Sydenham Pearl Brownfield Remediation Project 2017 Conference - - - PowerPoint PPT Presentation

sydenham pearl brownfield remediation project
SMART_READER_LITE
LIVE PREVIEW

Sydenham Pearl Brownfield Remediation Project 2017 Conference - - - PowerPoint PPT Presentation

Sydenham Pearl Brownfield Remediation Project 2017 Conference - Brownfields: The Next Generation June. 15, 2017 Ed Taves Joshua Schram, BA Project Manager Policy Planner CH2M HILL City of Brantford Presentation Overview Site Context


slide-1
SLIDE 1

Sydenham Pearl Brownfield Remediation Project

2017 Conference - Brownfields: The Next Generation June. 15, 2017

Joshua Schram, BA Policy Planner City of Brantford Ed Taves Project Manager CH2M HILL

slide-2
SLIDE 2

Presentation Overview

  • Site Context
  • Historical

Background

  • Pre-remediation

Environmental Assessments

  • Remediation

Phases 2 &3

  • Key Project

Challenges

  • Next Steps
slide-3
SLIDE 3

City of Brantford

  • Population: 100,000
  • Single-tier

municipality

  • 2 Major Brownfield

Projects Underway

  • Brownfield projects

managed by:

  • *Planning Department
  • Technical support

from other departments

slide-4
SLIDE 4

Site Context

  • Site is comprised of 2

properties owned by the City of Brantford

  • The site area is

approximately 2.4 ha (6 acres)

  • Mostly surrounded by a

residential neighbourhood.

  • 22 Sydenham Street

directly abuts the CN rail line on the north side.

slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7
  • Smaller companies went

bankrupt

  • vacant & underutilized

infrastructure

  • Prone to vandalism, fire, pests,

squatters

slide-8
SLIDE 8
slide-9
SLIDE 9

Project History

1991 - 2001

  • Major industry vacated the Site and portions of onsite infrastructures were

demolished. 2002 - 2004

  • After a subsequent fires, the City acting as the agent on behalf of the Medical

Officer of Health, demolished all remaining structures on site.

  • The City proceeded with environmental investigations of the site, the demolition
  • f above ground structures, and removal of underground storage tanks.

2005 - 2011

  • The City entertained options for purchase and sale of the property.
  • City decided to undertake remediation and redevelopment of the site
  • To achieve parkland/residential standards
slide-10
SLIDE 10

Project Funding

  • 2012 Council approved $4.6 million to complete

the remediation of the Sydenham Pearl Site to the highest environmental standards to support residential/parkland uses.

slide-11
SLIDE 11

Remediation Program

2012 Phase One (Technical Background) 2013-2015 Phase Two Environmental Site Remediation Risk Assessment 2016 Risk Assessment-Soil Cap Requirement Site Risk Assessment Approval 2017 Record of Site Condition Finalized regulatory procedures Consideration for Redevelopment

slide-12
SLIDE 12

Project Mobilization

2012 RFP: Phase One and Two Environmental Site Assessments CH2M HILL Retained to oversee remediation and provide contract administration 2013-2015 Milestone Environmental Contracting was hired by the City to complete the remediation of the site, and remediation was overseen by CH2M HILL.

slide-13
SLIDE 13

Phase Two Environmental Site Assessment (17 Sydenham)

slide-14
SLIDE 14

The remediation took 8 weeks to complete and included:

  • The removal of underground storage tanks
  • Excavation and offsite disposal of petroleum hydrocarbons in soil
  • Insitu-soil mixing to break down volatile organic compounds in soil

and groundwater

Phase 2 - Remediation Program

slide-15
SLIDE 15

Phase 2 - Remediation Program

slide-16
SLIDE 16

Lang Tool

slide-17
SLIDE 17
slide-18
SLIDE 18

Phase 3 took roughly 8-10 weeks to complete and included:

  • Asphalt stripping, transport and

disposal excavation,

  • Crushing and reuse of concrete onsite;
  • Berm construction (CN requirement);
  • Installation of non-woven geotextile and

soil capping over the entire site and;

  • Hydro-seeding, tree planting, and

sodding.

Phase 3: Soil Cap Design and Construction

slide-19
SLIDE 19

Preparation for Concrete Crushing Stockpiling of Crushed Concrete

Phase 3 Photos

slide-20
SLIDE 20

Phase 3 Photos

Infiltration Gallery 22 Sydenham Street Infiltration Gallery 17 Sydenham Street

slide-21
SLIDE 21

Non-woven geotextile installed on 17 Sydenham Installation of geogrid on 17 Sydenham

Phase 3 Photos

slide-22
SLIDE 22

22 Sydenham (March 2016) 22 Sydenham (Nov 2016)

(City of Brantford Planning Department, 2016)

Phase 3 Photos

slide-23
SLIDE 23

22 Sydenham (Nov 2016)

(City of Brantford Planning Department, 2016)

22 Sydenham (Sep 2016)

slide-24
SLIDE 24
slide-25
SLIDE 25

Key Project Challenges

  • Adjacent Residential
  • Encroachments
  • Public Communication
slide-26
SLIDE 26

Options

The Public City of Brantford Consultants

Next Steps: Public Consultation – Future Uses

slide-27
SLIDE 27

Project Timelines

Task Schedule Record of Site Condition Fall 2017 Staff Report to Council Fall 2017 Public Communication & Information Fall/Winter 2017

slide-28
SLIDE 28

THANK YOU - QUESTIONS?

Joshua Schram, BA Policy Planner City of Brantford JSchram@brantford.ca Ed Taves Project Manager CH2M HILL etaves@ch2m.com