The Expansion of the Panama Canal The Impact of Developments in Rock - - PowerPoint PPT Presentation

the expansion of the panama canal
SMART_READER_LITE
LIVE PREVIEW

The Expansion of the Panama Canal The Impact of Developments in Rock - - PowerPoint PPT Presentation

The Expansion of the Panama Canal The Impact of Developments in Rock Mechanics presentation to the American Rock Mechanics Association Luis D. Alfaro Vicepresident of Engineering Panama Canal Authority June 25, 2012 Panama Creation of the


slide-1
SLIDE 1

The Expansion of the Panama Canal

The Impact of Developments in Rock Mechanics

presentation to the

American Rock Mechanics Association

Luis D. Alfaro Vicepresident of Engineering Panama Canal Authority June 25, 2012

slide-2
SLIDE 2

Panama

slide-3
SLIDE 3

Creation of the Canal

Chagres Obispo Rio Grande Atlantic Pacific

slide-4
SLIDE 4

The Panama Canal

Gatun Dam Gatun Locks Gatun Lake Madden Dam Madden Lake Miraflores Spillway

Principal components

Gaillard Cut Miraflores Locks Pedro Miguel Locks Miraflores Lake Atlantic Pacific

slide-5
SLIDE 5

Longitudinal Profile of the Canal

ATLANTIC PACIFIC GATUN LAKE MIRAFLORES LAKE GAILLARD CUT GATUN LOCKS PEDRO MIGUEL LOCKS MIRAFLORES LOCKS

slide-6
SLIDE 6

The Canal Expansion Program

slide-7
SLIDE 7

History of Panama Canal Traffic

FY 1915 – FY 2010

5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000 50,000

1916 1919 1922 1925 1928 1931 1934 1937 1940 1943 1946 1949 1952 1955 1958 1961 1964 1967 1970 1973 1976 1979 1982 1985 1988 1991 1994 1997 2000 2003 2006 2009

50 100 150 200 250 300 350

PCUMS Tonnage in millions

Transits per year

PCUMS 299.1 Transits 14,342

Fiscal Year

slide-8
SLIDE 8

Long Term Demand Forecast

100 150 200 250 300 350 400 450 500 550 600 1995 1997 1999 2001 2003 2005 2007 2009 2011 2013 2015 2017 2019 2021 2023 2025

Year PCUMS in Millions Historical Canal Capacity (Tonnage) Revised Forecast (January 2009)

Historical Forecast

340 508

Additional capacity after expansion Existing Canal maximum capacity (Tonnage)

Demand for shipping

slide-9
SLIDE 9

Deepening and widening Atlantic entrance Atlantic Pospanamax Locks Pacific Pospanamax Locks

17.65 M m3

Deepening & Widening Pacific Entrance

9.06 M m3

Increase of the maximum

  • perating level of Gatun Lake

26.7 m 27.1 m

Gatun Lake widening and deepening and widening of Gaillard Cut navigation channels (26.5Mm3) Pacific Access Channel 50.1 M m3

Program Components

New Locks Access Channel Existing Locks Existing Locks

slide-10
SLIDE 10

Atlantic entrance deepening and widening Atlantic Site pospanamax Locks Pacific Site pospanamax Locks 17.65M m3

Pacific entrance

deepening and widening

9.06 M m3

Increase of the maximum

  • perating level of Gatun Lake

26.7 m 27.1 m

Gatun Lake widening and deepening and widening of Gaillard Cut navigation channels (26.5Mm3) Pacific Access Channel 49 M m3

Program Components

slide-11
SLIDE 11

The Cost of the Canal Expansion Program

Total: $5.25 Billion

New Locks 52% Water Saving Basins 12% Pacific Access Channel 16% Improvements to Existing Channels 5% Water Regulation 5% Inflation during Construction 10%

slide-12
SLIDE 12

Post-Panamax Locks Project Pacific Access Channel – Phase 4 Atlantic Entrance Pacific Entrance

Sacyr-Vallehermoso - Spain Impregilo - Italy Jan De Nul – Belgium CUSA – Panama Montgomery Watson Harza - US Design Construction ICA - Mexico FCC - Spain MECO – Costa Rica Jan De Nul - Belgium Dredging International - Belgium

Main Contractors

slide-13
SLIDE 13

The Post-Panamax Locks

slide-14
SLIDE 14

Dimensions of Locks and Ships

33.5 m (110’) 32.3 m (106’) 12.8 m (42’) 55 m (180’) 49 m (160’) 18.3 m (60’) 12.4 m (39.5’) 15.2 m (50’)

Maximum size of vessels in existing Locks: 4,400 TEU

Maximum size of vessels in new Locks:

13,000 – 14,000 TEU

slide-15
SLIDE 15

Post-Panamax Locks Operation GUPC Proposal

With the WSB, the new locks will save 60%

  • f the water used for a lockage

WSB 1 WSB 2 WSB 3

Operation of the Water Saving Basins

slide-16
SLIDE 16

New Atlantic Locks

2.10M m3 of structural concrete

slide-17
SLIDE 17

New Atlantic Locks

slide-18
SLIDE 18
slide-19
SLIDE 19

Canal Expansion Program

New Pacific Locks

2.34M m3 of structural concrete

slide-20
SLIDE 20

New Pacific Locks

slide-21
SLIDE 21

New Locks Project

slide-22
SLIDE 22

New Locks Project

0% 50% 100%

24%

Completed

slide-23
SLIDE 23
slide-24
SLIDE 24

Rolling gates

  • 8 pairs of rolling gates in 8 lockheads
  • Approximately 52,500 tons of steel

Lockhead with 2 Rolling Gates Single Rolling Gate

slide-25
SLIDE 25

Gate Manufacturing – Cimolai (Pordenone, Italy)

slide-26
SLIDE 26

Gate Manufacturing

slide-27
SLIDE 27

Cimolai Assembly yard

slide-28
SLIDE 28

Pacific Access Channel

(the second Gaillard Cut)

slide-29
SLIDE 29

Structural Geology of the PAC area

Tb: Basalt Tpa: Pedro Miguel Agglomerate Tca: Cucaracha Soft Rocks TL: La Boca Soft Rocks

New Pacific Access Channel

Miraflores Faults Pedro Miguel Fault Aguadulce Faults Miraflores Faults Pedro Miguel Fault Aguadulce Faults

slide-30
SLIDE 30

PAC-3 PAC-4

Borinquen Dam 1E Cellular Cofferdam

PAC-1 PAC-2

Pacific access channel

Layout of Excavation Projects

slide-31
SLIDE 31

Estimated date of completion: 31-Oct-13

Pacific Access Channel

0% 50% 100%

.

81%

Actual

slide-32
SLIDE 32
  • Scope of Contract:

– 26 M m3 excavation – Borinquen dam construction – Clearing of 80 hectares of UXO.

  • Award: January 7, 2010
  • Amount: B/. 267,798,795.99
  • Company: Consortium ICA-FCC-MECO
  • Completion of contract: August 2, 2013

.

0% 50% 100%

59 % Completed

.

Completed 68 %

excavation contract

Pacific Access Channel – Phase 4

26 M m3 dry excavation

slide-33
SLIDE 33

Pacific Access Channel – Phase 4

slide-34
SLIDE 34

Pacific Access Channel – Phase 4

34

slide-35
SLIDE 35

The Borinquen Dams

slide-36
SLIDE 36

The Borinquen Dams

+26m +16m

  • 3m to +3m
slide-37
SLIDE 37

PostPanamax navigation channel & Miraflores Lake

10 m Pacific access channel Rockfill Miraflores Lake Clay core

slide-38
SLIDE 38

View of Excavated Slopes, Cofferdam and Rockfill

Cofferdam Dam foundation Rockfill

slide-39
SLIDE 39

View of the cofferdam and construction of Dam 1E

Cofferdam Dam foundation Rockfill

slide-40
SLIDE 40

Widening and Deepening of Existing Navigation Channels

slide-41
SLIDE 41

Widening and Deepening of the Atlantic Entrance

  • Total Excavation : 17.65 M m3
  • Excavation to date: 17.38 M m3

.

0% 50% 100%

98% Actual

slide-42
SLIDE 42

Widening and Deepening of the Atlantic Entrance

slide-43
SLIDE 43

Deepening and widening of the Pacific Entrance

.

0% 50% 100%

85% Actual

  • Total Excavation : 9.06 M m3
  • Excavation to date: 7.70 M m3
slide-44
SLIDE 44

Barro Colorado

Gamboa Gatun Lake

Completed by ACP Work underway by ACP Completed by Dredging International Completed by Dredging International

Gatun Lake and Gaillard Cut Dredging Areas

.

0% 50% 100%

69 % Actual

slide-45
SLIDE 45

Total Excavation and Dredging - May 2012

75%

.

150.8 Program Total 112.7 Completed

Locks 47.5 M m3 Pacific Access 50.1 M m3 Dredged 53.2 M m3 Estimated 150.8 M m3

slide-46
SLIDE 46

Excavation Volumes (Mm3)

Canal Expansion

151 545

French effort

23 271

Landslides (post- construction)

70

Improvement projects

394 123

U.S. construction

201 178

slide-47
SLIDE 47

Expansion Program Progress

Pacific Access Channel

Progress

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Progress

Pacific Entrance Deepening and Widening Gatun Lake and Gaillard Cut Deepening and Widening

Progress

End of last Contract: 31-Oct-2013 End of Contract: 31-Aug-2012

Locks Design and Construction Atlantic Entrance Deepening and Widening

Progress Progress

End of Contract: 21-Oct-2014 End of Contract: 24-Apr-2013

Progress

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Expansion Program Raising Gatun Lake’s Maximum Operational Level

Progress

37.62 M m3 excavated / 49 M m3 7.68 M m3 dredged / 8.7 M m3 16.8 M m3 dredged / 28 M m3 23.2 M m3 excavated / 40 M m3 17.3 M m3 dredged / 17.6 M m3

End: 30-Sep-2013 End: 11-Apr-2014

68% 84% 69% 24 % 98% 6% 38% Design: 75%

slide-48
SLIDE 48

The impact of developments in Rock Mechanics on the Canal

slide-49
SLIDE 49

Canal Construction (1904-1914)

Goethals Gorgas Hodges Gaillard Sibert Rousseau Bishop Thatcher

Picture taken: 25 August 1910

slide-50
SLIDE 50
  • Col. David DuBose Gaillard

(1859-1913)

1850 1900 1950 2000

1904 -1913

Completed the task, considering the extremely limited knowledge and tools at his disposal In charge of excavations through the continental divide (Culebra Cut)

slide-51
SLIDE 51

September 19, 1912

East Culebra Slide

slide-52
SLIDE 52

February 2, 1913

East Cucaracha Slide

slide-53
SLIDE 53

February 7, 1913

East Cucaracha Slide

slide-54
SLIDE 54
slide-55
SLIDE 55
slide-56
SLIDE 56

Inauguration of the Canal

August 15, 1914

slide-57
SLIDE 57

East & West Culebra slides (October 1915)

slide-58
SLIDE 58

Original Design of Excavations

Reference: McCullough “The Path Between the Seas” (1977)

slide-59
SLIDE 59

Karl von Terzaghi (1883-1963)

1850 1900 1950 2000

1936 “.… the catastrophic descent of the slopes in the deepest cuts on the Panama Canal issued a warning the we were overstepping the limits of our ability to predict the consequences of our actions.”

Presidential Address given at the first International Conference on Soil Mechanics and Foundation Engineering, Cambridge Massachusetts, June 1936

slide-60
SLIDE 60

Arthur Casagrande (1902-1981) in the Panama Canal

Birth of the Modern Landslide Control Program

October 1968

slide-61
SLIDE 61

Modern Landslide Control Program

Monument with prism EDM on Master Station

Incipient slide

slide-62
SLIDE 62
slide-63
SLIDE 63

Marcuson Schuster Duncan Morgenstern Wesson Sowers

1850 1900 1950 2000

1987-present ACP’s Geotechnical Advisory Board Canal Personnel

Technology Transfer & Credibility

slide-64
SLIDE 64
  • Impact of geologic structure on failure mechanism
  • Groundwater conditions
  • Operative strength parameters

Requirements for the design of effective remedial measures

slide-65
SLIDE 65

USGS

Map I-1232 (1980) R.H. Stewart J.L. Stewart W.P. Woodring

slide-66
SLIDE 66

Increased Site Investigation efforts

slide-67
SLIDE 67

Continuous Geological Mapping of the Excavations

slide-68
SLIDE 68
  • Dr. Frank Patton

Westbay Instruments

Multi-point Piezometers

Packer Packer Measurement Port Pumping Port (Hydraulic Conductivity)

slide-69
SLIDE 69

Multi-point Piezometers

slide-70
SLIDE 70
  • Dr. Evert Hoek in the Panama Canal

Shear strength characterization for weak rocks

Hoek-Brown envelope

= (cot i’ – cos i’) m

c / 8 i’= arctan[4hcos2{30+(1/3)arcsin h-3/2} -1]-1/2

h = 1 + 16(m ’+s

c)/(3m2 c)

slide-71
SLIDE 71
  • 100

200 300 400 500 600 700

shear strength (kPa) effective normal stress (kPa)

Hoek-Brown m = 0.2 s = 0.001 UCC = 3,500 kPa (500 psi)

R = 7.5o

JRC = 10 JRC = 5 Barton

Strength Envelopes for weak tuffs

Cucaracha, Culebra, La Boca and Gatuncillo Formations

slide-72
SLIDE 72

1850 1900 1950 2000

1991 ACP’s Geotechnical Laboratory

slide-73
SLIDE 73

10 100 1,000 10,000 100,000 1,000,000 1 10 100

Young's Modulus, E MPa Uniaxial Compressive Strength, σa (ult) MPa

Modulus Ratio for the Cucaracha Formation in Gaillard Cut

Cucaracha

Mpa 100:1 50:1

27.6 55.2 110.3 220.6

MPa

E

VERY LOW STRENGTH

D

LOW STRENGTH

C

MEDIUM STRENGTH

B

HIGH STRENGTH

A

VERY HIGH STRENGTH

500:1 200:1 300:1 1,000:1

6.9

slide-74
SLIDE 74

10 100 1,000 10,000 100,000 1,000,000 1 10 100

Young's Modulus, E MPa Uniaxial Compressive Strength, σa (ult) MPa

Modulus Ratio for Soft Rocks in Gaillard Cut

La Boca Culebra Cucaracha

Mpa 100:1 50:1

27.6 55.2 110.3 220.6

MPa

E

VERY LOW STRENGTH

D

LOW STRENGTH

C

MEDIUM STRENGTH

B

HIGH STRENGTH

A

VERY HIGH STRENGTH

500:1 200:1 300:1 1,000:1

6.9

slide-75
SLIDE 75

Strength Characterization

Pedro Miguel Sound Basalt Sheared Basalt La Boca Cucaracha

Geological Strength Index (GSI)

0.00 0.50 1.00 1.50 0.00 0.25 0.50 0.75 1.00 NORMAL STRESS, MPa SHEAR STRESS, MPa

CUCARACHA-FULLY-SOFTENED CUCARACHA-RESIDUAL STRENGTH FULLY-SOFTENED-LA BOCA GSI-21, mi=7, Sc=6.4MPa, LA BOCA PEDRO MIGUEL, GSI=26, mi=19, Sc=31 PEDRO MIGUEL, GSI=9, mi=19, Sc=31 BASALT, GSI=26, mi=25, Sc=59 SHEARED BASALT BASALT, GSI=5, mi=25, Sc=59 PACIFIC MUCK

60 45 30 15 7.5

Shear Strength Envelopes

Hard Rocks Soft Rocks and Soils

slide-76
SLIDE 76
slide-77
SLIDE 77

June 25, 2012

Thank you!!