Project Update SYSTEM ASSESSMENT PROJECT 5/15/2012 1 System Assessment Project Status Update Phase one: relay setting comparison All contract engineer reports have been reviewed and no additional corrective actions have been


slide-1
SLIDE 1

5/15/2012  1

SYSTEM ASSESSMENT PROJECT

Project Update

slide-2
SLIDE 2

5/15/2012  2

System Assessment Project Status Update

Phase one: relay setting comparison

  • All contract engineer reports have been reviewed and no additional corrective actions have

been required.

  • At Newport, additional documentation effort is required before a contract engineer is able to

perform the comparison. Phase two: record drawing review

  • Contract engineer reviews have been completed on thirteen stations, with VELCO

acceptance review completed on the same thirteen stations.

  • Newport has been added as a station requiring drawing review and will require an additional

effort to prepare the documentation before engaging the contract engineer. Phase three: relay setting basis

  • Anticipated completion of contract engineer reviews for the Vernon & VY areas is in

September, and the anticipated completion of the Essex area is in July.

  • It was identified the cross tripping of 345kV A & B systems does not meet NPCC
  • requirements. VELCO is in the process of making design enhancements and will be

establishing a corrective action plan for systems that are already in service. Phase four: line testing

  • Fourteen of thirty-four lines have been tested. Summary reports are still pending from the

contract engineer.

slide-3
SLIDE 3

5/15/2012  3

System Assessment Project Status Update

1 1 1 1 3 4 5 7 13 14 18 21 23 24 24 24 24 24 24 24 24 24 24 24 24 3 7 7 15 17 18 23 29 29 30 31 31 31 31 31 31 31 31 31 31 31 31 31 31 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 1 6 8 8 13 16 20 26 28 30 31 31 31 31 31 31 31 31 31 31 31 2 2 3 8 8 8 11 13 18 24 31 33 37 40 40 43 44 45 45 46 48 49 1 1 1 1 3 3 3 21 22 23 23 23 24 24 24 24 24 24 24 24 24 24 24 24 24 1 2 2 4 4 5 9 10 14 16 21 23 25 27 29 30 30 30 30 31 31 31 31 31 1 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 3 3 5 5 10 10 16 21 24 26 28 29 30 30 30 30 31 31 31 2 3 3 3 3 3 3 14 21 29 30 32 36 39 39 42 44 44 46 48 49 49 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 20 40 60 80 100 120 140 160

Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13

PH4L EAC (Cum) PH4S EAC (Cum) PH3 EAC (Cum) PH2 EAC (Cum) PH1 EAC (Cum) PH4L BL (Cum) PH4S BL (Cum) PH3 BL (Cum) PH2 BL (Cum) PH1 BL (Cum) % Complete Actual % Complete (Prj) % Complete (BL)

Percent Complete

Number of Completion

WORK DOWN PROJECTION CURVE - May 4, 2012

1% 3% 7% 8% 15% 22% 28% 33% 47% 53% 61% 72% 79% 86% 88% 91% 93% 93% 96% 96% 97% 97% 98% 99% 100%

8% 10% 26% 29% 33% 46% 55% 69% 75% 80% 86% 90% 91% 93% 95% 96% 97% 99% 100% 100%

Actual as of report date is 33%. Projection by the end

  • f this month is 46%.