TenneT Transmission System Operator Mel Kroon CEO TenneT - - PowerPoint PPT Presentation

tennet
SMART_READER_LITE
LIVE PREVIEW

TenneT Transmission System Operator Mel Kroon CEO TenneT - - PowerPoint PPT Presentation

TenneT Transmission System Operator Mel Kroon CEO TenneT 01-12-2014 1 Key tasks of a TSO Our three key tasks Transmission services 1 Constructing and maintaining a robust and effcient high-voltage grid. System services 2 Maintaining


slide-1
SLIDE 1

1

Transmission System Operator

Mel Kroon CEO TenneT 01-12-2014

TenneT

slide-2
SLIDE 2

2

Key tasks of a TSO

Our three key tasks

Transmission services Constructing and maintaining a robust and effcient high-voltage grid. System services Maintaining the balance between electricity supply and demand 24/7. Market facilitation Facilitating a smooth functioning, liquid and stable electricity market.

1 3 2

slide-3
SLIDE 3

3

Organisation

slide-4
SLIDE 4

4

Organisation

Ownership structure

01-12-2014 TenneT - Transmission System Operator

slide-5
SLIDE 5

5

Board of management

A Dutch-German team

18-11-2014 TenneT - Transmission System Operator 01-12-2014

slide-6
SLIDE 6

6

Supervisory board

01-12-2014

  • dr. ir. A.W. (Aad) Veenman

Chairman Supervisory Board Member Remuneration and Appointment Committee Member Strategic Investments Committee Member Audit Committee Year of birth: 1947 Nationality: Dutch Initial appointment: 2005 Principal position Former President N.V. Nederlandse Spoorwegen

  • dr. J.L.M. (Hans) Fischer

Member Supervisory Board Member Strategic Investments Committee Year of birth:1956 Nationality: German Initial appointment: 2014 Principal position Chief Technical Officer, Tata Steel Europe

  • ir. R.G.M. (Rien) Zwitserloot

Member Supervisory Board Member Strategic Investments Committee Year of birth: 1949 Nationality: Dutch Initial appointment : 2010 Principal position Former Chairman Management Board Wintershall AG

  • drs. S. (Stephanie)

Hottenhuis Member Supervisory Board Chairman Remuneration and Appointments Committee Year of birth: 1965 Nationality: Dutch Initial appointment: 2013 Principal position Member of Executive Board Arcadis N.V.

  • dr. P.M. (Pieter) Verboom

Vice-chairman Supervisory Board Chairman Audit Committee Year of birth: 1950 Nationality: Dutch Initial appointment: 2012 Principal position Former Executive Vice- President and CFO Schiphol Group

TenneT - Transmission System Operator

slide-7
SLIDE 7

7

Vision

Our society has committed to the large-scale introduction of renewable energy. Generation of renewable energy is changing the dynamics of supply. At the same time, dependence on electricity continues to increase. This demands continuous reliability. To cope with these developments, the European electricity market must be integrated further. Sound market design, technical and operational innovation, storage solutions and adequate grid capacity are all required to continue to match supply and demand across borders.

slide-8
SLIDE 8

8

Renewable energy

  • Production not driven by price
  • Marginal costs almost zero
  • On other locations then conventional production
  • Connections & Storage: “Spread and Store”
  • Flexibility of demand
  • Back-up capacity
slide-9
SLIDE 9

9

Mission

To provide security of electricity supply in the markets we serve, and to pursue, as a leading Transmission System Operator, the development of an integrated and sustainable North West European electricity market.

slide-10
SLIDE 10

10

Energy policy

Three pillars

01-12-2014

Energy policy

Sustainable

Green energy

Reliable

High standard

Affordable

Efficiency

TenneT - Transmission System Operator

slide-11
SLIDE 11

11

TenneT grid

01-12-2014 TenneT - Transmission System Operator

slide-12
SLIDE 12

12

Key figures

01-12-2014

50Hz 99.9999% 200x 61 14% p/y 12 bn 20 bn 400 m IRR: 10.9% LTIF 4.5 82% (employees) 75% (customers) 0,4 μT SF6<1.000 kg

TenneT - Transmission System Operator

slide-13
SLIDE 13

13

Grid integration and interconnection

18-11- 2014

2008 NorNed (700 MW) 2009 Integration High Voltage networks 2010 BritNed (1000 MW) + Integration NL-DE 2014 Decision Cobra-cable ready: 2019 (700 MW) 2014 Decision NordLink ready: 2018 (1400 MW) 2016 Doetinchem- Wesel ready (1500 MW) 2018 Expansion Meeden- Diele ready (+500 MW) 2008-heden Market coupling

The interconnection capacity consists of more than 20% of the total operational electricity production capacity . This makes the Netherlands the best connected country of the world. The EU dictates at the moment an interconnection capacity

  • f 10%.
slide-14
SLIDE 14

14

Challenges

  • Safety
  • Public acceptance
  • Introduction of innovations
  • Regulatory regime the Netherlands
  • Timely implementation of projects
  • Further cooperation / integration TSO’s
slide-15
SLIDE 15

15

Onshore

slide-16
SLIDE 16

16

Onshore grid expansion NL

  • Large projects (380 kV):
  • Randstad 380 kV North Ring
  • North-West 380 kV
  • South-West 380 kV
  • Doetinchem-Wesel
  • Increase capacity connection Zwolle-

Diemen-Geertruidenberg-Maasbracht (2 x 380 km)

  • NoordOostPolder (NOP) 110 kV

EUR 4-5 billion investment over the next ten years

01-12-2014 TenneT - Transmission System Operator

slide-17
SLIDE 17

17

Onshore grid expansion NL

  • 300 other projects a.i.:
  • Five interconnections to Belgium and

Germany; sixth interconnectors under construction (Doetinchem-Wesel, to be completed in 2016)

  • Approx. 400 km of new connections

EUR 4-5 billion investment over the next ten years

01-12-2014 TenneT - Transmission System Operator

slide-18
SLIDE 18

18

Onshore grid expansion GER

  • Over 500 kilometers of new connections

planned: fifteen large onshore projects plus hundreds of smaller projects

  • Transporting wind energy from northern

Germany to consumers and industry in southern Germany

  • Connecting new power plants to the grid
  • SuedLink: will be the longest DC grid

connection with the highest transport capacity (2GW) in Germany and will transport wind energy from northern Germany to industrial regions in the south

  • f the country

EUR 7-8 billion over the next ten years

TenneT - Transmission System Operator 01-12-2014

slide-19
SLIDE 19

19

Offshore

slide-20
SLIDE 20

20

Offshore developments

*Locations are fictional.

  • Lower financing costs for TSO
  • Double connection

= redundant = higher efficiency

  • Fewer dune crossings:

environmental benefits and cost reductions

  • Standardization, learning effects

and purchasing advantages: cost reduction

  • Prepared for use of 380 kV cable

in the near future Station also functions as hub Wind farm directly connected to station Centralized maintenance: cost reduction

Project “Wind op Zee”, Offshore NL

TenneT - Transmission System Operator

A cost reduction of 35 to 40% and achieving the 2023 targets is only feasible with a structured approach, careful planning and standardisation. Expected investment of EUR 2-3 billion.

01-12-2014

slide-21
SLIDE 21

21

Offshore grid expansion

TenneT - Transmission System Operator Projects (DE) Capacity (MW) Operational (planned) Operational alpha ventus 60 (AC) 2009 BorWin1 400 (DC) 2010 Riffgat 108 (AC) 2014 Total 568 Projects Capacity (MW) Operational (planned) Project put out to tender BorWin4 900 (DC) 2019 Projects Capacity (MW) Operational (planned) Under construction/awarded BorWin2 800 (DC) 2015 DolWin1 800 (DC) 2014 DolWin2 900 (DC) 2015 DolWin3 900 (DC) 2017 HelWin1 576 (DC) 2014 HelWin2 690 (DC) 2015 SylWin1 864 (DC) 2015 Nordergründe 111 (AC) 2016 BorWin3 900 (DC) 2018 Total installed and under construction 7,109 2019 Projects Capacity (MW) Operational (planned) Interconnections NorNed 700 (DC) 2008 BritNed 1,000 (DC) 2011 NordLink 1,400 (DC) 2018 Cobra 700 (DC) 2019 Projects (NL) Capacity (MW) Operational (planned) Offshore Wind NL 3,450 (AC) 2023 01-12-2014

slide-22
SLIDE 22

22

DolWin beta

slide-23
SLIDE 23

23

Safety at TenneT

Ben Voorhorst COO TenneT

slide-24
SLIDE 24

24

Why this Safety Vision?

  • A fatal incident
  • A lot of ‘near miss incidents and high risk incidents’
  • Increasing risk of operations, expansion of offshore activities
  • Different level Safety performance contractors
  • Oil & Gas and Petrochemical industry: it is possible!

TenneT - Transmission System Operator 01-12-2014

slide-25
SLIDE 25

25

Safety goals 2018

  • LTIF < 1, TenneT employees and contractor employees
  • Be a leading Safety company
  • Safety performance is a reflection of operational excellence
  • From the perspective to strive for zero harm and zero incidents

TenneT - Transmission System Operator 01-12-2014

slide-26
SLIDE 26

26

How?

Focus on:

  • One TenneT
  • Safety Leadership
  • Contractor

Management

  • Safety Roadmap

TenneT - Transmission System Operator 01-12-2014

slide-27
SLIDE 27

27

Roadmap activities

  • Board level meeting on Safety
  • Joined Incident Review Board
  • Execution of Safety Walks by contractor
  • Active discussions on Safety with contractor
  • Aligning procurement procedures with Safety ambitions
  • Implementation of Life Saving Rules
  • Safety performance reviews with contractor

Focus on dialogue Focus on processes and indicators

TenneT - Transmission System Operator 01-12-2014

slide-28
SLIDE 28

28

Impact

Contractor Management:

  • Best performers will be rewarded
  • Continue to work with strong safety performers
  • Challenge contractors to improve their performance
  • Challenge contractors to improve TenneT performance
  • Say goodbye to underperformers

TenneT - Transmission System Operator 01-12-2014

slide-29
SLIDE 29

29

Safety Performance

Improve Safety performance by:

  • Challenging not only our main contractor, but also sub contractors.
  • Making a shift from compliance driven to a risk based approach.
  • Having a pro active and open relationship with our contractors.

You are our “Partners in Safety”. Let’s make it work (safely)!

Working together on Safety

TenneT - Transmission System Operator 01-12-2014