Sulfur Recovery Unit Reaction Furnaces Waste Heat Boilers Ferrule Failure Root Cause Analysis
Presented By: Muhammad Bashir Khan – Manager, Technical
Sulfur Recovery Unit Reaction Furnaces Waste Heat Boilers Ferrule - - PowerPoint PPT Presentation
Sulfur Recovery Unit Reaction Furnaces Waste Heat Boilers Ferrule Failure Root Cause Analysis Presented By: Muhammad Bashir Khan Manager, Technical Page 1 Abu Dhabi Gas Development Company Ltd. CONFIDENTIAL SRU and Ferrule Configuration
Sulfur Recovery Unit Reaction Furnaces Waste Heat Boilers Ferrule Failure Root Cause Analysis
Presented By: Muhammad Bashir Khan – Manager, Technical
SRU and Ferrule Configuration
furnaces in the thermal section of the Claus reaction
Location of ceramic ferrule tubesheet liningSRU and Ferrule Configuration
from the high temperature (approximately 1100°C) in the furnace by a lining made up of 2-piece ceramic ferrules (a hexagonal head and a cylindrical stem insertion).
Assembled Ferrule Ferrule Components Gasket, Stem, Hexagonal HeadSRU and Ferrule Configuration
the tube-sheet lining as can be seen here.
the beige mortar and the white mastic grouting.
– Both types of grout are white after dry-out
Ferrule Tube-sheet LiningInspection Findings
after start-up, the two reaction furnaces of Unit 751 were scheduled to be opened and inspected in January 2016.
– 99% of ferrules in both H-101 and H-102 found damaged
into ceramic stem body
weld
Inspection Findings
Cracked Ferrule Stem with 6 o’ clock Corrosion Deposit Tube-end and Strength Weld with Hot Sulphidation DamageInspection Findings
inspected over the course of the next 12 months and the results were very similar only varying slightly by magnitude.
Observation 751 754 752 753 Date of inspection Jan 2016 Feb 2016 Oct 2016 Jan 2017 Months in service at time of inspection 12 12 21 23 Corrosion deposit on ferrule stem Between 5 to 7 o’ clock Between 5 to 7 o’ clock Between 3 to 9 o’ clock Between 5 to 7 o’ clock % of ferrules cracked 99% 70% 100% 60% Hot Sulphidation at tube to tubesheet weld Significant Minor Very significant MinimalInvestigation Details
January and February 2016, representatives from all stakeholders worked together as a joint investigation team. This included:
– Al Hosn Gas / Occidental Petroleum (Owners) – Saipem (as EPC)
– Other 3rd Party Consultants
Investigation Details
narrowed down to be one of the following four:
– Hot Gas Bypass
sulphidation on the tube end.
– Sagging Ferrules
sag and result in compression of the ceramic fiber paper on the stem and creating a hot contact point which then induced hot sulphidation corrosion on the tube end.
– Insufficient Thermal Protection by Ferrules
to hot sulphidation on the tube end.
– Two Phase Process
Investigation Actions
(751) and February (754) 2016 had all ferrules removed and the tube-sheet cleaned of residual Sulphur (by hand-tools)
installation by the OEM
waste heat boilers)
2016 (752) and January 2017 (753)
Investigation Actions
to address the various possible mechanisms.
– Re-run of CFD analysis of tube-sheet lining design
– Review and revision of shutdown procedures
– A follow-up inspection of 751 was planned for February 2017 as there was inconclusive evidence to definitively support one mechanism over all others
Further Investigation Findings
October 2016 and January 2017 respectively.
developed as part of the investigation.
residual Sulphur in the furnace compared to 751 and 754 (original procedure).
could have been prevented and that the original procedure was not fit for purpose.
Further Investigation Findings
shutdown and inspected for a second time as per the follow-up actions.
relevant to the previous inspection and documented:
– Location of ferrules being removed (in clusters of 7 or 19 to maintain the ferrule wall) – Condition of the mastic and mortar (for poor quality in the installation or dislodgement through transient conditions) – Corrosion growth, cracking (circumferential or longitudinal)
Further Investigation Findings
duration of the investigation
Further Investigation Findings
– No residual Sulphur – Only 14 and 118 ferrules (out of 4,200 in each furnace) were found affected with corrosion scale at 6 o’ clock position – No correlation between the affected ferrules and their installation condition (i.e. poor grouting) – No correlation between the affected ferrules and the thickness of ceramic fiber paper wrap on the stem – All affected ferrules located at the top and bottom extremities and on the left hand side of the tube-sheet.
Further Investigation Findings
Failure Mechanism Analysis
follow-up inspection of 751 concluded the following:
Failure Mechanism Expected Observations Actual Observations Excluded or Accepted Hot Gas Bypass Wide-spread ferrule failure with increased hot sulphidation at tube end 98.4% of ferrules were notFailure Mechanism Analysis – Two Phase Process
– Starts with wet Sulphur corrosion where moisture condensed and collected (being coalesced by the ceramic fiber paper) at the tube end and in the presence of Sulphur after a shutdown of the unit to ambient conditions. – This results in a corrosion scale to grow which impregnated the ceramic fiber paper and the ceramic ferrule stem.
– After the furnace is then restarted, the corrosion scale deposit forms a thermal bridge allowing a heat transfer to the tube end and starts hot sulphidation corrosion. – The cracking in the ferrule stem was due to the dissimilar properties of thermal expansion between the ceramic stem and the impregnated scale which on cooldown resulted in mechanical stress from the scale “wedge” and caused the brittle ceramic stem to crack circumferentially.
Failure Mechanism Analysis – Two Phase Process
Unit in OperationNormal Running Conditions
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to AmbientShutdown follows procedure
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion ConditionsWhilst Shutdown
The wet Sulphur corrosion process is aggressive
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at FerruleCorrosion Scale Deposit Grows
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at Ferrule Unit Start-upNot Known That Wet Sulphur Corrosion Has Occurred
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at Ferrule Unit Start-upRunning Conditions Are Now:
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at Ferrule Unit Start-up Heat Conduction in Scale Hot Sulphidation at Tube EndHeat Conduction To Tube End
Heat Affected Zone
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at Ferrule Unit Start-up Heat Conduction in Scale Hot Sulphidation at Tube End Shutdown to AmbientShutdown follows procedure
Failure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at Ferrule Unit Start-up Heat Conduction in Scale Hot Sulphidation at Tube End Shutdown to Ambient Scale Wedge in Ferrule PresentDissimilar Thermal Expansion Properties Between
On Cooldown, Forces Act On Brittle Ceramic
Ceramic Stem Hex head Tube Tube-sheet Weld Ceramic Fiber Wrap Ceramic Fiber Gasket Scale Wedge Force ForceFailure Mechanism Analysis – Two Phase Process
Unit in Operation Shutdown to Ambient Wet Sulphur Corrosion Conditions Corrosion Growth at Ferrule Unit Start-up Heat Conduction in Scale Hot Sulphidation at Tube End Shutdown to Ambient Scale Wedge in Ferrule Present Ferrule Cracks due to StressResults In Circumferential Crack To Ferrule Stem
Conclusions
conditions found in the follow-up inspection was the “2-Phase Mechanism”
– The magnitude of the failures in each pair of furnaces correlates to the shutdown procedure and duration as well as time in service. – The reason for the minimal number of failed ferrules in the follow up inspection is assumed to be due to their location and the residual Sulphur had not been fully removed and resulting in further wet Sulphur corrosion prior to restart.
the ceramic ferrules) is robust and requires no modifications.
furnace will be taken to ambient conditions for any period of time.