Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January - - PowerPoint PPT Presentation

status report
SMART_READER_LITE
LIVE PREVIEW

Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January - - PowerPoint PPT Presentation

HIE-ISOLDE Project: Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January 2013 Yacine Kadi Phase 1 Updated Schedule 2013 2014 2015 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D LS1 &


slide-1
SLIDE 1

HIE-ISOLDE Project: Status Report

EXTRA COSTS AND ADDITIONAL RESOURCES

CERN, 29 January 2013 Yacine Kadi

slide-2
SLIDE 2

Phase 1 Updated Schedule

Initially planned to start in May 2015, the Physics Program at 5.5 MeV/u is now expected to start in October 2015. The above schedule is could be affected by unforeseen emergency activities that could arise during LS1. Reprioritization of phase 2 and 3 is unavoidable.

2

2013 2014 2015

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

LS1 & shutdowns Refurbishment of the old ALEPH Cryo-Plant Compressor installation and commissioning Cryo-plant installation (cold box and transfer line) Cryo-plant commissioning HIE-ISOLDE SC Linac Cryomodule 1 Tests (SM18) Cryomodule 2 Tests (SM18) Cryomodule 1&2 installation (ISOLDE) Cryomodule 1&2 Commissioning (ISOLDE) HIE-ISOLDE High-Energy Beam Transfer Lines Power converters installation & Commissioning Magnet installation & Commissioning BI installation & Commissioning (HW) Vacuum installation & Commissioning Beam commissioning (phase1) Start of the Physics at 5.5 MeV/u

2016 2017 2018

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

LS2 & shutdowns Physics at 5.5 MeV/u

slide-3
SLIDE 3

Cost: External Funding Phase 1

The missing income of 0.7 MCHF should be covered through new applications:

  • Belgian Big Science Project #2 through K.U. Leuven => Phase-2
  • Local funds from Sweden through U. Lund
  • COSA EU-FP7-ITN Innovative Doctoral Program 24 man x years

3 Expenses

  • Linac+HEBT

Procurement Salaries (*) R&D Total 2007-2012 604.000 1.226.000 2.023.837 3.853.837 2013-2015 5.000.000 100.000 5.100.000

  • 5.604.000

1.326.000 2.023.837 8.953.837

  • (*) to be considered additional expenses on salaries of 6.0 MCHF (2011-2014) already

covered by EU-FP7-ITN Marie-Curie program: CATHI

1.084.845

slide-4
SLIDE 4

CERN Extra Costs Phase 1

4

Department Group Material Personnel R&D Total BE RF 150.000 190.000 150.000 490.000 ABP 200.000 239.500 70.000 509.500 350.000 429.500 220.000 999.500 EN CV 727.000 727.000 EL 44.000 44.000 HDO 100.000 100.000 HE 120.000 120.000 ICE 200.000 200.000 STI 301.000 301.000 1.172.000 320.000 1.492.000 GS SEM 400.000 400.000 TE CRG

  • 2.023.000 (*)
  • 2.023.000

MPE 100.000 100.000 MSC1 250.000 250.000 MSC2 133.000 133.000 VSC1 310.000 150.000 460.000 VSC2 260.000 173.000 433.000

  • 1.380.000

583.000 150.000

  • 647.000

542.000 1.332.500 370.000 2.244.500

(*) re-use of ALEPH cryo-plant

slide-5
SLIDE 5

Missing Resources for Phase 1

5

For the CRYOMODULE: HR needs (8 man years) All of these needs (the 5 man years listed above) have been filled by redeploying personnel from other projects. However, a short-term (3 year LD contract) position is requested to ensure the continuation of the experienced Mechanical Engineer currently assigned to the HIE-ISOLDE project beyond July 2013.

slide-6
SLIDE 6

Missing Resources for Phase 1

6

For the CRYOGENIC PLANT: HR Needs (2.3 man years)

  • HR needs are estimated to a total of 8.3 man years for the period (2013-2015).

The need is for Engineers and technicians to be involved in “Cold box reinstallation” and “Compressor station reinstallation” mainly in the activities

  • f: Project engineer, Mechanics/drawing, Process control, Instrumentation and

Commissioning.

  • All of these needs but, 2.3 man years, have been secured for the project.

For the Beam Instrumentation: HR Needs (2 man years)

  • HR needs are estimated to a total of 2 man years during the period (2013-2015).

Two electronic engineers are needed for a period of 12 months to develop: (i) the front-end analogue electronics for the Faraday Cup (in intensity and profile measurement modes) and the Silicon detector and (ii) the motion control for the beam diagnostic boxes.

  • All of these needs will be filled by redeploying personnel from other projects.
slide-7
SLIDE 7

CRYOMODULE: Status

7 Done In progress Pending

Active components Mechanical & cryogenics interfaces Assembly procedures redaction, current leads Quench protection system, RF interfaces Alignment Concept and procedures Adjustment mechanism design Jacks procurement Detailed design, drawings of supporting frame assembly Vacuum Concept, interfaces, instru. and product identification Interfaces drawings Vacuum vessel drawings Procurement and contract follow-up Cryogenics Concept, procedures, reservoir drawings, instrumentation list Aleph fridge compatibility study Thermal shield specifications redaction Response to cryogenics stop scenario. Thermal shield drawings Survey Concept, interfaces Targets definition Detailed design of supports Assembly Concept, general assembly sequence Clean room procurement Detailed procedure redaction Tooling detailed design Instrumentation Requirements

  • Selection, procurement, installation

Safety Risk identification, calculations Products selection Procurement, installation Contracts follow-up

  • Adjustment mechanism, helium

reservoir Vacuum vessel, thermal shield, supporting frame, bellows, instrumentation, tooling

 General

Conceptual design 100%

Detailed design 60%

Detailed drawings 20%

Priorities

Start procurement processes for components requiring long delays

Validate last active components solutions

Instrumentation consideration

slide-8
SLIDE 8

Jan-12 Feb-12 Mar-12 Apr-12 May-12 Coating system Design and procurement of SS cavity support Resistive heating inside the antenna Coatings Q1_9 Q1_10 Q2_6 Q3_1 RF tests Q2_5 Q1_9 Q2_5 LNL coupler+ In Q1_10 Q1_10 CERN coup Q2_6

Cavity development work in 2012

Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Coating system Copper screens, IR lamps, 8 kW Power supply 12 kW PS Coatings Q1_11 QP1_2 Q3_2 Q2_7 Q3_3 RF tests Q3_1 Cryo SM18 downQ3_1 + Magnet Q1_11 QP1_2 Q2_7 Q3_3 CRYO OK 37 Tests RF 12 3.083 Weeks/test 2Weeks/cavity demonstrated

slide-9
SLIDE 9

Parameter/feature HIE ISOLDE cavity CERN ALPI cavity INFN-LNL Substrate treatment SUBU Tumbling, EP then SUBU Rinsing water pressure 5-6 bar 100 bar Bake out temperature 670ᵒC (~ sputtering T) 600ᵒC (>sputtering T) Sputtering temperature 450ᵒC 690ᵒC 300  500 ᵒC Sputtering pressure 3 10-1 mbar 2 10-1 mbar Number of layers 12 12-20 layers Power 2 kW11 kW 5 kW (for 2.5 times smaller surface) Cathode voltage 1 kV 1 kV Bias voltage

  • 80 V
  • 120 V

Total electrical energy 46 kWh 15 kWh Auxiliary electrode 2 cm diameter, bias potential 4 cm diameter (2/3 of inner conductor), rounded, bias potential Film minimum thickness To be measured 2 µm Sputtering gas Argon Argon Venting gas N2 N2 vacuum joint Viton CF

Cavity Test Results

slide-10
SLIDE 10

Comparison of HIE ISOLDE and ALPI QWRs

Data from Legnaro vertical test courtesy of Anna Porcellato The slope of our best cavities is independent

  • n Q0 and close to the best ALPI cavities

(rounded substrates) Q2_7 ranks 9th out of 13 in terms of Q0 and initial slope Looks as if we were entering the distribution

  • f the LNL cavities from below
slide-11
SLIDE 11

Summary

11

Most recommendations of the previous cavity review were implemented:

  • Reconsidered mechanical tolerances
  • 4 prototypes available since summer 2012
  • Focused on dc bias sputtering
  • Dummy copper cavity available and used for sample studies in autumn 2012
  • Increasing cavity turnaround up to 2 weeks
  • Setting up a backup test place in Orsay
  • Continuing work on cavity ancillaries (tuning plate, coupler, RF line)

Cavity performance improved significantly in one year:

  • 1 MV/m @ 10 W in September 2011
  • 5 MV/m @ 10 W in October 2012

Remaining issues for cavity performance

  • Film thinness on cavity top (high current region)
  • Bad film quality on tip of the inner conductor (peak E field emission)
  • Stability
  • Statistics
slide-12
SLIDE 12

12