super b factory collider work at slac
play

Super-B-Factory Collider Work at SLAC U. Wienands, for John T. - PowerPoint PPT Presentation

SLAC Accelerator Department Super-B-Factory Collider Work at SLAC U. Wienands, for John T. Seeman SLAC Hawaii Super-B-Factory Meeting April 20, 2005 SLAC Accelerator Department The PEP-II Team August 2004 3 SLAC Accelerator


  1. SLAC Accelerator Department Super-B-Factory Collider Work at SLAC U. Wienands, for John T. Seeman SLAC Hawaii Super-B-Factory Meeting April 20, 2005

  2. SLAC Accelerator Department The PEP-II Team • August 2004 3

  3. SLAC Accelerator Department Topics • Brief PEP-II status and plans • Super-B-Factory Collider parameter studies • Conclusions 4

  4. SLAC Accelerator Department SLAC Beam Lines 5

  5. SLAC Accelerator Department PEP-II Interaction Region Components near BaBar LER HER BaBar Collision point 6

  6. SLAC Accelerator Department PEP-II arc section 7

  7. SLAC Accelerator Department PEP-II HER RF cavities 8

  8. SLAC Accelerator Department • Total >240 fb -1 ! 9

  9. SLAC Accelerator Department 10

  10. SLAC Accelerator Department PEP-II Performance Measure: Peak Luminosity 11

  11. SLAC Accelerator Department Trickle injection at the B Factories Best shift, no trickle Nov 2003 Best shift, LER only trickle Mar 2004 Best shift, double trickle PEP-II Lumi PEP-II: ~5 Hz continuous HER current KEKB: at ~5-10 min intervals LER current 12

  12. SLAC Accelerator Department Overall Parameters and Goals Twice design Best in Future Parameter Units Design collision 2007 goal I+ mA 2140 2450 4500 I- mA 750 1550 2200 Number 1658 1588 1715 bunches β y * mm 15-20 11 8.5 0.03 0.045, 0.07 0.055-0.08 ξ y x10 33 Luminosity 3.0 9.2 23 Integrated pb -1 130 710 1800 lumi / day Over five times design! 13 Over three times design

  13. SLAC Accelerator Department PEP-II Run Schedule • SLAC was shut down until early April due to electrical accident & ensuing safety reviews • PEP-II Run 5 started April 15, 2005. • Will collide steadily from April 2005 through July 2006 with a one month break in October 2005. • Down in 2006 August through November for BaBar and PEP-II upgrade work. • Three month down in Summer-Fall 2007 for LCLS work. • Collide through September 2008. 14

  14. SLAC Accelerator Department Integrated Luminosity Goal PEP II Integrated Luminosity (1/fb) 1200.0 1000.0 800.0 ∫ Ldt 600.0 400.0 200.0 0.0 r r r 5 6 7 8 l l l l e e e i i i i 0 0 0 0 r r r r b b b p p p p - - - - m m m A g A g A g A g u u u u e e e A c A c A c A e e e D D D Month 15 Series1

  15. SLAC Accelerator Department Upgrades for Run 5 • One additional rf station for each HER and LER – HER beam current >1.8 A, LER, 3.6 A • Removed NEGs in the LER upstream of BaBar – rf power leaking through screen caused severe heating. – more to be replaced in October 16

  16. SLAC Accelerator Department Existing 3082 chamber Quad extrusion BPM Cooling bar BPM NEG plenum Chamber support NEG heater 17

  17. SLAC Accelerator Department SiC HOM absorber Chamber shown inverted and plenum not shown for clarity 18

  18. SLAC Accelerator Department PEP-II/BaBar Roadmap: Super B-Factory Study May 2004 • The Roadmap Committee is studying the long range future of PEP-II and BaBar with a possible large upgrade at the end of the decade. • A Super-PEP-II could produce 10 ab -1 per year with a peak luminosity of 7 x 10 35 /cm 2 /s. • Accelerator parameter goals have been set and work towards a solid design has started. 19

  19. SLAC Accelerator Department Recommended scenario: 7 x 10 35 • Replace present RF with SC 952 MHz frequency over period of time. • Use 8 x 3.5 GeV with up to 15.5 A x 6.8 A. • New LER and HER vacuum chambers with antechambers for higher power (x 4). • Replace LER magnets to soften radiation and resistive wall losses; rework HER magnets as well. • Push β y * to 1.7 mm: need new IR (SC quadrupoles) with 15 mrad crossing angle and crab cavities with bunch lengths of 1.8 mm. • New bunch-by-bunch feedback for 6900 bunches (every bucket) at 1 nsec spacing. (Presently designing feedback system being 0.6-0.8 nsec spacing.) 20

  20. SLAC Accelerator Department SBF Overall Parameters and Goals Best of Parameter Units 7E35 SBF 1E36 SBF PEP-II I+ A 4.5 6.8 10.0 I- A 2.2 15.5 23.0 Number 1715 6900 6900 bunches β y * mm 8.5 1.8 1.7 0.065 0.11 0.11 ξ y x10 34 Luminosity 2.3 70 100 Integrated fb -1 /day 1.8 50 75 lumi / day 21

  21. SLAC Accelerator Department Achieving Super B Luminosities b nI EI b I b Higher Currents: L ∝ n ξ y o More rf power, cooling, injector * β y o More HOM heating (more bunches) o Beam instabilities o Electron clouds, fast ions Smaller β y *: ß y * o Smaller physical/dynamic aperture o Shorter lifetime, more background Shorter σ z : o More HOM heating o Coherent synchrotron radiation o Shorter lifetime, more background Higher tune shifts: ξ y o Head-on collisions replaced by angled crossing o Degrades maximum tune shift unless crabbing cavities used 22

  22. SLAC Accelerator Department Crossing-Angle Experiment - angle Normalized L sp vs. e W. Kozanecki 1.05 1.00 Lsp / Lsp(XP=0) 0.95 0.90 0.85 by-4, msrd by-4, fit 0.80 sp. by-2, msrd sp. by-2, fit 0.75 -1000 -500 0 500 1000 XP[e-] (murad) 23

  23. SLAC Accelerator Department Initial IR Design for a Super B-Factory e36 B-factory IR +/- 14 mrads RevD 30 QF5 ± 14 mr QD4 QF2 20 crossing LER angle QD1 10 o First look at SR QD1 HER backgrounds cm 0 200 kW 40 kW 13 kW -10 Try to limit 3 kW luminosity 83 kW 11 kW QD4 -20 component by QF2 minimizing M.Sullivan QF5 bends -30 -7.5 -5 -2.5 0 2.5 5 7.5 m M. Sullivan Apr 16, 2005 B3$E36_2_5M_8D_RL 24

  24. SLAC Accelerator Department New IR magnet design (Parker) B. Parker 25

  25. SLAC Accelerator Department New IR magnet design Quadrupole, anti- solenoid, skew quadrupole, dipole and trims B. Parker located in one magnet. All coils numerically wound on a bobbin. 26

  26. SLAC Accelerator Department New Rf system, s/c Technology • 1…2 MV/cavity, 500 kW/coupler • R/Q of 12 Ω aimed at for beam stability • 952 MHz => Potential for 6900 bunches • up to 40 MW power to the beam (LER, 23 A) • Support bunches as short as 1.8 mm 27

  27. SLAC Accelerator Department New cavity design for a SBF (SC, R/Q ≈ 5 Ω ) A. Novokhatski Accelerating field Distance (cm) 28

  28. SLAC Accelerator Department New Magnet Systems/Lattices – Low momentum compaction • short bunches without excessive rf voltage • increase stability against longitudinal multibunch instability • maintain reasonable synchrotron tune – (simulations predict high ν s to be detrimental to luminosity) – Larger-aperture magnets than present PEP-II • allows increase of beam-pipe radius, lower res. wall loss • becoming an issue at SBF beam current & bunch length 30

  29. SLAC Accelerator Department Resistive-Wall Wake (bunch lengthening) Power SS: 45 MW Al: 9 MW Cu: 7 MW SR: 18 MW A. Novokhatski 31

  30. SLAC Accelerator Department New bellows design with HOM absorber • Kurita Novokhatski Weathersby 32

  31. SLAC Accelerator Department LER ring (no IR yet) M. Biagini One sextant Small positive momentum compaction, using present LER dipoles & quads (16 families), 3 sextupole families

  32. SLAC Accelerator Department Electron Cloud Instability • PEP-II uses solenoidal fields and gaps in the fill to mitigate ECI – Experiment at end of Run 4: fill all gaps • Luminosity scaled with bunch# • =>probably don’t need the gap at present beam current (2.6 A). • At Super-B beam currents, these may not be sufficient – Investigate means to further reduce secondary emission in the vacuum system 34

  33. SLAC Accelerator Department Windings added for ECI reduction 35

  34. SLAC Accelerator Department 36

  35. SLAC Accelerator Department Low-Secondary Yield Test Pipe M. Pivi 37

  36. SLAC Accelerator Department 38

  37. SLAC Accelerator Department 39

  38. SLAC Accelerator Department Wall-Plug Power 40

  39. SLAC Accelerator Department Conclusions • PEP-II is again producing data. • Present B-Factories will provide solid data for four or more years. PEP-II is heading towards 2.3 x 10 34 in three years. • Super-B-Factory designs are stabilizing. • Designs of a Super-B-Factory should allow for upgrade paths to allow the accelerator to remain competitive over its lifetime. 41

  40. SLAC Accelerator Department Important Factors in Upgrade Direction • Accelerator project should have headroom: – Design for 7 x 10 35 – Headroom for machine up to 1 x 10 36 ; requires additional RF, which can be staged into machine over time. • Accelerator built in the timely manner with a rapid turn on. 42

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend