The Culzean Development Martin Urquhart, Project Director, Maersk Oil UK What makes Culzean different to a conventional development? >5x pressure of normal reservoir and >2x temperature Equipment at technical limits of supply chain


slide-1
SLIDE 1

The Culzean Development

Martin Urquhart, Project Director, Maersk Oil UK

slide-2
SLIDE 2
slide-3
SLIDE 3

What makes Culzean different to a conventional development?

  • >5x pressure of normal reservoir and >2x

temperature

  • Equipment at technical limits of supply chain

capability

  • Well costs c $250MM each. Normal well costs c

$40-50MM

  • Fully rated API 15K WHP Topsides
  • Design challenges due to scale and weight of

API15k equipment. Example:

  • Typical flowline cost of $250k. Culzean flowline

cost is $15MM

  • Complex, high integrity safety systems to mitigate

risks

‘8” API 15K Ball Valve from FCT Common classification of HP/HT vs. uHP/uHT

slide-4
SLIDE 4

Image: HPHT wellhead being installed

What’s the Impact on Time & Cost vs. NPNT?

  • Time
  • Wells take nearly 1 year to drill
  • Specialist HDJU rig required: 2 year

construction

  • Need three wells drilled before first gas
  • Minimize Depletion Drilling
  • Cost
  • Pre-FID investment on Culzean is $100s of

MM vs. pre-FID investment of $0-50MM

  • HDJU commitment – 5yr Contract
  • WHP Jacket & WAD – 10,000Te
  • Long Leads for Initial Wells & Relief Wells
slide-5
SLIDE 5

Case For Sanction?

  • Gas Bias Production Profile
  • Lean Gas, Economics not reliant on oil price
  • Sheltered UK Gas market
  • Fiscal Incentive
  • Worked with Treasury at Select Gate
  • 1st Cluster Allowance awarded
  • Front End Loading
  • Well Defined Requirements
  • 21 Long Leads worth $200MM procured &

novated

  • Market Deflation
  • Contracts
  • Commodities
slide-6
SLIDE 6

~$2bn of Contracts Awarded

  • 3 Topsides – SMOE Singapore
  • Power Generation Module Bridges

& Flare – SLP Lowestoft

  • 3 Jackets – Hereema Vlissingen
  • 6 Pile Cluster & WAD – Heerema

Hartlepool

  • Pipelines & Structures – Subsea 7

Aberdeen

  • FSO – Modec and Sembcorp

Marine

  • TBD – Hook up & Commissioning
  • TBD – HUC Accommodation vessel
slide-7
SLIDE 7

21st century installation

  • Integrated operations using real time data

monitoring and analysis enabling faster decision making

  • Fibre optic cable between base and field
  • Minimised offshore manning
  • Onshore integrated operations centre

providing 24/7 support

  • 100m bridges link ULQ, WHP and CPF topsides
  • Human involvement on processing facilities

kept to a minimum

  • 140 beds: no need for ‘walk to work’ vessels

Image: Siemens Walk Inside software allows users to interact with topside designs

slide-8
SLIDE 8

Long term outlook

  • Production profile
  • £2.1bn OPEX
  • 150+ Contracts YTBA
  • CoP 2034
  • UK energy security
  • Supporting thousands of jobs
  • Continued need for industry

efficiency

slide-9
SLIDE 9

Hub Potential

  • Culzean is Cluster 001
  • Exploration and Development

Expense can be offset against hub production

  • Maersk and CoVs have

prospects in the area

slide-10
SLIDE 10

Maersk Oil: navigating complexity, unlocking potential