Sulphide Oxidation Typical Albion Process leach test results Low - - PowerPoint PPT Presentation

sulphide oxidation
SMART_READER_LITE
LIVE PREVIEW

Sulphide Oxidation Typical Albion Process leach test results Low - - PowerPoint PPT Presentation

Sulphide Oxidation Typical Albion Process leach test results Low Oxidation High Oxidation 100 90 80 70 Gold Recovery (%) 60 50 40 30 20 10 0 0 10 20 30 40 50 60 70 80 90 100 Sulphide Oxidation (%) 21 Commercial


slide-1
SLIDE 1

Sulphide Oxidation

21

  • Typical Albion Process leach test results

10 20 30 40 50 60 70 80 90 100 10 20 30 40 50 60 70 80 90 100

Gold Recovery (%) Sulphide Oxidation (%)

Low Oxidation High Oxidation

slide-2
SLIDE 2

22

Commercial Plant – Flowsheet & Equipment

slide-3
SLIDE 3

Commercial Plant

23

  • Integrated Flowsheet

Albion Leach Slurry Cooling Cyanide Leach Limestone Oxygen NaCN Cyanide Destruct Underflow Thickening Tailings Elution GOLD DORE Loaded Carbon Bulk Pyrite Con Ultrafine grind Barren Carbon

Albion Process Plant

slide-4
SLIDE 4

Commercial Plant

24

  • Albion Process Reactor
  • Atmospheric leaching tank
  • Centrally mounted impeller
  • Dual hydrofoil agitators
  • Ring of supersonic oxygen spargers at

base of reactor

  • Fitted with baffles and slurry riser
  • Staged limestone slurry dosing from

limestone ring

  • Autothermal operation
  • No internal cooling coils or flash stages
slide-5
SLIDE 5

Commercial Plant

25

  • Albion Process Plant
  • Low cost materials due to

neutral pH nature of slurry (304/316 and duplex steels LDX 2101)

  • Low cost and efficient oxygen

mass transfer through combination of agitation power and sparger pressure

  • Conventional field erected or

modular tanks

  • Xstrata Technology now offers
  • ptions for prefab modular

tanks that the elements can be shipped in sea containers

slide-6
SLIDE 6

26

Capital & Operating Costs

slide-7
SLIDE 7

Capital & Operating Costs

27

  • Generic Case Study Inputs

10 20 30 40 50 60 70 80 90 100 10 20 30 40 50 60 70 80 90 100 Gold Recovery (%) Sulphide Oxidation (%)

Feed Type Concentrate Treatment rate 219,000 tpa Gold grade 20.0 g/t Sulphide sulphur grade 40.0% w/w Principle gold bearing mineral Pyrite Albion Process Design Basis Sulphide sulphur oxidation requirement* 70% Sulphide sulphur oxidation rate* 61,320 tpa CIL Process Gold recovery 90.0% Gold production 126,752 oz/y Project Input Costs Power 100 US$MWh Limestone 50 US$/t Oxygen 45 US$/t Weighted average labour cost 50,000 US$/person

slide-8
SLIDE 8

Capital & Operating Costs

28

  • Generic Case Study Order of Magnitude Capex (±30%)

Area Base 70% SOx 600 tpd (US$) ALBION PLANT 38,200,000 $ OXYGEN PLANT 24,500,000 $

TOTAL COST 62,700,000 $

NB:

Oxygen plant is outside Albion Process and Xstrata Technology scope of supply Oxygen plant costs are order of magnitude costs

Fully Installed Albion Process Plant Mechanical equipment Structural Steel Electrical distribution and plant substations Piping, valves, launders Instrumentation and control Concrete, ring beams and bunding Buildings and Architectural Civil Works (assuming level site) EPCM Labour EPCM Expenses Commissioning Labour Commissioning Expenses Insurances Temporary Works First fills and Reagents Spares Contingency Unit Operations IsaMill Fine Grind Leaching Neutral Slurry Thickening Slurry Cooling

Capex costs converted to operating cost (discount rate 12.5%

  • ver 10 years) = 185 US$/t SOx
slide-9
SLIDE 9

Capital & Operating Costs

29

  • Generic Case Study Order of Magnitude Opex (±30%)

NB: Oxygen plant is outside Albion Process and Xstrata Technology scope of supply Oxygen plant costs are order of magnitude costs that will require validation from vendors

Category US$/t con US$/oz Au Dist'n Power (IsaMill) 6 10 7% Power (Rest of plant) 2 3 2% Limestone 45 77 50% Oxygen 29 50 32% Labour 6 10 6% Maintenance supplies & consumables 3 5 3% Total 90 155 100%

Power (IsaMill) 7% Power (Rest

  • f plant)

2% Limestone 50% Oxygen 32% Labour 6% Maintenance supplies & consumables 3% Gold price US$/oz 1,000 750 500 Gold equivalent opex oz/y 19,669 26,226 39,339 g/t Au 2.8 3.7 5.6 SOx units % w/w sulphide 28.0 28.0 28.0 g/t Au per % SOx 0.10 0.13 0.20

Opex ~19.7M US$/y ~320 US$/t SOx

slide-10
SLIDE 10

Capital & Operating Costs

30

  • Generic Case Study- Sensitivity to Limestone and Power

Limestone: US$50 /t Power: US¢10/kWh Oxygen: US$45/t Limestone: US$40/t Power: US¢8/kWh Oxygen: US$35/t Limestone: US$30/t Power: US¢6/kWh Oxygen: US$27/t

Direct Opex Costs 261 US$/t SOx Amorised Capex Costs

185 US$/t SOx

TOTAL

445 US$/t SOx

215 US$/oz Au Discount Rate 12.5% Project Life 10 years Direct Opex Costs 205 US$/t SOx Amorised Capex Costs

185 US$/t SOx

TOTAL

390 US$/t SOx

189 US$/oz Au Discount Rate 12.5% Project Life 10 years Direct Opex Costs 321 US$/t SOx Amorised Capex Costs

185 US$/t SOx

TOTAL

505 US$/t SOx

245 US$/oz Au Discount Rate 12.5% Project Life 10 years