5/15/2012 1
SYSTEM ASSESSMENT PROJECT 5/15/2012 1 System Assessment Project - - PowerPoint PPT Presentation
SYSTEM ASSESSMENT PROJECT 5/15/2012 1 System Assessment Project - - PowerPoint PPT Presentation
Project Update SYSTEM ASSESSMENT PROJECT 5/15/2012 1 System Assessment Project Status Update Phase one: relay setting comparison All contract engineer reports have been reviewed and no additional corrective actions have been
5/15/2012 2
System Assessment Project Status Update
Phase one: relay setting comparison
- All contract engineer reports have been reviewed and no additional corrective actions have
been required.
- At Newport, additional documentation effort is required before a contract engineer is able to
perform the comparison. Phase two: record drawing review
- Contract engineer reviews have been completed on thirteen stations, with VELCO
acceptance review completed on the same thirteen stations.
- Newport has been added as a station requiring drawing review and will require an additional
effort to prepare the documentation before engaging the contract engineer. Phase three: relay setting basis
- Anticipated completion of contract engineer reviews for the Vernon & VY areas is in
September, and the anticipated completion of the Essex area is in July.
- It was identified the cross tripping of 345kV A & B systems does not meet NPCC
- requirements. VELCO is in the process of making design enhancements and will be
establishing a corrective action plan for systems that are already in service. Phase four: line testing
- Fourteen of thirty-four lines have been tested. Summary reports are still pending from the
contract engineer.
5/15/2012 3
System Assessment Project Status Update
1 1 1 1 3 4 5 7 13 14 18 21 23 24 24 24 24 24 24 24 24 24 24 24 24 3 7 7 15 17 18 23 29 29 30 31 31 31 31 31 31 31 31 31 31 31 31 31 31 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 1 6 8 8 13 16 20 26 28 30 31 31 31 31 31 31 31 31 31 31 31 2 2 3 8 8 8 11 13 18 24 31 33 37 40 40 43 44 45 45 46 48 49 1 1 1 1 3 3 3 21 22 23 23 23 24 24 24 24 24 24 24 24 24 24 24 24 24 1 2 2 4 4 5 9 10 14 16 21 23 25 27 29 30 30 30 30 31 31 31 31 31 1 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 3 3 5 5 10 10 16 21 24 26 28 29 30 30 30 30 31 31 31 2 3 3 3 3 3 3 14 21 29 30 32 36 39 39 42 44 44 46 48 49 49 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 20 40 60 80 100 120 140 160
Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13
PH4L EAC (Cum) PH4S EAC (Cum) PH3 EAC (Cum) PH2 EAC (Cum) PH1 EAC (Cum) PH4L BL (Cum) PH4S BL (Cum) PH3 BL (Cum) PH2 BL (Cum) PH1 BL (Cum) % Complete Actual % Complete (Prj) % Complete (BL)
Percent Complete
Number of Completion
WORK DOWN PROJECTION CURVE - May 4, 2012
1% 3% 7% 8% 15% 22% 28% 33% 47% 53% 61% 72% 79% 86% 88% 91% 93% 93% 96% 96% 97% 97% 98% 99% 100%
8% 10% 26% 29% 33% 46% 55% 69% 75% 80% 86% 90% 91% 93% 95% 96% 97% 99% 100% 100%
Actual as of report date is 33%. Projection by the end
- f this month is 46%.