Sydenham Pearl Brownfield Remediation Project
2017 Conference - Brownfields: The Next Generation June. 15, 2017
Joshua Schram, BA Policy Planner City of Brantford Ed Taves Project Manager CH2M HILL
Sydenham Pearl Brownfield Remediation Project 2017 Conference - - - PowerPoint PPT Presentation
Sydenham Pearl Brownfield Remediation Project 2017 Conference - Brownfields: The Next Generation June. 15, 2017 Ed Taves Joshua Schram, BA Project Manager Policy Planner CH2M HILL City of Brantford Presentation Overview Site Context
Joshua Schram, BA Policy Planner City of Brantford Ed Taves Project Manager CH2M HILL
Background
Environmental Assessments
Phases 2 &3
Challenges
from other departments
1991 - 2001
demolished. 2002 - 2004
Officer of Health, demolished all remaining structures on site.
2005 - 2011
2012 Phase One (Technical Background) 2013-2015 Phase Two Environmental Site Remediation Risk Assessment 2016 Risk Assessment-Soil Cap Requirement Site Risk Assessment Approval 2017 Record of Site Condition Finalized regulatory procedures Consideration for Redevelopment
2012 RFP: Phase One and Two Environmental Site Assessments CH2M HILL Retained to oversee remediation and provide contract administration 2013-2015 Milestone Environmental Contracting was hired by the City to complete the remediation of the site, and remediation was overseen by CH2M HILL.
and groundwater
disposal excavation,
soil capping over the entire site and;
sodding.
Preparation for Concrete Crushing Stockpiling of Crushed Concrete
Infiltration Gallery 22 Sydenham Street Infiltration Gallery 17 Sydenham Street
Non-woven geotextile installed on 17 Sydenham Installation of geogrid on 17 Sydenham
22 Sydenham (March 2016) 22 Sydenham (Nov 2016)
(City of Brantford Planning Department, 2016)
22 Sydenham (Nov 2016)
(City of Brantford Planning Department, 2016)
22 Sydenham (Sep 2016)
Options
The Public City of Brantford Consultants
Joshua Schram, BA Policy Planner City of Brantford JSchram@brantford.ca Ed Taves Project Manager CH2M HILL etaves@ch2m.com