Status of Sustainable Groundwater July 6, 2020 Management Act - PowerPoint PPT Presentation

Status of Sustainable Groundwater July 6, 2020 Management Act Implementation Technical Draft Recent Key Accomplishments Hydrogeological Conceptual Model Potential Groundwater Dependent Data Review and Assessment Tech


  1. Status of Sustainable Groundwater July 6, 2020 Management Act Implementation

  2. •Technical •Draft Recent Key Accomplishments Hydrogeological Conceptual Model •Potential Groundwater Dependent

  3. Data Review and Assessment • Tech memos describing data assessment, data gaps, recommendations for GW monitoring, Sampling and Analysis Six Month Plan (late 2020 or early 2021) Look Ahead Hydrogeological Conceptual Model • Final updates prepared • Future presentations will include 3D rendering Groundwater Model Update and Readiness • Peer review commencement • Technical memos prepared

  4. Groundwater Surface Water Interconnection • Efforts continue to gain site access and permissions for equipment installation (piezometers, water Six Month level data loggers and temperature probes) Look Ahead • In mean time- careful review of existing data from wells and preparation of a tech memo.

  5. Water Budget Development • Historical, current, and future water budgets will be prepared. Six Month Look Ahead

  6. Outreach • Completion of Workshop 5 on Groundwater/Surface Water Interaction Six Month • Pre workshop meeting of SAC, Workshop, post workshop meeting, Look Ahead completion of final outreach report • Completion of Workshop 6 on Water Budgets • Same meeting steps as above

  7. • Delays in implementing field work • Mitigate by preparation of a specific study of existing data, and more evaluation with groundwater flowmodel Challenges

  8. • Scope for GSP Technical Consultant has broadened- need for additional meetings, inefficiency related to COVID-19 delays, more detailed SAC and Workshop process. • SCV-GSA budget includes a 15% contingency Fiscal for GSP Technical Consultant ($187,733) • Staff evaluating workflow and cost options. • Anticipate special Board meeting to consider options to authorize use of contingency funds.

  9. • Significant work last quarter. • Schedule concern with field work being mitigated. Summary • Next six months including finalization of technical studies, ongoing robust SAC process and workshops

  10. • Questions?

  11. • Representative Work from Each Task for both GSI Water Solutions Inc. and CV Strategies Essential  Data Review and Assessment  Hydrogeological Conceptual Model Consultant  Groundwater Model Update and Readiness Work  Groundwater Surface Water Interconnection  Water Budget Development  Sustainable Management Criteria  Projects and Management Actions  Preparation of the Groundwater Sustainability Plan

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.