technology and operation
play

technology and operation Andreas Efstratiadis, Nikos Mamassis & - PowerPoint PPT Presentation

Renewable Energy & Hydroelectric Works 8 th semester, School of Civil Engineering Hydroelectric reservoirs: technology and operation Andreas Efstratiadis, Nikos Mamassis & Demetris Koutsoyiannis Department of Water Resources &


  1. Renewable Energy & Hydroelectric Works 8 th semester, School of Civil Engineering Hydroelectric reservoirs: technology and operation Andreas Efstratiadis, Nikos Mamassis & Demetris Koutsoyiannis Department of Water Resources & Environmental Engineering, NTUA Academic year 2018-19

  2. Schematic layout of hydroelectric reservoir Crest level Maximum pool level Freeboard Normal pool level Max. flood Extra capacity Spill gate storage Weir (spill) level & head Useful capacity Actual level Dam Useful height storage Minimum Intake Gross pool level storage Power station River Dead volume bed Foundation level

  3. Characteristic elevations & storage components Normal pool level : Maximum elevation to which the water surface will rise during normal  operating conditions; the corresponding storage is referred to as total capacity . Minimum pool level : Lowest elevation to which water is drawn from a reservoir under  normal operating conditions. Maximum pool level : Maximum elevation to which the water surface is expected to rise  during the design flood of the spillway. Dead storage : Volume of water held below the minimum pool level, which cannot be used  for any purpose under normal condition. It depends on: the volume of sediment that is expected to be deposited into the reservoir during  its design life; the elevation of the lowest outlet of the dam;  the minimum head required for efficient functioning of the turbines.  Useful storage : Volume of water stored between the normal pool level and the minimum  pool level, i.e. difference between the actual storage and the dead volume; also referred to as active storage , as water can be used for various purposes. Useful capacity : Total capacity after subtracting the dead storage.  Surcharge or flood storage : Uncontrolled volume of water stored between the normal and  the maximum pool level; it exists only during floods and cannot be retained for later use.

  4. Storage-elevation & area-elevation curves Graphs illustrating the change of reservoir storage, s ,  and impoundment area, a , against the water level, z . The relationships s = f 1 ( z ) and a = f 2 ( z ) are extracted  on the basis of data sets ( z i , a i ) that either estimated by measuring the associated areas on a topographic map or are calculated automatically (and with high accuracy) by using the digital elevation model of the area of interest. Reservoir area (km 2 ) Επιφάνεια ταμιευτήρα (km 2 ) Digital elevation 32.0 28.0 24.0 20.0 16.0 12.0 8.0 4.0 0.0 model (DEM) of 800 Plastiras reservoir Max pool level +792 m Reservoir level (m) 790 Στάθμη ταμιευτήρα ( m) The two curves can also be expressed  Min. pool analytically, as power functions of z , i.e.: 780 level +776 m s = κ ( z – z 0 ) λ 770 s = κ ( z / z 0 ) λ Απόθεμα Storage 760 where κ and λ are parameters that are Area Επιφάνεια estimated through regression, and z 0 is 750 a characteristic low level, e.g. the dead 0 50 100 150 200 250 300 350 400 450 500 550 volume level or the foundation level. Reservoir storage (hm 3 ) Απόθεμα ταμιευτήρα (hm 3 )

  5. Major hydraulic structures Dam : Barrier constructed across a river, thus forming an artificial lake (reservoir) to hold  back water and raise its level. Generally, they are classified into two groups: Embankment dams , constructed from natural material excavated or obtained  nearby (further classified into earthfill and rockfill); Gravity dams , either from conventional vibrated concrete (CVC) or concrete mixed  with earth materials, e.g. roller compacted concrete (RCC) or hardfill. Ancillary hydraulic structures :  Bottom outlet , which allows emptying the reservoir in case of emergency;  Intakes and penstocks , controlling the water releases through the reservoir;  Spillway system , typically consisting of a controlling weir, a channel (chute) and a  stilling basin, to safely pass overflows downstream when the reservoir is full; Spillway gates , to regulate floods flows and further increase both the storage  capacity and the available head (mainly applicable to large hydroelectric works); Power station , located at the end of the penstock, to host the electromechanical  equipment (turbines, generators, transformers); Internal drainage works, collecting seepage within the body of the dam;  Auxiliary structures (used during the construction phase) :  Cofferdams (the upstream one is often incorporated into the main dam);  Diversion system (tunnel or channel), to bypass the river flows during construction; 

  6. Layout of hydroelectric system: Kastraki, Achelous Tunnel entrance Achelous river Diversion tunnel Intake Spill weir Crest & road Earthfill dam Penstocks Spill channel (chute) Power station Tunnel Tailrace outlet Transformer

  7. River diversion during dam construction The period of construction may exceed ten years, thus  the upstream cofferdam and the diversion tunnel are designed to retain floods of return periods 20-50 years. Usually, another (smaller) cofferdam is built downstream  of the main dam site to prevent water flowing back into the construction area. After the end of construction, two closure actions are  employed to allow first impounding , i.e. a temporary closure of the entrance by using gates, and a permanent closing, by implanting a concrete plug inside the tunnel. Entrance & outlet of diversion tunnel during construction of Hilarion dam

  8. Outlet bottom Bottom outlets mainly are safety works, to  Louros dam, pilot ensure conveyance of water into downstream operation (1954) river and to lower the level of the reservoir, in case of emergency evacuation . The intake is constructed close to the  foundation, while the inlets of main conveyance works (e.g., penstocks) are sited at much higher elevations (lower operation level). Modern bottom outlets are also designed to  provide ecological flow to the downstream river, as well as to discharge sediments , thus increasing the economic life of the dam. Plastiras dam, downstream view Cerro del Águila Dam, Peru (2015)

  9. Intakes and associated works Usually horizontal, followed by a curve to an  inclined or vertical power tunnel or a penstock. Horizontal layout facilitate the  placement of gates, trash racks, bulkheads and stoplogs. Stratos dam: inclined intakes under construction Kremasta dam: Power intake Kastraki dam: trash racks and gates

  10. Penstocks and associated works For large hydroelectric systems, the number of penstocks typically equals the number of  turbines (expensive design); otherwise a single penstock of larger diameter is applied that splits at the power house (increase of local losses). General design recommendations:  Kastraki dam: four exposed (surface) penstocks, H = 76 m Total hydraulic losses should not  exceed 5% of gross head; Velocity should not exceed 6 m/s  Major design issue: water hammer (surge tank  or pool, in case of large pipes and large heads) Plastiras dam, diversion penstock, H = 577 m

  11. Spillways Objective: safe abstraction of the overflowed  floodwater and its safe transfer and disposal to the downstream river. Main components are: Approach channel;  Control structure (weir);  Discharge channel (chute);  Terminal structure (stilling basin);  During a flood event, the inflow hydrograph is routed through the reservoir and the  spillway system, thus the outflow hydrograph arriving downstream is attenuated. The return period of the design flood may exceed 5 000 to 10 000 years. Controlled spillways : The flow is regulated through mechanical structures or gates. This  design allows nearly the full height of the dam to be used for water storage, and flood waters can be released as required by opening one or more gates. Uncontrolled spillways : When the water rises above the crest, it begins to be released  from the reservoir. The outflow rate is controlled only by the depth of water above the reservoir's spillway. The volume above the crest can only be used for the temporary storage of floodwater; it cannot be accounted for as useful storage, because it is normally empty. Remarks : In hydropower reservoirs, order to minimize water losses due to spill, when the water level reaches or exceeds the weir elevation, the turbines are forced to operate in their maximum capacity, thus producing surplus energy (also referred to as secondary energy ).

  12. Spillways of large hydroelectric reservoirs in Greece Gated spillway, Side-channel spillway, Kremasta dam Kastraki dam Pilot operation of Overturning Platanovrisi spillway gates, Kastraki

  13. Outlet works: draft tubes & tailraces Layout of outlet works of Stratos dam Stratos I Ι Stratos Ι (underground) Tailrace (outlet channel), 7.0 km Dry bed of River Achelous Gates at the outlet Downstream Wet river bed downstream of the tailrace Upstream

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend