The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH - - PowerPoint PPT Presentation

the challenge of legacy assets
SMART_READER_LITE
LIVE PREVIEW

The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH - - PowerPoint PPT Presentation

The Impact of the Internet of Things on our Lives. The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH Wireless ASH Wireless is an electronics design consultancy Specialising in wireless and sensors An Ofgem funded Network


slide-1
SLIDE 1

The Impact of the Internet of Things on our Lives.

The Challenge of Legacy Assets

Richard Lucas, BSc(Eng) MBA

MD of ASH Wireless

ASH Wireless is an electronics design consultancy Specialising in wireless and sensors

slide-2
SLIDE 2

2

An Ofgem funded Network Innovation Competition project

slide-3
SLIDE 3

3

The problem

Assets have nominal thermal rating Ratings = OC Ratings K amps Diverse range of environments Small changes in environmental factors can result in very different actual ratings

HV network LV network

Assumed thermal ratings can lead to capacity being under-utilised

  • r

unnecessary risk Objective is to maximise power through transformer

slide-4
SLIDE 4

4

Celsius as part of the smart future

Celsius monitoring Smart meter data Thermal Ratings Tool Reinforce Retrofit cooling Extra capacity Lower bills for customers

slide-5
SLIDE 5

5

Step 1: Fit thermal monitoring

Internal temperature Asset Environmental factors External temperature Thermal coefficient Learning Thermal Ratings Tool Deliverable More capacity Benefit

slide-6
SLIDE 6

6

Step 2: Retrofit cooling

Retrofit cooling Internal temperature Asset Environmental factors External temperature Full capacity Benefit Enhanced Thermal Ratings Tool Deliverable Retrofit cooling specifications, installation methodologies and buy order Learning

slide-7
SLIDE 7

7

Partners and roles on project

Facilitate customer focus groups Develop customer communication materials Lead the customer survey engagement Analyse trial data Develop methodologies to understand relationship between asset temperature, load characteristics and surrounding environment Determine impact of cooling technologies Develop tool and spec for low cost temperature sensor Recommendations for BAU rollout Supply complete retrofit monitoring solution Provide ongoing support throughout installation, commissioning and

  • peration of the

retrofit thermal monitoring workstream Peer review of the analysis methodology of the retrofit temperature sensor part of the project An investigative study on the impact

  • f Celsius on the

lifetime health of network assets Work with ASH, Ricardo-AEA and Electricity North West to develop retrofit thermal monitoring solution Participate in evaluation and selection of retrofit cooling techniques

slide-8
SLIDE 8

8

Monitoring site selection and timescales

To enable trials to take place during all seasons and to trial all cooling techniques Four year project Subset of 520 substations – enough sites to adequately trial all techniques 100 cooling technique sites Enough substations to represent 80% of GB substation population 520 substations

slide-9
SLIDE 9

9

Celsius

£5.5

million

Investment

Up to £583m across GB by 2050

Financial benefits

Awarded: 9th December 2015

Go live

Monitoring installation Mar 2017 Monitoring trial Mar 2018 Thermal ratings tool stage 1 Oct 2018 Retrofit cooling installation Jun 2018 Cooling trial Jun 2019 Thermal ratings tool stage 2 Jan 2020

Closedown Mar 2020

slide-10
SLIDE 10

So the answer’s simple

  • 1. Gather data on the power throughput &

characteristics, asset temperature,

  • 2. Work out the relationships, and how you can change

these with retrofitted cooling technology

  • 3. Decide how long you can postpone reinforcing or

replacing assets,

  • 4. Save lots of money

But there are some practical problems…………..

slide-11
SLIDE 11

11

Legacy Assets

▪ A significant percentage of electrical substations are more than half a century old ▪ Most are not installed with measurement equipment for voltage, current, power, power quality, temperature

  • f key assets

▪ Critical infrastructure – any work must not intrude on continued operation. ▪ Access to the sites is restricted for safety reasons

slide-12
SLIDE 12

12

?How to fit monitoring sensors when…

▪ No internet connection available ▪ No mains power available ▪ Can’t install wiring, mount equipment, etc without intruding on critical

  • perations

▪ Challenging RF environment for radio connections,, multipath, multiple monitoring points needed

slide-13
SLIDE 13

KeLVN

  • Design Requirements

▪ Monitoring system can be installed non-invasively; ▪ All equipment magnetic or cable-tie mounting; ▪ All equipment battery powered for duration of data gathering project (3.5 years). ▪ All equipment wireless, only leads are those required to actually take measurements. ▪ Daily reports to back end. 30 minute measurements of V, I, P, Q, THD, Temperature

slide-14
SLIDE 14

Backhaul Choices

  • Clusters of sensors over a

small area

  • Spread over a large part of

the country

  • Mobile network is clear winner
  • LPWAN
  • Possible, but patchy network

support

  • 2.5G GPRS chosen
  • Coverage, component cost
slide-15
SLIDE 15

Local Wireless Sensor Network

  • Requirement for large substations (30m x 15m), sensors

may be in cabinets

  • Path loss at 2.4GHz expected less than 90dB
  • Avoid stationary nulls by using antenna diversity
  • Energy-efficient 802.15.4 transceivers used, no front-

end-modules

  • Operation needs to allow for more than one hub
  • Large coverage
  • Check installation from outside the substation
slide-16
SLIDE 16

Local Wireless Sensor Network

  • Simple, non-paired network access, minimised energy
  • Sensors transmit the last 6 hours of measurements

(1 packet) every 30s

  • Time-jittered to avoid multiple collisions from time-

aligned sensors

  • A hub listens for 60s for reports every 6 hours
  • Hub transmits a daily report to a back-end database
  • Hub operates for 3.5 years on a Lithium D-cell
  • Other sensors use AA or D cells for >3.5 year life
slide-17
SLIDE 17

T T T T

Voltage Sensor Temperature Sensor GPRS Backhaul Mobile data link

Hub 1 Hub 2 (optional) Hex 1 PMU Hex 2 Ind. V,I,T

Low Power Radio Network

Single Temperature Sensors

Back End

KeLVN

  • Substation Monitoring
slide-18
SLIDE 18

Battery Life

  • The Hub is an interesting challenge:
  • Lithium D-cell, 10AH
  • Over 3.5 years life
  • Distribution of where the capacity is used:

KeLVN Hub battery usage

Daily GPRS data transfer Sensor receiver window Quiescent: ‘off’

slide-19
SLIDE 19

Key learning points

  • The installation and environment defines
  • Equipment design (e.g. magnetic mounting)
  • Protocol (e.g. multiple hubs allowed)
  • installation procedure (fast, non-invasive)
  • GPRS modem auto-connect modes are not reliable,

process needs detailed design

  • Alarms
  • Not required in Celsius
  • Low latency for alarms is managed with a hub

software extension, and external power to the hub

slide-20
SLIDE 20

Example of how legacy assets can be made to yield valuable data

Retrofitting monitoring equipment to legacy assets:

  • Ease of installation is primary consideration
  • Use of a local wireless sensor network eases installation
  • Optimise air interface to manage trade off between

latency, data rate, battery life

slide-21
SLIDE 21

Additional material

slide-22
SLIDE 22

22

Site selection map

slide-23
SLIDE 23

23

Celsius technology

Hub Wireless sensor

slide-24
SLIDE 24

24

Celsius technology – trial fit

LV board with three sensors

slide-25
SLIDE 25

25

Celsius technology – trial fit

Transformer

slide-26
SLIDE 26

26

Trial site data

  • 5

5 10 15 20 25 30 35

  • 20

20 40 60 80 100 120 140

30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016 12:00 02/10/2016 00:00 02/10/2016 12:00 Temperature Degrees C Real Power kW per Phase

Magda Rd 750kVA Transformer Load and Temperatures

P1 kW P2 kW P3 kW Top Oil oC Inlet oC Outlet oC Bottom Oil oC