Status of the Detector Control and Vacuum Systems PANDA - - PowerPoint PPT Presentation

status of the detector control and vacuum systems
SMART_READER_LITE
LIVE PREVIEW

Status of the Detector Control and Vacuum Systems PANDA - - PowerPoint PPT Presentation

Status of the Detector Control and Vacuum Systems PANDA Collaboration Meeting 18/1 Florian Feldbauer Ruhr-Universitt Bochum - Experimentalphysik I AG Current Setup in our Lab IOCs running on Single Board Computer (SBC) Structure in our lab


slide-1
SLIDE 1

Status of the Detector Control and Vacuum Systems

PANDA Collaboration Meeting 18/1

Florian Feldbauer

Ruhr-Universität Bochum - Experimentalphysik I AG

slide-2
SLIDE 2

Current Setup in our Lab

IOCs running on Single Board Computer (SBC) Structure in our lab according to final PANDA scheme

, 1

  • F. Feldbauer

DCS & Vacuum

slide-3
SLIDE 3

Current Setup in our Lab What is ready:

Power Supplies: HV, LV Vacuum System: Pumps, Gauges, Valves Cooling: Chiller, Temperature Sensors (THMP , PT100)

What is missing:

PLC for vacuum system (equipment safety) Linear Shift Mechanism: (Motor control, distance sensors) Modification of THMP Temp-PBB for NTC thermistor read-out MuPix configuration

, 2

  • F. Feldbauer

DCS & Vacuum

slide-4
SLIDE 4

Equipment Safety I

Electronics operated inside vacuum ⇒ only cooling by holding structure ⇒ Need to switch off LV and HV in case of failure of cooling Two PT100 per holding structure plus two on each PCB Comparing voltage drop over PT100 with reference voltage If temperature to high ⇒ emergency off signal for LV and HV signal is active low to be fail save

, 3

  • F. Feldbauer

DCS & Vacuum

slide-5
SLIDE 5

Differential Pumping Scheme

Thin transition foil ⇒ Vacuum in Box required Differential pumping to avoid large pressure differences Requirement

◮ Beam pipe: 1 · 10−9 mbar ◮ Vacuum box: 1 · 10−6 mbar

First test results

◮ Beam pipe: 6 · 10−8 mbar ◮ Vacuum box: 4 · 10−7 mbar ◮ Only turbo pumps , 4

  • F. Feldbauer

DCS & Vacuum

slide-6
SLIDE 6

Differential Pumping Scheme

Vacuum system attached to old prototype

, 5

  • F. Feldbauer

DCS & Vacuum

slide-7
SLIDE 7

Stress Test

First prototype measurements performed with manually

  • perated valves

Forgot to open valve BVvb between fore pump and turbo pump at vacuum box Glueing of beam pipe broke at downstream flange, foil undamaged

, 6

  • F. Feldbauer

DCS & Vacuum

slide-8
SLIDE 8

Control of Vacuum System Current status

Pumps and Gauges read out via RS485 bus Electro-pneumatic valves controlled via GPIOs from SBC

But: Controlling valves/pumps via multi-purpose OS is dangerous

Software might fail Processor might be blocked by other processes Valves might be opened/closed by other processes ⇒ Equipment Protection System (EPS) needed! Instead of controlling valves/pumps directly with EPICS use a PLC

, 7

  • F. Feldbauer

DCS & Vacuum

slide-9
SLIDE 9

Equipment Safety II Leakage in vacuum system

Inform accelerator crew Close quick-acting gate valves to HESR Open a bypass valve between Vaccum Box and Inner Beam Pipe

Power Outage

All valves currentless closed (except bypass) Large hose between compressed ait filters and manifold ⇒ reservoir Turbo pumps act as generator to safely shut down

, 8

  • F. Feldbauer

DCS & Vacuum

slide-10
SLIDE 10

Summary and Outlook

DCS is mostly finished and tested Setup according to PANDA scheme First parts of PLC for Vacuum System just arrived Test of Vacuum System with new Protoype to be performed very soon

, 9

  • F. Feldbauer

DCS & Vacuum

slide-11
SLIDE 11

Backup

, 10

  • F. Feldbauer

DCS & Vacuum

slide-12
SLIDE 12

When "vacuum goes bad"

Valve in beamline X-16 at NSLS. Probably around 1988

, 11

  • F. Feldbauer

DCS & Vacuum