLY complex type from each of the submission operation as a separate HOURLY type, to avoid generating unconventional names; 2. Adding faults for query operations, to identify errors in the request sent to MIM Web Services.
New version of web services files are available on the IESO web site http://www.ieso.ca/Pages/Participate/Stakeholder-Engagement/SE-118.aspx
5
Project Schedule
Development
- Jan 2015 –Nov 2015
Participant Testing/Market Trial
- Dec 2015 - Jan 2016
Go Live
- Apr 2016
Decommission IDK
- Apr 2017
6
RTEM Mock-up User Interface -1
7
RTEM Mock-up User Interface -2
8
RTEM Mock-up User Interface -3
9
RTEM Mock-up User Interface -4
10
Next Steps
Date Activities Expected Action April 17, 2015 Deadline for written input from stakeholders
- n EMI RTEM mock-up
screens Working Group to submit written feedback
- n EMI RTEM mock-up
screens May 8, 2015 Deadline for written responses to the input from stakeholders on EMI RTEM mock-up screens Working Group to receive written responses from the IESO Q3, 2015 Preparation of the participant testing Market Participants to receive notification regarding the participant testing and the IESO to arrange the training and testing.
11
Thank You!
12