the challenge of legacy assets
play

The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH - PowerPoint PPT Presentation

The Impact of the Internet of Things on our Lives. The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH Wireless ASH Wireless is an electronics design consultancy Specialising in wireless and sensors An Ofgem funded Network


  1. The Impact of the Internet of Things on our Lives. The Challenge of Legacy Assets Richard Lucas, BSc(Eng) MBA MD of ASH Wireless ASH Wireless is an electronics design consultancy Specialising in wireless and sensors

  2. An Ofgem funded Network Innovation Competition project 2

  3. The problem HV network LV network Objective is to Assets have Diverse range of Assumed thermal maximise power nominal thermal environments ratings can lead to through rating capacity being Small changes in transformer under-utilised environmental Ratings = O C or factors can result Ratings K amps unnecessary risk in very different actual ratings 3

  4. Celsius as part of the smart future Thermal Ratings Tool Smart meter data Celsius Retrofit monitoring cooling Reinforce Extra capacity Lower bills for customers 4

  5. Step 1: Fit thermal monitoring Learning Deliverable Benefit Asset Internal temperature External temperature Environmental More Thermal Thermal factors capacity coefficient Ratings Tool 5

  6. Step 2: Retrofit cooling Learning Deliverable Benefit Asset Internal temperature External temperature Environmental Full Retrofit cooling Enhanced factors specifications, Thermal capacity installation Ratings Retrofit methodologies Tool cooling and buy order 6

  7. Partners and roles on project Supply complete Peer review of the Analyse trial data Work with ASH, Facilitate customer retrofit monitoring analysis Ricardo-AEA and focus groups Develop solution methodology of the Electricity North methodologies to retrofit temperature West to develop understand Develop customer sensor part of the retrofit thermal relationship between Provide ongoing communication project monitoring solution asset temperature, support throughout materials load characteristics installation, and surrounding commissioning and An investigative Participate in environment Lead the customer operation of the study on the impact evaluation and survey engagement retrofit thermal of Celsius on the Determine impact of selection of retrofit monitoring lifetime health of cooling technologies cooling techniques workstream network assets Develop tool and spec for low cost temperature sensor Recommendations for BAU rollout 7

  8. Monitoring site selection and timescales 100 cooling 520 substations Four year project technique sites Enough To enable trials to Subset of 520 substations to take place during substations – represent 80% of all seasons and to enough sites to GB substation trial all cooling adequately trial all population techniques techniques 8

  9. Celsius Awarded: 9th December 2015 Thermal Thermal Retrofit Monitoring Monitoring ratings Cooling ratings Closedown cooling Go live installation trial tool stage trial tool stage installation Mar 2020 Mar 2017 Mar 2018 1 Jun 2019 2 Jun 2018 Oct 2018 Jan 2020 Up to £583m £5.5 across GB by million Financial 2050 benefits Investment 9

  10. So the answer’s simple 1. Gather data on the power throughput & characteristics, asset temperature, 2. Work out the relationships, and how you can change these with retrofitted cooling technology 3. Decide how long you can postpone reinforcing or replacing assets, 4. Save lots of money But there are some practical problems…………..

  11. Legacy Assets ▪ A significant percentage of electrical substations are more than half a century old ▪ Most are not installed with measurement equipment for voltage, current, power, power quality, temperature of key assets ▪ Critical infrastructure – any work must not intrude on continued operation. ▪ Access to the sites is restricted for safety reasons 11

  12. ?How to fit monitoring sensors when… ▪ No internet connection available ▪ No mains power available ▪ Can’t install wiring, mount equipment, etc without intruding on critical operations ▪ Challenging RF environment for radio connections,, multipath, multiple monitoring points needed 12

  13. KeLVN - Design Requirements ▪ Monitoring system can be installed non-invasively; ▪ All equipment magnetic or cable-tie mounting; ▪ All equipment battery powered for duration of data gathering project (3.5 years). ▪ All equipment wireless, only leads are those required to actually take measurements. ▪ Daily reports to back end. 30 minute measurements of V, I, P, Q, THD, Temperature

  14. Backhaul Choices • Clusters of sensors over a small area • Spread over a large part of the country • Mobile network is clear winner • LPWAN • Possible, but patchy network support • 2.5G GPRS chosen • Coverage, component cost

  15. Local Wireless Sensor Network • Requirement for large substations (30m x 15m), sensors may be in cabinets • Path loss at 2.4GHz expected less than 90dB • Avoid stationary nulls by using antenna diversity • Energy-efficient 802.15.4 transceivers used, no front- end-modules • Operation needs to allow for more than one hub • Large coverage • Check installation from outside the substation

  16. Local Wireless Sensor Network • Simple, non-paired network access, minimised energy • Sensors transmit the last 6 hours of measurements (1 packet) every 30s • Time-jittered to avoid multiple collisions from time- aligned sensors • A hub listens for 60s for reports every 6 hours • Hub transmits a daily report to a back-end database • Hub operates for 3.5 years on a Lithium D-cell • Other sensors use AA or D cells for >3.5 year life

  17. KeLVN - Substation Monitoring Hub 1 Back Single Temperature GPRS End Low Power Sensors Backhaul Radio Network Mobile data link Hub 2 (optional) Hex 1 Hex 2 PMU Ind. V,I,T Voltage Sensor T Temperature Sensor T T T

  18. Battery Life • The Hub is an interesting challenge: • Lithium D-cell, 10AH • Over 3.5 years life • Distribution of where the capacity is used: KeLVN Hub battery usage Quiescent: ‘off’ Daily GPRS data transfer Sensor receiver window

  19. Key learning points • The installation and environment defines • Equipment design (e.g. magnetic mounting) • Protocol (e.g. multiple hubs allowed) • installation procedure (fast, non-invasive) • GPRS modem auto-connect modes are not reliable, process needs detailed design • Alarms • Not required in Celsius • Low latency for alarms is managed with a hub software extension, and external power to the hub

  20. Example of how legacy assets can be made to yield valuable data Retrofitting monitoring equipment to legacy assets: • Ease of installation is primary consideration • Use of a local wireless sensor network eases installation • Optimise air interface to manage trade off between latency, data rate, battery life

  21. Additional material

  22. Site selection map 22

  23. Celsius technology Hub Wireless sensor 23

  24. Celsius technology – trial fit LV board with three sensors 24

  25. Celsius technology – trial fit Transformer 25

  26. Trial site data Magda Rd 750kVA Transformer Load and Temperatures 140 35 120 30 100 25 80 20 Real Power kW per Phase Temperature Degrees C 60 15 40 10 20 5 0 0 30/09/2016 00:00 30/09/2016 12:00 01/10/2016 00:00 01/10/2016 12:00 02/10/2016 00:00 02/10/2016 12:00 -20 P1 kW P2 kW P3 kW Top Oil oC Inlet oC Outlet oC Bottom Oil oC -5 26

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend